Using an AC circuit tester, test for proper phase and ground continuity on all circuits.
Reason:
https://public-library.safetyculture.io/products/factory-acceptance-template?amp_dev=0244d120-2a46-4e2e-b7e9-36b05edabf67 1/12
6/28/24, 5:35 AM Factory Acceptance Template - SafetyCulture
Reason:
Start
Finish
Test the run time on all battery backup (UPS) units with all of the required components
connected. Note actual run time before power failure.
Audio Test
All outboard equipment shall be set up, wired and tested according to the audio flow
diagrams.
Reason:
Load project media, created per the final specification, in to all devices.
Reason:
Load DSP files, created per the final specification, in to all devices.
Reason:
Set all processors with external level controls to 0dBu @ 1k. No other audio or control
connections should be attached to the processor at this time.
Reason:
Adjust amplifier dip switch settings to the appropriate voltage, resistance and mode.
Reason:
Using the Audio Precision APX515 signal generator and analyzer, sweep and record each
line using tones ranging from 20Hz-20kHz, testing for proper level, phase, crosstalk,
THD and noise.
Reason:
Reason:
Download the project's DSP file and test for proper routing and functionality.
Reason:
Perform an audible test on each line and test for signal quality from the source
equipment through to the amplifier output.
Reason:
Video Test
All outboard equipment shall be set up, wired and tested according to the video flow
diagrams.
Reason:
6/28/24, 5:35 AM Factory Acceptance Template - SafetyCulture
Using generated color bars (from a CD, color bar generator, or generated from source
equipment), visually check each line for clarity, from the source equipment, through to
the monitor.
Reason:
Load project media, created per the final specification, in to all devices.
Reason:
Using media, created per the final spec, visually check each line for signal clarity, from
the source equipment through to the monitor.
Reason:
All outboard equipment shall be set up, wired and tested according to the control flow
diagrams.
https://public-library.safetyculture.io/products/factory-acceptance-template?amp_dev=0244d120-2a46-4e2e-b7e9-36b05edabf67 5/12
6/28/24, 5:35 AM Factory Acceptance Template - SafetyCulture
Reason:
Load a control program, created per the final specification, in to the control systems and
touch screens. Check for proper continuity and routing functions to all devices.
Reason:
With the fire mute closure activated, check that all applicable equipment has been
muted and emergency paging is routing correctly.
Reason:
Network Test
All equipment shall be set up, wired and tested according to the network flow diagrams.
Reason:
Using a cable tester, test all network cables for proper pinout, continuity, signal power
and quality.
https://public-library.safetyculture.io/products/factory-acceptance-template?amp_dev=0244d120-2a46-4e2e-b7e9-36b05edabf67 6/12
6/28/24, 5:35 AM Factory Acceptance Template - SafetyCulture
Reason:
Test communication and function to all devices with Ethernet and Cobranet
connections.
Reason:
Reason:
Reason:
Appearance
All wires are accurately labeled, with labels visible from the standing position, without
having to twist the wires.
https://public-library.safetyculture.io/products/factory-acceptance-template?amp_dev=0244d120-2a46-4e2e-b7e9-36b05edabf67 7/12
6/28/24, 5:35 AM Factory Acceptance Template - SafetyCulture
All equipment is accurately labeled, with device ID on both the front and rear.
Reason:
All AC plugs are properly labeled, with labels visible from the standing position, without
having to twist the wires.
Reason:
All terminal and barrier strips are tightened down and the wires have been pulled for
verification of the connection.
Reason:
Equipment racks are neatly dressed, with wire tray covers on.
https://public-library.safetyculture.io/products/factory-acceptance-template?amp_dev=0244d120-2a46-4e2e-b7e9-36b05edabf67 8/12
6/28/24, 5:35 AM Factory Acceptance Template - SafetyCulture
Reason:
Rear doors (and front doors, where applicable) are placed on the equipment racks.
Reason:
SDB and SBB panels have been loaded with terminal blocks, labeled, repackaged and
placed back on the job shelf.
Reason:
Documentation
Create a tab in the corresponding POM for the serial numbers and fill in completely.
Reason:
Hand over the fabrication as-built drawings to the Design Engineer for review and
approval, then to the CAD department for revisions.
https://public-library.safetyculture.io/products/factory-acceptance-template?amp_dev=0244d120-2a46-4e2e-b7e9-36b05edabf67 9/12
6/28/24, 5:35 AM Factory Acceptance Template - SafetyCulture
Reason:
Load the latest version of all audio and video media files and control programs on to a
CD. Label the CD with file names, versions and date of transfer. Place the CD in the file
folder on the rear door of the head-end rack.
Reason:
Print an 11x17 set of fabrication as-built drawings and place them in the file folder on
the rear door of the head-end rack.
Reason:
Print two sets of field labels and place them in the file folder on the rear door of the
head-end rack.
Reason:
Print the line reference spreadsheet and corresponding sweep documentation from the
audio, video, control and network tests and place them in the file folder on the rear
door of the head-end rack.
https://public-library.safetyculture.io/products/factory-acceptance-template?amp_dev=0244d120-2a46-4e2e-b7e9-36b05edabf67 10/12
6/28/24, 5:35 AM Factory Acceptance Template - SafetyCulture
Reason:
Reason:
Hand over FAT documentation to the Project Manager, and post to the project folder.
Reason:
Verify all final punch list items have been fixed and documented, then handed over to
the Project Manager and Site Supervisor.
Reason:
The Project Manager and the Fabrication Manager shall provide to the Warehouse
Manager a list and cost estimate of all equipment and parts that will ship to the job site.
https://public-library.safetyculture.io/products/factory-acceptance-template?amp_dev=0244d120-2a46-4e2e-b7e9-36b05edabf67 11/12
6/28/24, 5:35 AM Factory Acceptance Template - SafetyCulture
Reason:
Completion
This factory acceptance template has been completed to the satisfaction of all parties.
The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's
solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice.
You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should
independently determine whether the template is suitable for your circumstances.
https://public-library.safetyculture.io/products/factory-acceptance-template?amp_dev=0244d120-2a46-4e2e-b7e9-36b05edabf67 12/12