Environmental Impact Assessment (Eia) : Screening
Environmental Impact Assessment (Eia) : Screening
Environmental Impact Assessment (Eia) : Screening
❖ Screening
This step categorizes projects and determines whether a full-scale environmental impact assessment is
required or not. The output from the screening process is often a document called an Initial
Environmental Examination or Evaluation (IEE). The main conclusion will be a classification of the
project according to its likely environmental sensitivity.
Screening Stage
Different types of tools used during the screening method are:
1. Inclusive project list (projects must undergo EIA) and exclusive project list (projects exempted from
EIA)
2. Case-by-case examinations to determine whether projects may have significant environmental effects.
if so, the project should undergo EIA
❖ Scoping
Scoping is the process of determining the most critical issues to be considered and this step will involve
community participation to some degree. It establishes the content and scope of an EIA report. It is at
this early stage that EIA can most strongly influence the outline proposal. Two major types of scoping
method are closed scoping and open or public scoping.
76
1. Closed scoping
In this method, the content and scope of an EIA Report is pre-determined by law and modified through
closed consultations between a developer and the competent authority.
The scoping process begins with the preparation of a scope outline through informal consultation with
environmental and health authorities. The outline is then made available for the public and is compiled
with an extensive list of concerns, which is followed by the evaluation of relevant concerns to establish
key issues. The key issues are further organized into impact categories and the outline is amended
accordingly. A ‘Terms of reference’ (ToR) is then developed for impact analysis and the progress is
monitored. If necessary, revising is carried out. Another major activity of scoping is to identify key interest
groups (both governmental and non-governmental) and to establish good lines of communication.
❖ Impact Analysis
In this phase, the likely impacts are analyzed in greater detail in accordance with the terms of reference
specifically established for this purpose. Impact analysis is conducted using various tools, such as
checklists, matrices, networks, overlays and geographical information systems (GIS), expert systems, and
professional judgment.
Type Biophysical, social, health or economic
Nature Direct or indirect, cumulative, etc.
Magnitude High, moderate, low
Extent Local, regional, trans-boundary or global
Timing Immediate/long term
Duration Temporary/permanent
Uncertainty Low likelihood/high probability
Reversibility Reversible/irreversible
Significance Unimportant/important
• Checklists
Checklists are comprehensive lists of environmental effects and impact indicators designed to stimulate
the analyst to think broadly about possible consequences of contemplated actions. There are four types
of checklist:
1. Simple checklist
A list of environmental parameters with no guidelines on how they are to be measured and interpreted.
2. Descriptive checklist
This method involves the identification of environmental parameters and guidelines on how to measure
data on particular parameters.
77
3. Questionnaire
This is based on a set of questions to be answered. Some of the questions may concern indirect impacts
and possible mitigation measures. They may also provide a scale for classifying estimated impacts from
highly adverse to highly beneficial.
• Matrices
Matrices are two-dimensional tables that facilitate the identification of impacts arising from the interaction
between project activities and specific environmental components. The entries in the cell of the matrix
can be either qualitative or quantitative estimates of impact. The three important types of matrices used
in EIA are:
1. Magnitude Matrices
Go beyond the mere identification of impacts according to their magnitude, importance, and time frame
(e.g., short, medium or long term)
2. Quantified Matrix
Leopold Matrix is one of the best-known types of quantified matrix. It was developed by Leopold et al.
for the US geological survey. This matrix is based on a horizontal list of 100 project actions and a vertical
list of 88 environmental components.
78
3. Weighted Matrix
In this method, Importance weightings are assigned to environmental components, and sometimes to
project components. The impact of the project (component) on the environmental component then
assessed and multiplied by the appropriate weightings.
• Network
The network is an alternative for illustrating the secondary and subsequent effects of actions on
environmental elements. This method involves the construction of a network tracing such effects. The
advantage of a network approach is that it permits clear tracing of high-order effects of initial actions;
indeed, mitigation and control measures can also be illustrated.
Sorenson network is probably the best-known approach used to illustrate and understand primary,
secondary and tertiary impacts of developmental activity. It also identifies feasible mitigation measures
and assesses multiple impacts at the same time. However, the applications of the Sorenson network are
limited by inadequate data availability and reference networks relevant to the local environment.
Battelle Environmental Evaluation System is designed to assess the impacts of water resource
development projects, water quality management plans, highways, nuclear power plants, and other
projects. In an Environmental Evaluation System, the major concerns are separated into four categories:
Ecology, Physical/chemical, Aesthetics and Human Interest, and Social. Each category is further broken
down into a number of environmental components and for each component, an index of environmental
quality normalized to a scale ranging from 1 to 10 is developed. Environmental Indicator is defined as
the difference in environmental quality between before and after the impact states. Each environmental
component has a weighting factor (relative importance). From this, the overall impact of the project is
calculated by summing the weighted impacts indicators.
