Drainage Design Report
Drainage Design Report
Drainage Design Report
CONTENTS
3- APPENDICES
Design Report (B+G+M+3+P) MIXED USE COMMERCIAL & RESIDENTIAL BUILDING
DRAINAGE SYSTEM
Drainage System
This part shall be related to the sanitary fixtures drainage up to existing drainage network in the
project.
1. There shall be two pipes system used one for waste and another for soil serving the sanitary
fixtures up to the risers and /or manholes.
2. There shall be vent stacks to keep positive pressure inside traps throughout the system for
avoiding any bad smells or odors may be transferred through these traps inside building.
3. All foul drainage pipe internal network routes shall be discharge to building external manholes
{with double seal cover to avoid any bad smells from them} which shall be connected to the
existing drainage network inside the project, or to a holding tank {if required}.
4. Underground drainage pipes from the building to the manhole shall be UPVC to bs 4660 with
push fit polypropylene flexible joints.
5. Above ground drainage pipes shall be UPVC to BS4514 for sizes of 75mm dia and above with
solvent weld joints for size up to and including 50mm dia. pipes shall be ABS /UPVC/MUPVC
toBS5245/5255 suitable for high temperature.
6. Floor gullys shall be 100mm dia. UPVC with a 75mm dia. Deep seal trap. Provision for back
inlet connection a grating and a blank cover to engineer’s approval.
7. Wash hand basin, sink, bathtub, shower, etc connection shall be provided with a 75mm deep
seal trap.
8. All internal waste pipes to be bracketed at minimum centers of 1 meter.
9. Outlet and adapters shall be fitted to ensure that correct air and water seal is to be attained.
Design Report (B+G+M+3+P) MIXED USE COMMERCIAL & RESIDENTIAL BUILDING
1. The internal drainage routes sizes shall be designed in accordance to the flow and velocity
inside pipes which shall be decided in accordance to the drainage fixture unit load {DFUL}.
2. a) 50/75mm pipe min.slope of 2℅with minimum velocity of flow 2 FT/S to achieve scouring
action.
. b) 110/160mm pipe min.slope of 1℅ with minimum velocity of flow 2 FT/S to achieve scouring
action.
3. A/C condensate discharge pipes shall be upvc pipes insulated by fiber glass pipes
4. MATERIAL SCHEDULE FOR UPVC PIPES AND FITTINGS:
UPV Pipes and Fittings – Below ground, Inside building, SDR (41)
Specified Proposed
1 Standard BS 4660 BS 4660 / BS EN 1401
2 Pipe sizes – Range From Dia 110mm and above
3 Fittings – Type Rubber Ring Joints
4 Area of Application Below ground soil, Rain Water
Below ground of UPVC Pipes and fittings – External surface Water, SDR (41)
Specified Proposed
1 Standard BS 4660 BS EN 1401
2 Pipe sizes – Range From Dia 110mm and above
3 Fittings – Type Rubber Ring Joints
4 Area of Application Below ground soil and ventilation, Rain Water
Sanitary drainage design shall be based on the fixture unit method. The weight in fixture units
for various fixtures shall be as tabulated here below in accordance with National Plumbing
Code Handbook
Design Report (B+G+M+3+P) MIXED USE COMMERCIAL & RESIDENTIAL BUILDING
Design Report (B+G+M+3+P) MIXED USE COMMERCIAL & RESIDENTIAL BUILDING
Design Report (B+G+M+3+P) MIXED USE COMMERCIAL & RESIDENTIAL BUILDING
• System Philosophy
1- The project area has not external municipality storm network to allow for external discharge.
In addition, it is not allowed to drain storm water out of the project area.
2- The system operation philosophy is to drain the storm water from reservoirs roofs by gravity to
a holding tank proposed in the basement floor through piping network. The flooded water on the
ground surface will be drained into the road gullies located in the edge of the internal plot area
of the project. The gullies drain directly to soak away via piping network.
3- rainwater pipes shall be provided on the edge of building, horizontal pipes are not allowed.
