Project Engineering (Week 7) PERT, Difference Between CPM and PERT, Scheduling With Limited Resources, Multiple Project Scheduling
Project Engineering (Week 7) PERT, Difference Between CPM and PERT, Scheduling With Limited Resources, Multiple Project Scheduling
Project Engineering
Chapter 3
PROJECT PLANNING AND
SCHEDULING
Lecture 7 (Week 7)
Program evaluation and review technique
(PERT), Difference between CPM and
PERT, Project scheduling with limited
resources and Multi project scheduling
Learning Objective
The main objective of this lecture is to understand about:
Concept of Program evaluation and review technique (PERT).
Difference between CPM and PERT.
Project scheduling with limited resources.
Multiple project scheduling.
NUMERICAL EXAMPLE
Consider the following activities in a network.
• Determine expected completion time and critical path.
Prepared By: Associate Prof. Ishwar Adhikari/Department of Civil Engineering/Kathmandu Engineering
College (Affiliated to Tribhuvan University), Kathmandu, Nepal.
• Variance and standard deviation of the critical path
3
t= 1, 4, 7 t= 3.5, 4, 4.5
t=1, 2, 3
1 2 5 t= 2, 6.5, 8
6
t= 3,4,11 4 t= 5, 6, 13
PERT Average time / the most expected time (µ/te) = (to + 4tm + tp)/6
For Activity 1-2, te = (1+ 4*2+ 3) / 6 = 2
Standard deviation (σ) = t p-to/6 = 2/6 =1/3
Variance = σ2 = 1/9
Repeating the same process for all the activities.
S.N. Activity to tm tp te σ σ2 Remark
1 1-2 1 2 3 2 1/3 1/9 CP
2 2-3 1 4 7 4
3 2-4 3 4 11 5 4/3 16/9 CP
4 3-4 3.5 4 4.5 4
5 4-5 5 6 13 7 4/3 16/9 CP
6 5-6 2 6.5 8 6 1 1 CP
Expected Project Duration = Summation of expected time along critical path
= 2+5+7+6 = 20 days.
Variance of Project (σ2) = Summation of variance along CP
= 1/9 + 16/9 + 16/9 + 1 = 42/9
Standard Deviation (σ) = (42/9)1/2 = 2.16.
Here the critical path is: 1-2-4-7-9-11-12, with the duration of 19 days.
Resource Histogram
The graphical representation of the project resources with respect to time is called resource
histogram.
Here the mason limitation per day is 10 numbers and we can see clearly in the above
figure that the mason exceeds the limited number in the day 7 and 8.
To overcome this, we have to use the available float of the non-critical activity suitably.
We shift the activity 5-9 by seven days.