❖ Impact Mitigation
Mitigation measures are considered after environmental impact evaluation. An important outcome of
this stage will be recommendations for mitigating measures. This would be contained in the
Environmental Impact Statement. Clearly, the aim of this stage will be to introduce measures that
minimize any identified adverse impacts and enhance positive impacts. Even measures that are not
economically viable should not be dropped out, because, in the long run, they make the project both
economically and environmentally viable.
• Contingent Valuation
This approach involves asking people to directly report their willingness to pay (WTP) for the use or
conservation of natural goods. In other words, it is a method of estimating the value that a person places
on a good.
❖ Decision-making
The decision is taken by a manager or a committee, or personnel from the concerned ministry who had
not been associated with the EIA during its preparation. In general, the decision-maker has three choices:
The comprehensive EIA report incorporates the data of all four seasons of a year. Whereas, Rapid EIA
(i.e. completed within 3 months) has only one season data. It should be noted that the Environmental
Ministry has recently diluted the comprehensive EIA policies, therefore, in most cases only Rapid EIA
is required. The completed report is then submitted to the regulatory agency to decide if the project may
go for formal EIA or not.
Screening is the primary stage of EIA to decide if the project requires EIA or not. Based on the
government rules, the existing projects are generally categorized into two.
• All new National Highways are classified as Category A. In addition, expansion of National
Highways greater than 30 KM, involving additional Right of Way (ROW) greater than 20m,
involving the land acquisition and passing through more than one State are categorized as
Category A.
81
• Crude oil refineries and installations for the gasification and liquefaction of 500 tonnes or more
of coal or bituminous shale per day.
• Thermal power stations and other combustion installations (including cogeneration) with a heat
output of not less than 300 megawatts (equivalent to the gross electrical output of 140 MWe for
steam and single-cycle gas turbines power stations) and nuclear power stations and other nuclear
reactors.
• Construction of airports with a basic runway length of 2,100 meters or more.
• Waste-processing and disposal installations for the incineration, chemical treatment or landfill
of hazardous, toxic or dangerous wastes.
• Large dams and other impoundments designed for the holding back or permanent storage of
water.
• Industrial plants for the production of pulp, paper, and board from timber or similar fibrous
materials.
• Municipal wastewater treatment plants with a capacity exceeding 150,000 population
2. Category B projects (with potentially less significant impacts) are evaluated and given clearance by
state-level authorities, the State Environment Impact Assessment Authority (SEIAA) and State Expert
Appraisal Committee (SEAC). Under Category B projects, there was only one distinction—coal and non-
coal mines—with all non-coal mine leases below 50 ha clubbed under Category B. Environmental
clearance (EC) is compulsory for mining of minor minerals in areas less than or equal to five hectares
Category B projects are further categorized as ‘B1’ and ‘B2’ (except for township and area development
projects). The MoEF is assigned the task of issuing appropriate guidelines from time to time for such
projects.
The projects categorized as B1 require an EIA report for appraisal and also have to undergo a public
hearing process. But those falling under B2 are exempted from requirements of both EIA and public
consultation. If the project clears the screening stage, the developer will have to conduct a Preliminary
Assessment, which will predict the extent of the impacts and would briefly evaluate the importance for
decision-makers. After reviewing the preliminary report, the competent authority will decide if there is a
need for comprehensive EIA or Rapid EIA.
Scoping is an important stage prior to the main EIA process. During scoping, the study team interacts
and engage in discussions with various stakeholders, such as developers, investors, regulatory agencies,
scientific institutions, local people, etc. The numerous concerns and issues raised by different
stakeholders will be investigated and addressed by the study team. Then the team would select primary
impacts for the main EIA to focus and determine detailed and comprehensive Terms of Reference
(ToR).
It is during Main EIA stage that the key impacts on the environment, such as changes in air quality, noise
levels; impacts on wildlife, impact on biodiversity, impact on local communities’ settlement patterns,
changes in employment statistics, changes in water consumption and availability, etc., are formally
identified. It is followed by “prediction” in which the impacts are characterized quantitatively as well as
82
qualitatively. The predicted adverse impacts are then evaluated to determine if they can be significantly
mitigated. This stage also involves estimating mitigation costs and benefit-cost analysis.
Once the above-mentioned procedures are over, the next part is documentation, which is called the EIA
report. The report contains an executive summary of the project. The project developer would now
submit 20 copies of the executive summary to SPCB (State Pollution Control Board). It is now the
responsibility of the SPCB to conduct public hearing.