The holding tank is designed for duration of 24hrs of rainfall. In case of excess of rainfall than
24hrs duration the system shall be emptied by a private tanker.
The holding tank volume is calculated by considering the various parameters of plot like area
draining, rainfall depth, runoff coefficient and climate change factor.
• Rainfall intensities
The Intensity Duration Frequency curves developed by the Qatar University using A.S. Bazaraa& S.
Ahmed formula are used for the pipe work design. Based on these curves the work of Bazaraa & Ahmed
derived the following formula for predicting rainfall intensity.
i = C Trm/ (t+d) n
Where
I = rainfall intensity (mm/hr)
t = storm duration (minutes) which is considered time of concentration
Tr= return period of storm.
And C, m, n and d are fitting parameters which to date have been given the following values:
C = 410
m = 0.206
n = 0.787
d = 10
The IDF curves based on the work by Qatar, outlining rainfall intensities (mm/hr) for varying storm
durations (5 mins to 24 hrs) and return periods (2 to 50 years).
Design Report (B+G+M+3+P) MIXED USE COMMERCIAL & RESIDENTIAL BUILDING
Figure (1-1) shows the standard I.D.F curves as per Qatar Sewerage and Drainage Design Manual –
Volume III – Storm Water Drainage.
Table 1-1 is showing the Levels of Flood Protection Required for various areas in Qatar. The selection of
storm returned period is a function of the piping network performance referring to ASHGHAL design
manual, the following table illustrates the storm return period for different type of land use.
Event Area
Parks, playgrounds, natural areas and minor
1 in 2 Years Storm
roads
1 in 5 Years Storm Low cost housing, major roads
Government, institutional and other official
development, technically sensitive property,
1 in 10 Years Storm
basements, power equipment, ….etc High cost
housing
1 in 25 Years Storm
High prestige or ceremonial developments
• Runoff Coefficients C:
Run-off coefficients are assigned to different categories of catchments within the Project area according
to Qatar Drainage Design Manual volume 3 as indicated in the below table 1-2.
• Pipe Material
UPVC pipes will be used for the gravity drainage pipelines, due to its availability and good
resistance to aggressive groundwater conditions.
• Pipe Diameter
The minimum UPVC pipe diameter used for connecting gullies is 200 mm
• Planning
The total area is required to be drained including roads and roof Building, Road gullies are
designed to collect the storm water and are draining via a gravity network system to holding
tank.
Design Report (B+G+M+3+P) MIXED USE COMMERCIAL & RESIDENTIAL BUILDING
Appendices: -
Appendix-A
SEWERAGE CALCULATION SHEET
Appendix-B
SUMP PIT CALCULATIONS
Appendix-C
SURFACE WATER HOLDING TANK CALCULATIONS
Appendix-D
SOAK AWAY CALCULATIONS
Appendix A
Sewerage Calculations
Definitions:
-Waste branch size will be 2 inch (50 mm) (table 710.1(2)) international plumping code.
So, waste branch (1) size will be 2 inch (50mm) which means that the 4 inch (110mm) waste branch size we
considered is more safe.
-waste stack (1) size will be 3 inch (80 mm) (table 710.1(2)) international plumping
code. So, waste stack (1) size will be 3 inch (80mm) which means that the 4 inch (110mm) waste stack
size we considered is more safe.
-soil stack (1) size will be 3 inch (80 mm) (table 710.1(2)) international plumping
code. So, soil stack (1) size will be 3 inch (80mm) which means that the 4 inch (110mm) waste stack
size we considered is more safe.
Riser (07,10,11,12,13,14,15,15a,16,16a,17,18,19,29,32,33,34,35)
-Waste branch size will be 2 inch (50 mm) (table 710.1(2)) international plumping code.
So, waste branch (1) size will be 2 inch (50mm) which means that the 4 inch (110mm) waste branch size we
considered is more safe.
-waste stack (1) size will be 3 inch (80 mm) (table 710.1(2)) international plumping
code. So, waste stack (1) size will be 3 inch (80mm) which means that the 4 inch (110mm) waste stack
size we considered is more safe.
