Method Statement
Method Statement
Method Statement
PROJECT DESCRIPTION
This method statement is proposed for the planning and implementation of the tender for the
CONSTRUCTION OF AP OFFICE AT KAKONKO VILLAGES KAKONKO
AP – KIGOMA CLUSTER with tender no. FEI/TC/01/Y24 which is expected to start on 12th
July 2024 and end on 12th September 2024.
PROJECT TEAM
The team which will be responsible for the construction of the AP office at Kakonko villages
Kakonko ap – Kigoma cluster will comprise the following members
1. Project manager: Eng. Joan Jesse
2. Site engineer: Eng Joseph Lukwi
3. Site foreman.
4. Electrical engineer: Eng. Nicholaus Kimaro.
5. Plumber.
6. Driver.
7. Safety officer.
MATERIALS
Materials that are going to be used will be about the provided specifications and conditions. The
materials required for the execution of the project are
Sand
Aggregates of the recommended size
Cement
Paints
Wood
Water
Steel bars
PLANT TOOLS AND EQUIPMENT
The followings are the tools and equipment that are going to be used to execute the project under
a given condition
Dumping trucks
Inspection vehicle
Concrete mixer
Porker vibrator
Various hand tools (spades, shovels, handsaw, hammer etc)
Surveying and leveling equipment (Dumpy level)
ACTIVITIES TO BE EXECUTED
S/N OPERATION SEQUENCE OF OPERATION TOOLS AND LABOUR
EQUIPMENT
1 Survey and Survey points shall be marked in Total station 1. Site
setting out either direction of the alignment. /theodolite engineer
A benchmark shall also be /Dumpy level 2. Site
established nearby where no from control foreman
disturbance will occur throughout the points 3. 3 unskilled
execution phase. labours
The benchmark shall be checked at
frequent intervals.
The foundation shall be marked on
the ground with the clearance of
formwork space required.
2. Excavation and The excavation shall be done with Hand tools such 1. Site
earthworks safe side slopes per ground as spades, foreman
conditions, and sufficient margin for shovels 2. 10
the minimum working area shall be unskilled
left (500mm). labours
Proper hand tools will be used in
excavating and removing the soil
from the work area.
10. Painting works The finishing process requires Hand tools such 1. 6 skilled
meticulous preparation. First, all dust as paintbrush, labour
and dirt must be removed, and any sandpaper 2. 6 unskilled
joint treatment needs to be labour
completely dry. Then, a multi-step
process of applying joint compound,
embedding joint tape, sanding, and
applying a final coat ensures a
flawless finish ready for painting
according to the manufacturer's
instructions
11. External works Construction of septic tank and soak
away pits.
The construction of the septic tank and soak
away pit will follow a well-defined
sequence, prioritizing safety and adherence
to regulations. Initial steps involve site
excavation based on approved plans,
ensuring proper dimensions, and maintaining
safe working conditions. The excavated
materials will be stockpiled for potential
backfilling or disposal. Following
excavation, the focus will shift to
constructing the tank and soak away pit
using approved materials and techniques, as
outlined in the relevant engineering
specifications. in-situ casted concrete will be
used. Strict quality control measures will be
implemented throughout the process to
guarantee a watertight and functional septic
system
QUALITY CONTROL AND QUALITY ASSURANCE
Quality Control
To maintain Quality Control, the following procedures and processes will be adhered to ensure
that quality is being achieved.
Personnel Qualifications
Assigning qualified full-time personnel trained and experienced in managing and
executing quality assurance and quality control procedures similar in nature and extent to
those required for the contract.
Submittal Procedure
The procedures for ensuring compliance with requirements through review and management of
the submittal process shall be adhered to as described in the Quality Control Plan. The
qualifications of personnel responsible for submittal review are indicated in the FPL
ENGINEERING INVESTMENT Control Plan as well.
Quality Assurance (QA)
Testing and Inspection
Performing tests and inspections including third party-performed tests and inspections.
Special inspections required by authorities having jurisdiction and indicated on the
Specifications and special conditions of the contract.
Samples of materials and finished work shall be subjected to testing by relevant
laboratories for quality assurance.
Continuous Inspection of Workmanship
The process for continuous inspection during construction to identify and corrective
actions for deficiencies in workmanship shall be implemented to bring work into
compliance with standards of workmanship as per the contract requirements.
Monitoring and Documentation
The testing and inspection reports including log of approved and rejected results shall be
maintained and recorded. The corrective actions taken to bring nonconforming work into
compliance with requirements are carried out and recorded.
Reports from approved lab for testing will be presented to the Client and included in the
progress reports.
Reports and Documents
Test and Inspection Reports: The test and inspection reports are prepared, certified and
submitted to the Client or their representatives. The reports include following:
Date of issue.
Project title and number.
Name, address, and telephone number of testing agency.
Dates and locations of samples and tests or inspections.
Names of individuals making tests and inspections.
Description of the work and test and inspection method.
Identification of product and specification section.
Complete test or inspection data.
Test and inspection results and an interpretation of test results.
Record of temperature and weather conditions at time of sample taking and testing and
inspecting.
Comments or professional opinion on whether tested or inspected Work complies with
the
Contract Document requirements.
Name and signature of laboratory inspector.
Recommendations on retesting and re-inspection.
Permits, Licenses, and Certificates
The copies of permits, licenses, certifications, inspection reports, releases, jurisdictional
settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar
documents should be submitted to the employer for their record and review.
HEALTH AND SAFETY PROCEDURE
All staff will be trained on safety and environmental matters before the commencement
of the work.
A first aid kit shall be maintained at the site.
All tools and equipment shall be well maintained and checked for safety compliance.
Toolbox training shall be conducted as per engineer instructions and record kept at the
site.
Health and accident logs shall be present at the site and incidents will be recorded on a
daily basis.
All persons accessing the site will be required to wear PPEs
Relevant signs will be kept in place during the whole period of implementation
The PPE’s will be available site are safety boots, reflector, helmet, ropes, safety googles, gloves
and respiratory protection masks.