The Public hearing is organized within 30 days after the release of official notification at the site or in its
close proximity for ascertaining concerns of local stakeholders. SPCB fixes a date for Public Hearing
and informs the proponent to advertise in the local newspapers inviting the public for the hearing. Once
the hearing is completed, the SPCB forwards the minutes of the hearing along with the No objection
certificate to MoEF. In MoEF, the application is evaluated by an Impact Assessment Agency (IAA). The
IAA has the complete right of entry and inspection of the sites or factory premises prior to, during or
after the commencement of the project. The team carries out a technical assessment and gives its
recommendations within 90 days. On the basis of this, the MOEF grants the environmental clearance
which is valid for a period of seven years for the commencement of the project.
Under the Environment Protection Act, 1986 of India, notification was issued in February 1991, for the
regulation of activities in the coastal area by the Ministry of Environment and Forests (MoEF). As per
the notification, the coastal land up to 500m from the High Tide Line (HTL) and a stage of 100m along
banks of creeks, estuaries, backwater, and rivers subject to tidal fluctuations is called the Coastal
Regulation Zone (CRZ). Under this regulation, coastal areas have been classified as CRZ-1, CRZ-2, CRZ-
3, CRZ-4.
83
CRZ-1: These ecologically sensitive areas are essential in maintaining the ecosystem of the coast. They
lie between low and high tide lines. Exploration of natural gas and extraction of salt is permitted.
CRZ-2: These areas are urban coastal areas. As per CRZ, 2011 Notification, for CRZ-II (Urban) areas,
Floor Space Index (FSI) or the Floor Area Ratio (FAR) had been frozen as per the 1991 Development
Control Regulation (DCR) levels. In the CRZ, 2018 Notification, it has been decided to de-freeze the
same and permits FSI for construction projects, as prevailing on the date of the new notification. This
will enable the redevelopment of these areas to meet emerging needs.
CRZ-3: Rural and urban localities that fall outside the CRZ1 and CRZ2. Only certain activities related to
agriculture and some public facilities are allowed in this zone. Two separate categories have now been
stipulated as below:
(a) CRZ-III A – These are densely populated rural areas with a population density of 2161 per square
kilometer as per the 2011 Census. Such areas shall have a No Development Zone (NDZ) of 50 meters
from the HTL as against 200 meters from the High Tide Line stipulated in the CRZ Notification, 2011,
since such areas have similar characteristics as urban areas.
(b) CRZ-III B – Rural areas with a population density of below 2161 per square kilometer as per the
2011 Census. Such areas shall continue to have an NDZ of 200 meters from the HTL.
CRZ-4: This zone lies in the aquatic area up to territorial limits. Fishing and allied activities are permitted
in this zone. Solid waste should be let off in this zone. This zone has been changed from 1991
notification, which covered coastal stretches in islands of Andaman & Nicobar and Lakshadweep.
2. Temporary tourism facilities are also now permissible in the "No Development Zone" (NDZ) of the
CRZ-III areas as per the Notification. However, a minimum distance of 10 m from HTL should be
maintained for setting up of such facilities.
3. CRZ Clearances streamlined: The procedure for CRZ clearances has been streamlined. Only such
projects/activities, which are located in the CRZ-I (Ecologically Sensitive Areas) and CRZ IV (area
covered between Low Tide Line and 12 Nautical Miles seaward) shall be dealt with for CRZ clearance
by the Ministry of Environment, Forest and Climate Change. The powers for clearances with respect to
CRZ-II and III have been delegated at the State level with necessary guidance.
4. A No Development Zone (NDZ) of 20 meters has been stipulated for all Islands: For islands close to
the mainland coast and for all Backwater Islands in the mainland, in wake of space limitations and unique
geography of such regions, bringing uniformity in treatment of such regions, NDZ of 20 m has been
stipulated.
5. Pollution abatement has been accorded special focus: In order to address pollution in Coastal areas,
treatment facilities have been made permissible activities in CRZ-I B area subject to necessary safeguards
and precautions.
84
Environmental Audit
Environmental auditing is a management tool intended to provide information on environmental
performance to the concerned people at the right time. This audit includes an analysis of the technical,
procedural and decision-making aspects of the EIA. It also encompasses all kinds of activities related to
the environmental measures of an organization.
85
Auditing Action
Eco-mark Logo
An earthen pot symbolizes the Eco-mark scheme that uses renewable resources like earth, which does
not produce hazardous wastes and consumes less energy in making. The Central Pollution Control
Board has set up guidelines for environmentally friendly products. These products can obtain
environmental labeling from the Government of India if they meet the criterion set by the acts in Indian
laws.
▪ "Screening", investigation of whether the plan or programme falls under the SEA legislation,
▪ "Scoping", defining the boundaries of investigation, assessment and assumptions required,
▪ "Documentation of the state of the environment", effectively a baseline on which to base
judgments,
▪ "Determination of the likely (non-marginal) environmental impacts", usually in terms of
Direction of Change rather than firm figures,
▪ Informing and consulting the public,
▪ Influencing "Decision taking" based on the assessment and,
▪ Monitoring of the effects of plans and programmes after their implementation.