-soil stack (1) size will be 2.5 inch (65 mm) (table 710.1(2)) international plumping
code. So, soil stack (1) size will be 2.5 inch (65mm) which means that the 4 inch (110mm) waste stack
size we considered is more safe.
-Waste branch size will be 1.5 inch (32 mm) (table 710.1(2)) international plumping code.
So, waste branch (1) size will be 1.5 inch (32mm) which means that the 4 inch (110mm) waste branch
size we considered is more safe.
-waste stack (1) size will be 1.5 inch (32 mm) (table 710.1(2)) international plumping code.
So, waste stack (1) size will be 1.5 inch (32mm) which means that the 4 inch (110mm) waste stack size we
considered is more safe.
-Waste branch size will be 1.5 inch (32 mm) (table 710.1(2)) international plumping code.
So, waste branch (1) size will be 1.5 inch (32mm) which means that the 4 inch (110mm) waste branch
size we considered is more safe.
-waste stack (1) size will be 1.5 inch (32 mm) (table 710.1(2)) international plumping
code. So, waste stack (1) size will be 1.5 inch (32mm) which means that the 4 inch (110mm) waste stack
size we considered is more safe.
-Waste branch size will be 1.5 inch (32 mm) (table 710.1(2)) international plumping code.
So, waste branch (1) size will be 1.5 inch (32mm) which means that the 4 inch (110mm) waste branch
size we considered is more safe.
-waste stack (1) size will be 2 inch (50 mm) (table 710.1(2)) international plumping
code. So, waste stack (1) size will be 2 inch (50mm) which means that the 4 inch (110mm) waste stack
size we considered is more safe.
Soil Stack (1)
- No of fixture unit load for soil stack (1) = 4 x 3 =12 f.u.l
-soil stack (1) size will be 2.5 inch (65 mm) (table 710.1(2)) international plumping
code. So, soil stack (1) size will be 2.5 inch (65mm) which means that the 4 inch (110mm) waste stack
size we considered is more safe.
-Waste branch size will be 1.5 inch (32 mm) (table 710.1(2)) international plumping code.
So, waste branch (1) size will be 1.5 inch (32mm) which means that the 4 inch (110mm) waste branch
size we considered is more safe.
-waste stack (1) size will be 2.5 inch (65 mm) (table 710.1(2)) international plumping
code. So, waste stack (1) size will be 2.5 inch (65mm) which means that the 4 inch (110mm) waste stack
size we considered is more safe.
-soil stack (1) size will be 3 inch (80 mm) (table 710.1(2)) international plumping
code. So, soil stack (1) size will be 3 inch (80mm) which means that the 4 inch (110mm) waste stack
size we considered is more safe.
-Waste branch size will be 2.5 inch (65 mm) (table 710.1(2)) international plumping code.
So, waste branch (1) size will be 2.5 inch (65mm) which means that the 4 inch (110mm) waste branch
size
we considered is more safe.
-Waste branch size will be 2 inch (50 mm) (table 710.1(2)) international plumping code.
So, waste branch (1) size will be 2 inch (50mm) which means that the 4 inch (110mm) waste branch size we
considered is more safe.
-waste stack (1) size will be 3 inch (80 mm) (table 710.1(2)) international plumping
code. So, waste stack (1) size will be 3 inch (80mm) which means that the 4 inch (110mm) waste stack
size we
considered is more safe.
-waste stack (1) size will be 2 inch (50 mm) (table 710.1(2)) international plumping
code. So, waste stack (1) size will be 2 inch (50mm) which means that the 4 inch (110mm) waste stack
size we
considered is more safe.
-soil stack (1) size will be 2 inch (50 mm) (table 710.1(2)) international plumping
code. So, soil stack (1) size will be 2 inch (50mm) which means that the 4 inch (110mm) waste stack
size we
considered is more safe.
Calculation for horizontal pipes
Waste horizontal pipe (1) (wp1) size = no of fixture unit load of risers (13+14+15+16+17+18+19)
=(15x11)
=165 f.u.l
-waste pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, waste stack size will be 4 inch (100 mm) which means that the 6 inch (160mm) waste pipe size we make
considered more save.
