Managing Risks in Complex Projects
Managing Risks in Complex Projects
Share
Share
Abstract
Introduction
Uncertainty is both a reality and great challenge for most projects (Hillson,
2010, ¶2). The presence of risk creates surprises throughout the project life
cycle, affecting everything from technical feasibility to cost, market timing,
financial performance, and strategic objectives (Loch, Solt, & Bailey, 2008,
p. 28; Thieme, Song, & Shin, 2003, p. 104). Yet, to succeed in today's
ultracompetitive environment, management must deal with these risks
effectively despite these difficulties (Buchanan, & O‘Connell, 2006, pp. 34–
35; Patil, Grantham, & Steel, 2012, pp. 35–40; Shenhar, 2001, pp. 394–410;
Srivannaboon & Milosevic, 2006, pp. 185–190). This concerns executives,
and it is not surprising that leaders in virtually all organizations, from
commerce to government, spend much of their time and effort to deal with
risks-related issues. Examples trace back to ancient times that include huge
infrastructure projects and military campaigns. Writings by Sun Tzu
articulated specific risks and suggested mitigation methods 2,500 years ago
(Hanzhang & Wilkinson, 1998). Risk management is not a new idea.
However, in today's globally connected, fast-changing business world with
broad access to resources anywhere, and pressures for quicker, cheaper,
and smarter solutions, projects have become highly complex and intricate.
Many companies try to leverage their resources and accelerate their
schedules by forming alliances, consortia, and partnerships with other
firms, universities, and government agencies that range from simple
cooperative agreements to “open innovation,” a concept of scouting for new
product and service ideas anywhere in the world. In such an increasingly
complex and dynamic business environment, risks lurk in many areas, not
only associated with the technical part of the work but also include social,
cultural, organizational, and technological dimensions. In fact, research
studies have suggested that much of the root cause of project-related risks
can be traced to the organizational dynamics and multidisciplinary nature
that characterizes today's business environment, especially for technology-
based developments (Torok, Nordman, & Lin, 2011). The involvement of
many people, processes, and technologies spanning different organizations,
support groups, subcontractors, vendors, government agencies, and
customer communities compounds the level of uncertainty and distributes
risk over a wide area of the enterprise and its partners, often creating
surprises with potentially devastating consequences. This paradigm shift
leads to changing criteria for risk management. To be effective, project
leaders must go beyond the mechanics of analyzing the work and its
contractual components of the “triple constraint,” such as cost, schedules,
and deliverables, but also understand the sources of uncertainty before
attempting to manage them. This requires a comprehensive approach with
sophisticated leadership, integrating resources and a shared vision of risk
management across organizational borders, time, and space. Currently, we
are good at identifying and analyzing known risks, but weak in dealing with
the hidden, less-obvious aspects of uncertainty (Thamhain & Skelton, 2007,
pp. 37–40). Yet, some organizations seem to be more successful than others
in dealing with the uncertainties and ambiguities of our business
environment, an observation that is being explored further in this field
study.
We Are Efficient in Identifying and Analyzing Known Risk Factors. With the
help of sophisticated computers and information technology, we have
become effective in dealing with risks that can be identified and
described analytically. Examples range from statistical methods and
simulations, to business case scenarios and user centered design. Each
category includes hundreds of specialized applications that help in dealing
with project risk issues, often focusing on schedule, budget, or technical
areas. Risk management tools and techniques have been discussed
extensively in the literature (Bstieler, 2005, pp. 267–280; Cooper, Grey,
Raymond, & Walker, 2005; Hillson, 2010, ¶2; Jaofari, 2003, pp. 47–52;
Kallman, 2006, p. 46). Examples include critical path analysis, budget
tracking, earned value analysis, configuration control, risk-impact matrices,
priority charts, brainstorming, focus groups, online databases for
categorizing and sorting risks, and sophisticated Monte Carlo analysis, all
designed to make project-based results more predictable. In addition, many
companies have developed their own policies, procedures, and management
tools for dealing with risks, focusing on their specific needs and unique
situations. Especially in the area of new product development, contemporary
tools such as phase-gate processes, concurrent engineering, rapid
prototyping, early testing, design-build simulation, CAD/CAE/CAM, spiral
developments, voice-of-the-customer, user centered design (UCD), agile
concepts and scrum have been credited for reducing project uncertainties.
