OM Sample Questions
OM Sample Questions
Management
Sample Questions :
Time-Function Mapping
Process Charts
Q3 :
Describe five or more ways in which a company Industry Differentiation Low Cost
can use operations to contribute to company’s
cost leadership strategy; use a specific example Ordinary
Courier DHL, FedEx, Speed Post
post
Credit cards Diners, American Express SBI, ICICI managing operations in different stages of Product Life
Hotel Taj, Westin Ginger cycle.
Challenges :
Increase capacity
Introduction :
Factory manager of a home appliances company 3. Balance the line by assigning specific assembly
is concerned about unbalanced work on the TV tasks to each workstation. An efficient balance is
assembly line. The assembly line has 10 activities one that will complete the required assembly,
and it takes 20 minutes to assemble a TV. follow the specified sequence, and keep the idle
time at each workstation to a minimum. A formal
Describe the steps to balance the assembly line.
procedure for doing this is the following:
The current daily requirement is 560 TVs. Show a. Identify a master list of tasks.
all calculations and draw appropriate network b. Eliminate those tasks that have been assigned.
diagram, layout, etc. c. Eliminate those tasks whose precedence
relationship has not been satisfied.
d. Eliminate those tasks for which inadequate
Assembly line balancing objective is to minimize time is available at the workstation.
work imbalance on the assembly line while e. Use one of the line-balancing “heuristics”
meeting required output. described in
Starts with the precedence relationships
Determine cycle time.
Calculate theoretical minimum number of
workstations.
Balance the line by assigning specific
tasks to workstations.
the times for each element measured, adjusted for
unusual influence for each element:
Manager can test several of these heuristics to see Normal time = Average observed time *
which generates the “best” solution—that is, the Performance rating factor
smallest number of workstations and highest
efficiency. Remember, however, that although = 1.5 , 2.07, 2.04, 3.5
heuristics provide solutions, they do not
guarantee an optimal solution. The performance rating adjusts the average
observed time to what a trained worker could
expect to accomplish working at a normal pace.
Q7:
7. Add the normal times for each element to
A hotel housekeeper was observed five times on develop a total normal time for the task.
each of four task elements, as shown in the
Total Normal time = 9.1
following table. On the basis of these
observations, find the standard time for the 8. Compute the standard time . This adjustment to
process. Assume a 10% allowance factor. Show the total normal time provides for allowances
all calculations. such as personal needs, unavoidable work delays ,
Performanc Observations (minutes per and worker fatigue :
Element e Rating cycle)
(%) 1 2 3 4 5 Standard time = Total normal time / (1 -
Check minibar 100 1.5 1. 1.4 1.5 1.5 Allowance factor)
6
Make one bed 90 2.3 2. 2.1 2.2 2.4 = 9.1 / (1-10%) = 10.1
5
Vacuum flour 120 1.7 1. 1.9 1.4 1.6
9 Averag
Clean bath 100 3.5 3. 3.6 3.6 3.2 No of Sum of the e Norm
6 observatio time observ al
ns recorded ed time time
1.Define the task to be studied (after methods
analysis has been conducted). 5 7.5 1.5 1.5
2. Divide the task into precise elements (parts of
5 11.5 2.3 2.07
a task that often take no more than a few 5 8.5 1.7 2.04
seconds). 5 17.5 3.5 3.5
Total normal
3. Decide how many times to measure the task time 9.1
(the number of job cycles or samples needed). Standard
time 10.1
4. Time and record elemental times and ratings of
performance.
Example 4
On the basis of the precedence diagram and
activity times given in Example 3 , Boeing
determines that there are 480 productive
minutes of work available per day. Furthermore,
the production schedule requires that 40 units of
the wing component be completed as output
from the assembly line each day. It now wants to
group the tasks into workstations.