01 Flow Process Chart VSM IDEF0 With Solutions
01 Flow Process Chart VSM IDEF0 With Solutions
of Production System
Lesson 01: Formalisms for manufacturing process
modeling
[email protected]
Importance of formalism
● Problem of making
customers/colleagues
with different
backgrounds to
understand the process
to reach the solution of a
problem
Metaphor of the
swing
Problem of using
words to describe
processes
Importance of being
able to formalize a
process to have an
effective
communication
Importance of processes in production systems
Input Output
Process
Many variants
The same formalism may be used to represent different process
types
Flow chart
Activity
Decision
Input/output data
Flow control
Example: Customer support service
UML Activity Diagram
Initial state
End state
Activity
Decision
Flow control
Example: order management
Business process model and notation
start end
Analyzing the material flow, you can see that the shape quality
rejection rate is very high
A simple improvement could be to introduce an inspection
immediately after the manufacture of the cookies, before baking,
since the raw dough is easier to re-mix
With a successive intervention, the mixing and molding processes
can be improved to further reduce the rejection rate
Example: reengineering comparison
Example: packaging process
Example: chair assembly
Template
Exercise: paper factory
The wood is partly purchased from a supplier and partly produced in the
company's own forests. The wood is conveyed through an artificial channel to
the covered storage area. From there, it is taken to be cut in the chipper, where
the dimensions are made uniform to the standard size of 1x1/4 inch. Wood
chips that are too large are returned to the previous station, and those that are
too small are removed. The chips are then stored in silos.
Lignin is removed from wood chips by boiling them in caustic soda and sodium
sulphide solution. Then the chips pass into a low-pressure discharge vat which
physically separates the fibres. The wood fibres are then centrifuged and
pressed. The pulp produced in this process is finally subjected to bleaching and
then put to rest in the warehouse.
The paper is produced starting from the pulp in a dedicated machine, in which
the pulp is deprived of part of its content in water and compressed in steam-
heated cylinders. Then it is wrapped in large reels and stored. When delivered
to the customer it is cut and rewound into smaller reels.
Solution
Value Stream Mapping (VSM)
The manufacturing
process mapping is
performed using a
series of simple unified
icons
Safety Stock
• It represents the presence of voluntary stocks
• It must always be distinguished from the
(involuntary) accumulation of WIP generated by the
production system.
Truck Shipment
• It represents the transportation adopted 1 x day
• Internally the frequency of supplying and/or delivery
is brought
Material Flow
Striped arrow
• Represents the material flow between two stations
• Indicates a "Push" type flow
White arrow
• Represents the movement of raw materials from
suppliers
• Represents the movement of finished products
towards customers
Information Flow
Straight arrow
• Manual information flows (fax, e-mail, telephone,
etc.)
Lightning arrow
• Electronic information flows
Information Label
• Specify the type of information Schedulazione
• It is shown above the arrows of the information flow settimanale
Operator
The Timeline shows the overall Lead Time given by the sum
of the processing, handling and waiting times.
The low line means that the product is within the process, and it
will be worked for different time (it is the time in which the product
is processed on the machine)
In the high part of the line are indicated the waiting times
VSM design
I 1 1 1 1 1 I
coils 2700L
4 days 1440R
Z/T: 1S
C/T: C/T: 39 Ss
Z/T: Z/T:
C/T: 46
46 Ss Z/T: 62 Ss
C/T: Z/T:
C/T: 40
40 Ss
R/T: 60
C/O: 60 Min.
Min. R/T:
C/O: 10
10 Min.
min. C/O: 10
R/T: 10 Min.
min. R/T: 00 Min.
C/O: min. R/T:
C/O:00Min.
min.
V: 85 % 80%
Uptime: Uptime:
V: 10090%
% Uptime:
V: 80 %
80% Uptime:95%
V: 100 % V: 100 %
Uptime:95%
Q:
FTY:
0,01
0.9% A FTY:
Q: 0,80.9
%A Q: 0,20.85
FTY: %A FTY:
Q: 1,20.95
%A Q: 0,30.95
FTY: %A
Information 2 shift 2 shift 2 shift 2 shift 2 shift
Collection for
Data Box
VSM design
daily
R/T: 60
C/O: 60 Min.
Min. R/T: 10
C/O: 10 Min.
min. R/T: 10
C/O: 10 Min.
min. R/T:
C/O:00Min.
min. R/T:
C/O: 00 Min.
min.
