Catch Up Timeline - Google Sheets 4
Catch Up Timeline - Google Sheets 4
PROJECT LOCATION B4 L27 BORA BORA BEACH DRIV PROJECT START 9/11/2023
DISPLAY WEEK 2
PROJECT ARCHITECT KRISTINE MACALINAO
PROJECT MANAGER KRISTINE MACALINAO 3/4/2024 3/11/2024 3/18/2024 3/25/2024 4/1/2024 4/8/2024 4/15/2024 4/22/2024 4/29/2024 5/6/2024 5/13/2024 5/20/2024
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
TASK PROGRESS START DAYS END M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
TINSMITHRY
Fabrication and Installation of Tubular
0% 5/17/2024 9 5/25/2024
Canopy
Fabrication and Installation of Additional
0% 5/18/2024 5 5/22/2024
Ladder
Fabrication and Installation of Metal
0% 5/3/2024 7 5/9/2024
Fence
Fabrication and Installation of Metal
0% 5/10/2024 7 5/16/2024
Gate and Hardwares
Structural Roof Framing (Truss) 100% 3/15/2024 7 3/21/2024