ECM442 Lecture 5 Preparation of BQ - NE
ECM442 Lecture 5 Preparation of BQ - NE
ECM442 Lecture 5 Preparation of BQ - NE
Taking off
Abstracting
1. List down all works related to the project and refer to any standard method of
measurement (SMM) for example:
Piling – Refer to CESMM for piling
Excavation – Refer to CESMM earthwork class
Pile Cap construction – Refer to CESMM concrete class
Descriptions- Each item should be described in detail enough to enable anyone reading the bill of quantities is
able to locate the item in the works.
Excavation : Cubic
Brickwork : Cubic
Accuracy - It is usually necessary to re-measure civil engineering works when they are completed to
determine the exact value of the work, and therefore it is not necessary to calculate the quantities
too accurately when preparing the bill.
Writing Bill Of Quantity
Numbering – All items should be measured consecutively page by page
In building work the most usual practice is to letter the item alphabetically on each page to
Avoid the use of large number.
For example, the third item on page 20 of the bill of quantities. Would be referred to as item
20/C (page 20 item C ).
Abbreviations -The following abbreviations are often used on the dimension sheet :
Bwk : Brickwork
C.I : Cast iron
M.S : Mild steel
R.C : Reinforced concrete
P.C : Prime cost
L.S : Lump sum
Thk : Thickness
Ex : Excavation
Abbreviations are acceptable in the dimension sheet but should never be used in the bill
of quantities except for quantity units.
Writing Bill Of Quantity
Units of measurement
Cubic cu
Square sq
Linear in
Milimetre mm
Metre m
Kilometer km
Kilogram kg
Hectare ha
A complete set of bill of quantities
It is necessary to make provision for a daywork evaluation of work which cannot be assessed at
bill rates. CESMM provides three alternative procedures :
• A list of the various classes of labor, material and plant for which daywork rates or prices
are to be inserted by the tenderer.
• Provision for payment at the rates and prices and prices and percentage variations
contained in the current federation schedules of daywork.
• The insertion of provisional sums in the bill of quantities for work executed on a daywork
basis comprising separate items for labor, materials, plants etc.
Section D – Work Items
Part 1 : General Item
i)Prime Cost Items
-Shall be inserted in BOQ under General Items (Class A) to cover work carried out by
nominated sub contractors.
- A prime cost sum is an allowance, usually calculated by the cost consultant, for the
supply of work or materials to be provided by a sub-contractor or supplier that will be
nominated by the client - that is, a supplier that is selected by the client to carry out an
element of the works and imposed on the main contractor after the main contractor has
been appointed.
-work or materials by a specialist contractor or statutory body, e.g. gas, electricity, water
and sewer connections.
ii)Provisional sums
- A provisional sum is an allowance, usually estimated by a cost consultant, for a
specific element of the works that is not yet defined in enough detail for tenderers to
accurately price.
- Shall be used to cover contingencies of various types and they can be entered in
various section of the BOQ for subsequent adjustment.
- Is a monetary amount for work for which the full extent or character cannot be
determined precisely at the time of preparing tender documents.
Provisional quantites- cannot be determined precisely at the time of preparing tender
documents. (subjected to remeasurement)
Provisional Sum Example
Provisional sum items shall be added in the separate bill called Provisional sums or Prime
cost and Provisional sums in the Bills of Quantities.
1. Construction of the below-ground drainage system. (When there are no tender drawings)
2. Landscaping works
3. Road marking for car park
Quantity column and rate columns are usually not filled in this bill section. In the unit
column, “Pro Sum” or “Item” can be used as a unit.
In the amount column, the consultant will add a rounded provisional amount based on the
experience or previous records of projects.
Section E – General Summary
DEC 2016
Past Year Questions
JULY 2017
Past Year Questions
JAN 2018
JUNE 2018
Past Year Questions
DEC 2018
DEC 2019