Soil horizontal pipe (1) (sp1) size = no of fixture unit load of risers (13+14+15+16+17+18+19)
=(12x11)
=132 f.u.l
-soil pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, soil pipe size will be 4inch (100 mm) which means that the 6 inch (160mm) soil pipe size we make
considered more save.
Waste horizontal pipe (2) (wp2) size = no of fixture unit load of risers (14a+15a+16a)
=(9)+(15x4)+25
=94f.u.l
-waste pipe size will be 4 inch (100mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, waste stack size will be 4 inch (100 mm) which means that the 6 inch (160mm) waste pipe size we make
considered more save.
Soil horizontal pipe (2) (sp2) size = no of fixture unit load of risers (14a+15a+16a)
=(12)+(12x4)+12
=72 f.u.l
-soil pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, soil pipe size will be 4inch (100 mm) which means that the 6 inch (160mm) soil pipe size we make
considered more save.
Waste horizontal pipe (3) (wp3) size = no of fixture unit load of risers (7+10+11+12)
=(15x8)
=120 f.u.l
-waste pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, waste stack size will be 4 inch (100 mm) which means that the 6 inch (160mm) waste pipe size we make
considered more save.
Soil horizontal pipe (3) (sp3) size = no of fixture unit load of risers (7+10+11+12)
=(12x8)
=96 f.u.l
-soil pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at slope
per foot=1/8 inch.
So, soil pipe size will be 4inch (100 mm) which means that the 6 inch (160mm) soil pipe size we make
considered more save.
Waste horizontal pipe (4) (wp4) size = no of fixture unit load of risers (30+32+33+34+35)
=(9x2) + (15x7) + 12
=135 f.u.l
-waste pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, waste stack size will be 4 inch (100 mm) which means that the 6 inch (160mm) waste pipe size we make
considered more save .
Soil horizontal pipe (4) (sp4) size = no of fixture unit load of risers (30+32+33+34+35)
=(12x2) + (12x7)
=108 f.u.l
-soil pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, soil pipe size will be 4inch (100 mm) which means that the 6 inch (160mm) soil pipe size we make
considered more save .
Waste horizontal pipe (5) (wp5) size = no of fixture unit load of risers (20+22+23+24+25)
=(10) + (12x2) + 64 +(20x3)
=158 f.u.l
-waste pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, waste stack size will be 4 inch (100 mm) which means that the 6 inch (160mm) waste pipe size we make
considered more save .
Soil horizontal pipe (5) (sp5) size = no of fixture unit load of risers (20+22+23+24+25)
=(16x2) + 16 +(16x3)
=96 f.u.l
-soil pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, soil pipe size will be 4inch (100 mm) which means that the 6 inch (160mm) soil pipe size we make
considered more save .
Waste horizontal pipe (6) (wp6) size = no of fixture unit load of risers (26+27+31)
=(76) + 64
=140 f.u.l
-waste pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, waste stack size will be 4 inch (100 mm) which means that the 6 inch (160mm) waste pipe size we make
considered more save .
Soil horizontal pipe (6) (sp6) size = no of fixture unit load of risers (26+27+31))
=(60) + 16
=76 f.u.l
-soil pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at slope
per foot=1/8 inch.
So, soil pipe size will be 4inch (100 mm) which means that the 6 inch (160mm) soil pipe size we make
considered more save.
Waste horizontal pipe (7) (wp7) size = no of fixture unit load of risers (1+2+3+4+5+6)
=20x8 + 28
=188 f.u.l
-waste pipe size will be 5 inch (127 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, waste stack size will be 5 inch (127 mm) which means that the 6 inch (160mm) waste pipe size we make
considered save.
Soil horizontal pipe (7) (sp7) size = no of fixture unit load of risers (1+2+3+4+5+6)
=16x8 + 16
=144 f.u.l
-soil pipe size will be 4 inch (100 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, soil pipe size will be 4inch (100 mm) which means that the 6 inch (160mm) soil pipe size we make
considered more save.
