P5-MRPS-L-0724 2024-3-29 Reply For Engineer's Determination of Extension of Time Claim
P5-MRPS-L-0724 2024-3-29 Reply For Engineer's Determination of Extension of Time Claim
P5-MRPS-L-0724 2024-3-29 Reply For Engineer's Determination of Extension of Time Claim
of Page: 4
FF27, 1st Floor, Main Bolevard Gulberg Date: March 25, 2024
III
Lahore, Pakistan 54600 Ref: P5-MRPS-L-0721
Tel: 0092 42 3575 1358/1359 Pls Contact: Mr. Yu Lin
Fax No.: Email: [email protected]
Subject Mangla Refurbishment Project, Package V, Balance of Plant
: Mechanical Works GMHD-05
The Engineer’s comments in letter [4] for our observations for the EOT in [5] has
been well reviewed and the Contractor prepared the comprehensive reply as below
for your confirmation and re-valuation of our EOT for Unit 5&6.
Ii Contractor’s Observation: “the Engineer has not used the approved baseline
schedule to work out the EOT which is a fundamental
tool to determine the delay time in any EOT case “and
“the approved Baseline Project Time Schedule, which
also became part of the Contract, is the most
appropriate schedule for the analysis and evaluation
of the EOT.”
Iii Contractor’s Observation: “if the Engineer is not fully convinced with the
consequential delay time of 268 days, the Contractor
may further explicate/demonstrate the claimed time
of 268 days.”
4.1 EVENT #1: SPREAD OF COVID-19 IN CHINA and 4.2 EVENT #2: SPREAD OF
COVID-19 IN PAKISTAN
Contractor’s Reply for Event As clarified in our previous letters, this is a generic
#1: description of the Covid-19 project in Pakistan and
China, where the actual impacts lasted for almost 2
years (over 700 days), and some impacts still exist
even today. At the time when Covid-19 is spread, if we
strictly followed the related SOP, it was not possible
for us to conduct any site works. As we expressed
previously, we did the best to start site works slowly at
the condition that the work efficiency is quite low.
4.1.2 (C) EVENT #1: COVID-19; EVENT #1.2: DESIGN DELAY DUE TO COVID-19
2020-03-26 关于疫情防控期间继续调减国际客运航班
量的通知
2020-06-04 民航局关于调整国际客运航班的通知
2021-04-28 民航局关于国际定期客运航班熔断措施调
整试行的通知
Contractor’s Reply: It is agreed that there shall be many reasons for the
over-time in delivery. As the Contractor’s scope is to
arrange the vessel from Shanghai seaport to Karachi
seaport, we have collected the detailed shipment
situation (please refer to the evidence document in
event 2). The customs clearance is in Employer’s
scope and we have no idea about the reason of the
delay in customs works. As the customs agency,
CRRK shall provide the explanation. The Contractor
shall be entitled to apply claim for the delay of the
shipment.
1. Detail Situation for Shipment
Reference Documents
2. Shipment Arrival P5-S003
3. Shipment Arrival P5-S005
4. P5-MRPS-L-0222 2021-04-07 Tax Exemption
Certificate P5-S006 & P5-S010
5. Shipment Arrival P5-S009
6. P5-MRPS-L-0217 2021-03-25 Custom Clearance
for Shipment P5-S011 P5-S012 P5-S013
7. Demand No. MRP-16
8.Request for the clarification of the customs
clearance delays-2024.3.22
Contractor’s Reply: In the Project Programme, not all the items are listed.
At the kick-off meeting, we have requested the
document and information from the Engineer and
reminded for many times, which shall be deemed as
Contractor’s hint to the programme (no reply
received).
Contractor’s Reply: For the interface work, the contractor has signed a
daily Daywork sheet with MRPS's site engineer
representative. Please refer to attached document.
Contractor’s reply We assume the Engineer has agreed with our claim
for 19 days under this event.
Reference Documents
In view of our further explanations and clarifications above, the Contractor has
provided full and complete supporting document to clearly explain our
application for extension of time for completion unit 5&6 works in our scope.
However, as per our understanding, the Engineer insisted that the Contractor
has not provided concrete evidence for the EOT claim. Therefore, we would
like to call a meeting to discuss the EOT items and better explain our reply, so
that this EOT could be earlier approved.
Your Sincerely.
Yu Lin
Project Manager