Furthermore, industry-specific guidelines (i.e., DOD Directive 5000.1, 2007),
national and international standards (i.e., ANSI, CSA, ISO and National
Institute of Standards and Technology, 2000), and guidelines developed by
professional organizations (i.e., A Guide to the Project Management Body of
Knowledge (PMBOK® Guide)—Fifth Edition [Project Management Institute,
2013]), all have contributed to the knowledge base and broad spectrum of
risk management tools available today.
RQ1: How do contingencies impact project performance, and why does the
impact vary across different projects?
The work reported here is the continuation of ongoing research into risk
management practices and team leadership in complex project
situations(Skelton & Thamhain, 2007, pp. 36–47; Thamhain, 2011, pp. 40–
45). This article summarizes four years (2008–2011) of this investigation,
focusing on the risk management practices of 35 major product
developments in 17 high-technology, multinational enterprises with a
sample characteristics as summarized in Table 1.
Companies 17
Project teams 35
Team members* 489
Product managers 9
R&D managers 6
(months)
* Total team = Total team sample – project managers – product managers – R&D managers –
senior managers
Table 1: Summary of sample statistics
The current research uses an exploratory field study format with focus
on four interrelated sets of variables: (1) risk, (2) team, (3) team leader, and
(4) project environment. All these variables, plus the components of risk
management, product development, team work, technology, and project
management are intricately connected, representing highly complex sets of
variables with multiple causalities. Researchers have consistently pointed at
the nonlinear, often random nature of these processes (Bstieler, 2005, pp
267–284; Danneels & Kleinschmidt, 2001, pp 358–370; MacCormack, 2001,
pp. 22–35; Thamhain, 2009, pp. 20–30; Verganti & Buganza, 2005, pp. 225–
235). Simple research models, such as mail surveys, are unlikely to produce
significant results. Instead, one has to use exploratory methods, casting a
wide net for data collection, to look beyond the obvious aspects of
established theory and management practice. I used my ongoing work as
consultant and trainer with 17 companies to conduct discussions,
interviews and some surveys, together with extensive observations, all
helping to gain insight into the work processes, management systems,
decision making, and organizational dynamics associated with project risk
management. This method, referred to as action research, includes two
qualitative methods: participant observation and in-depth retrospective
interviewing. This combined method is particularly useful for exploratory
investigations, such as the study reported here, which is considerably
outside the framework of established theories and constructs (Eisenhardt,
1989, pp. 535–545).
The Questionnaire was designed to measure (1) risk factors, (2) frequency of
risk occurrences, (3) impact on project performance, and (4) managerial
actions taken to deal with contingencies (risks). To minimize potential
misinterpretations or biases from the use of social science jargon, each of
the 14 risk classes (e.g., summarized in Exhibit 3) was defined specifically at
the beginning of the questionnaire.
Data Analysis. The data collected via questionnaires were evaluated and
summarized via standard statistical methods, while content analysis was
used to evaluate the predominately qualitative data collected via work
process observation, participant observation and in-depth retrospective
interviewing.
Results
The findings of this field study are organized into three sections: First, a
simple risk assessment model for tracking the effects of risk on project
performance is presented. Second, the type of contingencies that typically
emerge during project execution are identified and examined regarding their
impact on project performance. Third, the managerial implications and
lessons learned from the broader context of the quantitative and qualitative
part of this study are summarized in two separate sections of this article.
“Risks do not impact all projects equally.” This observation from earlier
phases of this research is strongly supported by the formal results of this
field study. The managerial actions of dealing with the event, such as
eliminating or working around the contingency, greatly influence the ability
of minimizing the magnitude of problems caused and the cascading effects
that propagate through the organization. The dynamics of these processes is
being illustrated with the risk impact model in Exhibit 3, showing the
influences of the external and internal business environment.