FTY.:
V: 85 80
%% FTY.:
V: 10090%% V: 8080
s. r.: %% V:r.:
s. 100100
%% V: 100
s. r.: %%
100
Rejt:
Q: 0,01
0,01
%A%A Q: 0,8 % A Q: 0,2 % A Q: 1,2 % A Q: 0,3 % A
AZ/S:480Min
WT/S:480Min AZ/S:480Min
WT/S:480min AZ/S:480Min
WT/S:480min AZ/S:480Min
AZ/S:480Min
WT/S:480min AZ/S:480Min
WT/S:480min
S: 2 S: 2 S: 2 S: 2 S: 2
VSM design
• 3. Time information
• Timeline Design XYZ AG
customer
Krupp -Stahl
supplier
• Cycle Time, Waiting Time e Lead time 18400 pcs / month
150 ft coils 12000 L
6400 R
1Tray = 20 pieces
AZ/S: 480 min
S: 2
Mo +&Mi
We
daily
täglich
W/T: 23,6 d
5 days 7,6 days 1,8 days 2,7 days 2,0 days 4,5 days
1s 39 s 46 s 62 s 40 s
P/T: 188 s
VSM design
FIRM
● Acme Spa pressed steel steering arms
● The firm produces 2 types of products → L (left side)
and R (right side)
● Each month has 20 working days, in 2 shifts of 8
hours each and two breaks of 10 minutes for each
shift
CLIENT
● Client demand18.400 p/month:
L → 12.000 [p/ month]
R → 6.400 [p/month ]
● Shipments to customers are made 1 time per day
Example
PRODUCTION CONTROL
● The production control is carried out by MRP which
provides forecasts at 90, 60 and 30 days
● Every day the customer provides orders with the
desired quantities
● The production is managed through a weekly
schedule
● The MRP forecasts with 6-month horizon sent to the
supplier
● Acme sends orders to the supplier weekly
SUPPLIER
● The supplier supplies 500 feet long steel coils twice
a week, transporting them by truck
● The coils supplied allow you to have material in the
initial warehouse for 5 day
Example
PROCESSES
● The flow between the various phases of production are of push type
● 6 processes:
Stamping
Process time= 1 s
Setup time = 1 h
Uptime = 85%
Observed warehouse= 4600 L e 2400 R
Welding 1
Process time= 38 s
Setup time = 10 m
Uptime = 100%
Observerd warehouse= 1100 L e 600 R
Example
Welding 2
Process time = 45 s
Setup time = 10 m
Uptime = 80%
Observed warehouse = 1600 L e 850 R
Assembly 1
Process time = 61 s
Setup time = 10 m
Uptime = 100%
Observed warehouse = 1200 L e 640 R
Example
Assembly 2
Process Time = 39 s
Setup time = 0
Uptime = 100%
Observed Warehouse = 2700 L e 1440 R
Shipment
after assembly the product is shipped to the customer
Example - solution
Operator Availability
48
Example - solution
49
Example - solution
Draw the icons for the external handling connections (raw material and finished products) from the
warehouse to the Customer and from the Supplier. Represent the mode of transport used (e.g., Truck 50
shipment) and indicate the frequency of shipments (daily, etc.). Draw the icons representing manual and/or
electronic information and communication flow, describing the function/content with the Information icon.
Example - solution
Compute the total Value Added Time and Production Lead Time
Exercise
FIRM
● TWI produces components for tractors, in
particular steering arms
● Each month has 20 working days, consisting
of 2 shifts of 8 hours each, with two breaks
of 15 minutes for each shift.
CUSTOMER
● Demand of 24,000 pcs/month
● Shipments to customers are made 1 time a
day by trucks
Exercise
PRODUCTION CONTROL
● The customer provides a 60 day purchase forecast, and
a precise order schedule two weeks before delivery
● The production is managed through a weekly schedule
● Orders received are insert into the MRP system
● Every day a delivery plan is generated for the shipping
department
SUPPLIER
● The company purchases steel bars and raw joints from
two suppliers, Michigan Steel and Indiana Castings.
● Both suppliers make deliveries 2 times a month, and
guarantee an initial stock for 20 days.
● bar cutting and the joint trim are done in parallel, then
the two components are welded and continue the
processing.
Exercise
PROCESS DATA ● 2° Welding
1 operator
CT = 30s, C/O = 1h
● Bar cutting
Reliability = 80%
1 operator
Warehouse: 3 days of welded arms
CT = 15s, C/O = 1h
Reliability = 100% ● Deburring
Warehouse: 5 days of cutted bars 1 operator
CT = 30s, C/O = 1h
● Finishing
Reliability = 100%
1 operator
Warehouse: 5 days of welded arms
CT = 30s, C/O = 2h
Reliability = 100% ● Painting (outsourcing)
Warehouse: 5 days of finished bars Lead-Time = 2 days
Warehouse: 6 days of painted arms (TWI)
● 1° Welding
1 operator ● Assembly
CT = 30s, C/O = 1h 6 operators
Reliability = 90% CT = 195s, C/O = 10 min
Warehouse: 3 days of welded arms Reliability = 100%
Warehouse: 4 days of finished arms
● Shipping
Solution
Operator availability
Wheeled cabinets,
Solution (A0)
Wheeled
cabinets
Solution (A1)
Wheeled
cabinets
Exercise: Car repair shop
Process plan
Process
definition
Production
planning
Production plan