Waste horizontal pipe (8) (wp8) size = no of fixture unit load of horizontal pipes (1 to 7)
=165 + 94 + 120 + 135 + 158 + 140 + 188
=1000 f.u.l
-waste pipe size will be 8 inch (200 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, waste stack size will be 8 inch (200 mm) which means that the 8 inch (200mm) waste pipe size we make
considered save.
Soil horizontal pipe (8) (sp8) size = no of fixture unit load of horizontal pipes (1 to 7)
=132 + 72 + 96 + 108 + 96 + 76 + 144
=724 f.u.l
-soil pipe size will be 8 inch (200 mm) (table 710.1(1)) international plumping code at
slope per foot=1/8 inch.
So, soil pipe size will be 8inch (200 mm) which means that the 8 inch (200mm) soil pipe size we make
considered save.
Attachments
1- (Table 709.1) international plumping code.
2- (Table 710.1(2)) international plumping code.
3- Schematic Diagram
STANDARD DRAINAGE NOTES:
1. ALL SOIL,WASTE AND VENT PIPING SHALL BE CARRIED OUT IN UPVC CONFORMING
TO B.S 4514.
2. ALL INTERNAL AND EXTERNAL DRAINAGE PIPES FROM W.C./FLOOR GULLY TO
MANHOLES SHALL BE UPVC TO B.S.4660.
3. ALL INTERNAL WASTE PIPES UP TO 50mm SHALL BE UPVC.TO B.S.5255.
4. ALL SINKS WASH BASINS,FLOOR GULLIES,ETC.,SHALL BE TRAPPED BEFORE
CONNECTING TO DRAINAGE.TRAPS SHALL HAVE 75mm.DEEP SEAL.
5. PIPES PASSING THROUGH THE BUILDING STRUCTURE SHALL BE SLEEVED WITH SOIL
AND WASTE CLASS UPVC TUBULAR SLEEVE OF ONE SIZE BIGGER THAN THE PIPE.
6. MANHOLES,CATCH PITS,GULLY POTS,BEDDING FOR PIPE WORK AND OTHER DRAINAE
DETAILS TO COMPLY WITH THE "DEVELOPERS DRAINAGE GUIDE" DETAILS,MINISTRY
OF MUNICIPAL AFFAIRS AND AGRICULTURE,CIVIL ENGINEERING DEPARTMENT,
SEWERAGE DIVISION.
7. CONTRACTOR SHALL VERIFY THE SITE LEVELS BEFORE COMMENCING FOUL
AND SURFACE WATER DRAINAGE WORKS ON SITE.
8. ALL MANHOLE COVERS SHALL BE DUCTILE IRON TO B.S.497
9. ALL DRAINAGE INSTALLATIONS SHALL COMPLY WITH RELEVANT BRITISH STANDARDS
AND CURRENT BYELAWS AND REGULATIONS ISSUED BY DRAINAGE DIVISION,
CIVIL ENGINEERING DEPARTMENT AT THE MINISTRY OF MUNCIPAL AFFAIRS AND
AGRICULTURE OF THE STATE OF QATAR.
10. DIAMETER FOR ALL UNDERGROUND DRAINAGE PIPES ARE TO BE 150mm.
EXTRA STRENGHT VITRIFIED CLAY PIPE CONFORMING TO BSEN295,1991
11. DIAMETER FOR ALL DRAINAE PIPE ABOVE GROUND IS TO BE 100mm UPVC PIPE
CONFORMING TO BS 4514.
12. ANY DRAINAGE RUN UNDER THE BUILDING OR AT A DEPTH OF 600mm OR LESS
IN PEDESTRAIN AREAS OR AT THE DEPTH OF 1200mm OR LESS IN VEHICULAR
AREAS SHALL BE SURROUNDED WITH 150mm THICK CONCRETE IN S.R.C.20.
13. ALL PIPEWORK FLEXIBLE JOINTS SHALL BE RETAINED BY USING FIBER BOARDS
AT EACH JOINTS
14. A VENT PIPE IS REQUIRED AT ALL STARTING MANHOLES THE VENT PIPE SHOULD
BE RAISED 1.2m ABOVE ROOF LEVEL.