The Model suggests that contingencies affecting one part of a project, have
the tendency to cascade throughout the project organization, with
increasingly unfavorable impact on project performance, and eventually
affecting the whole enterprise.
Based on the performance impact, the model identifies four distinct risk
categories:
Category-I No impact on project performance. Two types of risks fall into this
Risks category. First, events that might occur in the external or internal project
environment with potentially harmful impact on project performance in
the future. These contingencies, such as a delayed contract delivery,
labor dispute, technical issue, or priority change, are lurking in the
environment, whether they are anticipated or not. But, they have not yet
occurred, and therefore have not yet impacted project performance. By
anticipating these contingencies, management can take preventive
actions to mitigate the resulting impact if the event occurs. Second,
events that actually occurred were identified and dealt with before they
affected project time, cost, or other performance parameters.
Category-II Impact on task or project sub-systems only. The risk events have
Risks occurred in the external or internal project environment with potentially
harmful impact on project performance. However, by definition, these risk
issues occurred at a lower level of project activity, such as a task or sub-
system, and have not yet affected overall project performance. Examples
are delayed contract deliveries, labor disputes, technical issues, or
priority changes that can be solved “locally.” Although the resolution
might require extra time, it is not part of a critical path, and therefore the
performance impact is limited to a sub-set of the project. A similar
situation exists for issues that affect cost, quality, or other performance
parameters at the local level only. Thus, while these risks are expected to
impact the whole project, they have not yet affected overall project
performance. Therefore, timely managerial actions could minimize or even
avoid such performance impact.
Category- Impact on project performance. Events that occurred in the external or
III Risks internal project environment did impact project performance, such as
schedules, budgets, customer relations or technical issues. The impact
on project performance could have been a direct result of a contingency,
such as a failure to obtain a permit, or resulting from an issue at a lower
level, but propagating to a point that affects total project performance.
Examples are test failure on a critical activity path, or problems caused at
a lower level propagate to a point where they affect total project
performance. However, by definition, the impact is still contained “within
the project,” without affecting enterprise performance. Proper timely
management actions can lessen the impact on overall project
performance, and possibly minimize or avoid any harmful impacts on the
enterprise.
Category- Impact on project and enterprise performance. Events have
IV Risks occurred and have already significantly impacted overall project
performance and the performance of the entire enterprise. Similar to
Category-III, the effects could be immediate or cascading (i.e., Toyota's
“accidental acceleration”). Proper management actions can lessen the
final impact on both project and enterprise performance, but by
definition, a certain degree of irreversible harm has been done to the
project and the enterprise.
The field study provides an interesting insight into the cause and effect of
contingencies on project performance, including their dynamics and
psychology. Whether a risk factor actually impacts project performance
depends on the reaction of the project team to the event, as graphically
shown in Exhibit 2. It also seems to depend on the judgment of the manager
whether or not a particular contingency is blamed for subsequent
performance problems. Undesirable events (contingencies) are often caused
by a multitude of problems that were not predictable or could not be dealt
with earlier in the project life cycle. During a typical project execution, these
problems often cascade, compound, and become intricately linked. It is also
noticeable that the impact of risk on project performance seems to increase
with project complexity, especially technology content of the undertakings.
From the interviews and field observations, clearly even small and
anticipated contingencies, such as additional design rework or the
resignation of a key project team member, can lead to issues with other
groups, confusion, organizational conflict, sinking team spirit, and fading
commitment. All these factors potentially contribute to schedule delays,
budget issues, and system integration problems that may cause time-to-
market delays and customer relation issues, which ultimately affect project
performance. Realizing the cascading and compounding effects of
contingencies on project performance, the research emphasizes the
importance of identifying and dealing with risk early in the project life cycle
to avoid problems at more mature stages. The study also acknowledges the
enormous difficulties of actually predicting specific risk situations, their
timing, root-cause, and dysfunctional consequences, and to act
appropriately before they impact project performance.
