Equipment Installation Report

The report describes the installation of contingency air conditioning equipment in the FONAFE Computing Center by Clean Room & Validation SAC The technical characteristics of the supplied and installed equipment, the installation process, and recommendations are given for the maintenance of the equipment.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
64 views6 pages

Equipment Installation Report

The report describes the installation of contingency air conditioning equipment in the FONAFE Computing Center by Clean Room & Validation SAC The technical characteristics of the supplied and installed equipment, the installation process, and recommendations are given for the maintenance of the equipment.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

EQUIPMENT INSTALLATION REPORT

For : NATIONAL ACTIVITY FINANCING FUND

STATE BUSINESS COMPANY – FONAFE

Jorge Vera Flores

Of : CLEAN ROMM & VALIDATION SAC

Eng. Luis Calderon.

Reference : SUPPLY AND INSTALLATION OF CONTINGENCY AIR


CONDITIONING EQUIPMENT FOR THE FONAFE COMPUTER
CENTER

Date : July 13, 2016.

1.- GENERALITIES:

The Split Type Decorative Floor Ceiling air conditioning unit was installed and put into operation,

after the supply and installation service carried out in the month of July of this year, this report

will show the technical characteristics of the equipment. Finally, the respective observations and

recommendations will be given.

Av. La Marina 886 int. 15 - Pueblo Libre Tel . 51 (1) 346 0805 – www.cleanroomvalidation.com.pe
2 - SUPPLY AND INSTALLATION OF AIR CONDITIONING EQUIPMENT.

The conditioning, supply and installation of the equipment and accessories for the Ventilation
and Air Conditioning System, SUPPLY AND INSTALLATION OF A CONTINGENCY AIR
CONDITIONING EQUIPMENT FOR THE FONAFE COMPUTER CENTER, have been
carried out by the company CLEAN ROOM & VALIDATION SAC As described below.

1.- UC-01 CONDENSING UNIT

ACCORDING
DESCRIPTION CHARACTERISTICS
YEAH NO

- Guy VERTICAL √

- Brand York √

- Coolant R-22 √

- Ability 24,000 BTU/HR √

- Model YNVFYC024BBH-AX √

- Series 243502106160400083 √

- Function JUST COLD √

- Electrical Characteristics. 220V / 1Ø / 60Hz. √

2.- UE-01 EVAPORATOR UNIT

Av. La Marina 886 int. 15 - Pueblo Libre Tel . 51 (1) 346 0805 – www.cleanroomvalidation.com.pe
ACCORDING
DESCRIPTION CHARACTERISTICS
YEAH NO

- Guy FLOOR ROOF √

- Brand York √

- Ability 24,000 BTU/HR √

- Model XNFFXC024BBH--FX √

- Series 241801632141200028 √

- Function JUST COLD √

- Electrical Characteristics. 220V / 1Ø / 60Hz. √

3.- SYSTEM INSTALLATION

Av. La Marina 886 int. 15 - Pueblo Libre Tel . 51 (1) 346 0805 – www.cleanroomvalidation.com.pe
The installation of the equipment, and other parts, as a means of operation of the supply
and installation of contingency air conditioning equipment for the FONAFE
Computing Center.

a.- ELECTROMECHANICAL INSTALLATION OF EQUIPMENT.

- Transfer of the Equipment from CRV in Lima, to the FONAFE facilities located in the
San Isidro district.

- Location and assembly of the Equipment and other parts, as indicated by the client.

- Mechanical installation of high and low pressure copper pipes for R-22 refrigerant gas,
drainage pipe, metal supports, etc. As indicated by the client.

- Installation and route of the electrical control wiring from the equipment to the existing
equipment control panel.

- Power electrical connection of the equipment from the point delivered by the client.

- Rearrangement of existing luminaire

- Drywall work, putty, sanding and painting false beam to cover pipes.

- The connection and electrical installation of the thermostat as indicated by the client.

- Functional tests, final regulations and commissioning of air conditioning equipment.

Av. La Marina 886 int. 15 - Pueblo Libre Tel . 51 (1) 346 0805 – www.cleanroomvalidation.com.pe
4.- OBSERVATIONS AND RECOMMENDATIONS:

1. Carry out a general inspection of the installed equipment and the input voltage to said
equipment, for an overvoltage problem at least every month.

2. Have a preventive maintenance program, within which the cleaning of air filters is
specified.

3. Have a preventive maintenance program for the equipment every 6 months. During the
warranty period.

Sincerely,

Av. La Marina 886 int. 15 - Pueblo Libre Tel . 51 (1) 346 0805 – www.cleanroomvalidation.com.pe
Av. La Marina 886 int. 15 - Pueblo Libre Tel . 51 (1) 346 0805 – www.cleanroomvalidation.com.pe