15. MANHOLES THAT ARE MORE THAN 1.m DEEP ARE TO BE CONSTRUCTED IN MASS
CONCRETE (S.R.C)
16. ALL MANHOLE COVERS ARE TO BE OF DOUBLE SEAL AND RECESSED TYPE.
17. NO SURFACE WATER WILL BE ALLOWED TO FLOW OUTSIDE OF THE PROPERTY.
18. CLIENT WILL BE RESPONSIBLE FOR PLUMBING ARRANGEMENT IN FUTURE IF
GOVERMENT SEWER LINE LAID ARE NOT DEEP ENOUGH FOR CONNECTION.
19. UNLESS A HOUSE CONNECTION CHAMBERS IS EXISTING WITH IN THE PLOT,
CLIENT MUST PROVIDE SEPTIC TANK AND SOAKAWAY.
20. THE PAINTING ROOM REQUIREMENTS SUCH AS LEVEL, SIZE AND MEP WORKS SHALL
BE CONSIDERED AND COORDINATED BEFORE STARTING EXECUTION ACTIVITIES
ACCORDING TO THE MODEL OF THE PAINTING ROOM WILL BE SELECTED BY CLIENT.
ROOF
PENTHOUSE
THIRD FLOOR
SECOND FLOOR
FIRST FLOOR
MEZZ. FLOOR
GROUND FLOOR
BASEMENT
STANDARD DRAINAGE NOTES:
1. ALL SOIL,WASTE AND VENT PIPING SHALL BE CARRIED OUT IN UPVC CONFORMING
TO B.S 4514.
2. ALL INTERNAL AND EXTERNAL DRAINAGE PIPES FROM W.C./FLOOR GULLY TO
MANHOLES SHALL BE UPVC TO B.S.4660.
3. ALL INTERNAL WASTE PIPES UP TO 50mm SHALL BE UPVC.TO B.S.5255.
4. ALL SINKS WASH BASINS,FLOOR GULLIES,ETC.,SHALL BE TRAPPED BEFORE
CONNECTING TO DRAINAGE.TRAPS SHALL HAVE 75mm.DEEP SEAL.
5. PIPES PASSING THROUGH THE BUILDING STRUCTURE SHALL BE SLEEVED WITH SOIL
AND WASTE CLASS UPVC TUBULAR SLEEVE OF ONE SIZE BIGGER THAN THE PIPE.
6. MANHOLES,CATCH PITS,GULLY POTS,BEDDING FOR PIPE WORK AND OTHER DRAINAE
DETAILS TO COMPLY WITH THE "DEVELOPERS DRAINAGE GUIDE" DETAILS,MINISTRY
OF MUNICIPAL AFFAIRS AND AGRICULTURE,CIVIL ENGINEERING DEPARTMENT,
SEWERAGE DIVISION.
7. CONTRACTOR SHALL VERIFY THE SITE LEVELS BEFORE COMMENCING FOUL
AND SURFACE WATER DRAINAGE WORKS ON SITE.
8. ALL MANHOLE COVERS SHALL BE DUCTILE IRON TO B.S.497
9. ALL DRAINAGE INSTALLATIONS SHALL COMPLY WITH RELEVANT BRITISH STANDARDS
AND CURRENT BYELAWS AND REGULATIONS ISSUED BY DRAINAGE DIVISION,
CIVIL ENGINEERING DEPARTMENT AT THE MINISTRY OF MUNCIPAL AFFAIRS AND
AGRICULTURE OF THE STATE OF QATAR.
10. DIAMETER FOR ALL UNDERGROUND DRAINAGE PIPES ARE TO BE 150mm.
EXTRA STRENGHT VITRIFIED CLAY PIPE CONFORMING TO BSEN295,1991
11. DIAMETER FOR ALL DRAINAE PIPE ABOVE GROUND IS TO BE 100mm UPVC PIPE
CONFORMING TO BS 4514.