Project leaders and senior managers differ in their “true cause” assessment
of performance problems, as was shown in the statistical analysis of Exhibit
3. Yet, there are additional implications to the perception of what causes
performance issues. These perceptions affect the managerial approaches of
dealing with risk. Specifically, we learn from the discussions and field
interviews that project leaders blame project performance problems and
failures predominately on contingencies (risk situations) that originate
outside their sphere of control, such as scope changes, market shifts, and
project support problems, while senior management points directly at
project leaders for not managing effectively. That is, senior management
blames project managers for insufficient planning, tracking and control,
poor communications, and weak leadership. Additional field investigations
show an even more subtle picture. Many of the project performance
problems and failures could be root-caused to the broader issues and
difficulties of understanding and communicating the complexities of the
project, its applications, and support environment, including unrealistic
expectations for scope, schedule, and budget, under funding, unclear
requirements, and weak sponsor commitment.
Lesson 7. Project leaders should have the authority to adapt their plans
to changing conditions. Projects are conducted in a changing environment of
uncertainty and risk. No matter how careful and detailed the project plan is
laid out, contingencies will surface during its execution that require
adjustment.
Conclusion
Risks do not affect all projects equally is one strong conclusion from this
field study. Actual risk impact does not only depend on the risk event, but
also on the managerial actions of dealing with the contingency and its
timing, which influence the magnitude of problems caused by the event and
the cascading effects within the project organization. The risk-impact-on-
performance model developed in this article contributes to the body of
knowledge by providing a framework for describing the dynamics and
cumulative nature of contingencies affecting project performance. The
empirical results show that effective project risk management involves a
complex set of variables, related to task, management tools, people, and
organizational environment. Simple analytical approaches are unlikely to
produce desired results, but need to be augmented with more adaptive
methods that rely on broad data gathering across a wide spectrum of the
enterprise and its environment. The methods also have to connect effectively
with the organizational process and the people-side of project management.
Some of the strongest influences on risk management seem to emerge from
three enterprise areas: (1) work process; (2) organizational environment; and
(3) people. I observed many approaches that effectively reduced risks by
simplifying the work and its transfer processes, shortening development
cycles, and testing project feasibility early. The best success stories of this
field study point at the critical importance of identifying and dealing with
risks early in the development cycle. This requires broad scanning across all
segments of the project team and its environment and creative methods for
assessing feasibilities early in the project life cycle. Many risk factors
originate outside the project organization, residing in the broader enterprise
and its environment. Therefore, it is important for management to foster an
organizational environment conducive to effective cross-functional
communications and collaboration among all stakeholders, a condition
especially important to early risk detection and risk management.
Cooper, D., Grey, S., Raymond, G., & Walker, P. (2005). Project risk
management guidelines: Managing risk in large projects and complex
procurements. Hoboken, NJ: Wiley.
Danneels, E., & Kleinschmidt, E. J. (2001). Product innovativeness from the
firm's perspective. Journal of Product Innovation Management, 18(6), 357–
374.
Hanzhang, T., & Wilkinson, R. (1998). The art of war. Hertfordshire, UK:
Wordsworth Editions.
Patil, R., Grantham, K., & Steele, D. (2012). Business risk in early design: A
business risk assessment approach. Engineering Management Journal,
24(1), 35–46.
Shenhar, A. J. (2001). One size does not fit all projects: Exploring classical
contingency domains. Management Science, 47(3), 394–414.
Skelton, T., & Thamhain, H. (2007). Success factors for effective R&D risk
management. International Journal of Technology Intelligence and Planning
(IJTIP), 3(4), 376–386.
Srivannaboon, S., & Milosevic, D. Z. (2006). A two-way influence between
business strategy and project management. International Journal of Project
Management, 24(2), 184–197.
Thieme R., Song, M., & Shin, G. (2003). Project management characteristics
and new product survival. Journal of Product Innovation Management,
20(2), 104–111.
Torok, R., Nordman, C., & Lin, S. (2011). Clearing the clouds: Shining a
light on successful enterprise risk management. Executive Report, IBM
Institute for Business Value, Somers, NY: IBM Global Services.
Verganti, R., & Buganza, T. (2005). Design inertia: Designing for life-cycle
flexibility in Internet-based services. Journal of Product Innovation
Management, 22(3), 223–237.