02 Introduction Factory Models With Solutions NEW
02 Introduction Factory Models With Solutions NEW
of Production System
Lesson 2: Introduction to Factory Models
[email protected]
Factory model
• Notational distinction
• average factory cycle time denoted as CTs
• average cycle time at workstation I, denoted as CT(i)
• CTs: average time that a job spends within the factory, either
being processed at a workstation or waiting in a workstation
queue;
• CT(i): average time jobs spend being processed by
workstation i plus the average time spend in the workstation i
queue (or buffer)
• CT: used for general properties related to the average cycle
time will be developed
Cycle time
CT(i) =CTq(i)+E[Ts(i)] ,
● The area, AB, between the curves A(t) and D(t) for a < t <
b is merely the summation given in the above equation.
This area can also be obtained by standard integration
methods as
WIP =λ×CT
DATA
• WIP = 25 pcs
• rate = λ = 4 pcs/hr
14.5
• E[T𝑆] = 14.5 min = = 0.24 hrs
60
• CTq = ?
λ TH = λ
WS
Exercise 1 – Solution
• 𝑆ℎ𝑖𝑓𝑡 = 24 ℎ𝑟𝑠/𝑑𝑎𝑦
10
• 𝑟𝑎𝑡𝑒 (𝜆) = 10 𝑝𝑐𝑠/𝑑𝑎𝑦 = 𝑝𝑐𝑠/ℎ𝑟 = 0.417 𝑝𝑐𝑠/ℎ𝑟
24
• 𝐶𝑇1 = 4.2 ℎ𝑟𝑠
• 𝐶𝑇2 = 5.3 ℎ𝑟𝑠
WS 1 WS 2
Exercise 2 – Solution
Critical parameters:
• rb = 1 pcs/2h = 0.5 pcs/g
(max utilization ≡ min capacity)
• T0 = 2h*4 = 8h
(sum of process times on machines)
• W0 = rb*T0 = 0.5*8 = 4 pcs
1 1 2
2 2 5
3 6 10
4 2 3
Example: not balanced production line
Machine
capacity WS capacity
Work Station Machines Process time
(inverse of (pcs/h)
process time)
Critical parameters:
• rb = 0.4 pcs/h (WS2 capacity: not WS3 with
slower machines and not WS1 with smaller
number of machines)
• T0 = 20 h (sum of process times)
• W0 = 0.4*20 = 8 pcs (it is smaller than the
number of machines, because some station
won’t be completely used)
HAL – Large Panel Line Processes
Data:
• Average process rate (number of panels/h)
• Average process time (h) at each station
min
j/min
j
Solution
CT TH