12. ANY DRAINAGE RUN UNDER THE BUILDING OR AT A DEPTH OF 600mm OR LESS
IN PEDESTRAIN AREAS OR AT THE DEPTH OF 1200mm OR LESS IN VEHICULAR
AREAS SHALL BE SURROUNDED WITH 150mm THICK CONCRETE IN S.R.C.20.
13. ALL PIPEWORK FLEXIBLE JOINTS SHALL BE RETAINED BY USING FIBER BOARDS
AT EACH JOINTS
14. A VENT PIPE IS REQUIRED AT ALL STARTING MANHOLES THE VENT PIPE SHOULD
BE RAISED 1.2m ABOVE ROOF LEVEL.
15. MANHOLES THAT ARE MORE THAN 1.m DEEP ARE TO BE CONSTRUCTED IN MASS
CONCRETE (S.R.C)
16. ALL MANHOLE COVERS ARE TO BE OF DOUBLE SEAL AND RECESSED TYPE.
17. NO SURFACE WATER WILL BE ALLOWED TO FLOW OUTSIDE OF THE PROPERTY.
18. CLIENT WILL BE RESPONSIBLE FOR PLUMBING ARRANGEMENT IN FUTURE IF
GOVERMENT SEWER LINE LAID ARE NOT DEEP ENOUGH FOR CONNECTION.
19. UNLESS A HOUSE CONNECTION CHAMBERS IS EXISTING WITH IN THE PLOT,
CLIENT MUST PROVIDE SEPTIC TANK AND SOAKAWAY.
20. THE PAINTING ROOM REQUIREMENTS SUCH AS LEVEL, SIZE AND MEP WORKS SHALL
BE CONSIDERED AND COORDINATED BEFORE STARTING EXECUTION ACTIVITIES
ACCORDING TO THE MODEL OF THE PAINTING ROOM WILL BE SELECTED BY CLIENT.
ROOF
PENTHOUSE
THIRD FLOOR
SECOND FLOOR
FIRST FLOOR
MEZZ. FLOOR
GROUND FLOOR
BASEMENT
APPENDIX-B
BASEMENT Submersible Pump & Sump Pit Calculations
Assumptions:
* If the total amount of water to be removed in 3 hours the pump flow rate would be 2.4 l/s
* If the total amount of water to be removed in 4 hours the pump flow rate would be 1.8 l/s
l/
s
* Based on the above, three significant flow rate figures are simulated in the Table
below
Selecting Duplex operation of the the sump pumps, the flow rate of each one to be selected is 2l/s
Thus when water reach a high level in the pit, the second pump operate and the total flow rate would be 4 l/s
Vreq TminQ
=
4
Where: Vreq is the required sump volume between the start level and stop level of the pump
Vtot Total sump volume between the start level and stop level of the pump
n 2
ΔH 0.2 m
S 1.96 m2
3
Vtot 0.692 m
The Total Volume for the sump with 2 pumps with cyclic alternation
n 2
ΔH 0.2 m
S 1.96 m2
3
Vtot 0.542 m
Force Main Pipe Run 130 m 3.0 m (7 ft/1000 ft friction loss for a 4 '' pipe)
Force Main Pipe Run 85 m 3.9 m (14 ft/1000 ft friction loss for a 3 '' pipe)
Residual 1.0 m
Safety 9.9 m
Pump head 10 m
Notes:
1- In pumping stations do not use 2 1/2" on the discharge of waste, use 3" pipe
For roof: ‐
Total roof area (A) = 3150sqm
Runoff coefficient (C) = 0.85
Rainfall depth for 24hrs rainfall duration (d’) = 45mm
Volume of holding tank for 24hrs = (A x C x d’)
V2 = (3150 x 0.85 x 0.045)
V1 = 120.4cu.m
In case of excess of rainfall above 24hrs, the Holding tank shall be emptied by a private tanker by
owner.
APPENDIX‐D
Soak away calculation sheet
Surface water from the plot areas except roof shall be drained into soak aways.
Volume of each soak away with dia 2.1m & depth 3.25m = 11.3cu.m
Total number of soak aways required for surface water volume = V3 / 11.3
= 7 number of soak aways