SEM-PLS Cost performance-ScopusQ2
SEM-PLS Cost performance-ScopusQ2
SEM-PLS Cost performance-ScopusQ2
Research Article
SEM-PLS Analysis of Inhibiting Factors of Cost
Performance for Large Construction Projects in Malaysia:
Perspective of Clients and Consultants
Copyright © 2014 A. H. Memon and I. A. Rahman. This is an open access article distributed under the Creative Commons
Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is
properly cited.
This study uncovered inhibiting factors to cost performance in large construction projects of Malaysia. Questionnaire survey was
conducted among clients and consultants involved in large construction projects. In the questionnaire, a total of 35 inhibiting factors
grouped in 7 categories were presented to the respondents for rating significant level of each factor. A total of 300 questionnaire
forms were distributed. Only 144 completed sets were received and analysed using advanced multivariate statistical software of
Structural Equation Modelling (SmartPLS v2). The analysis involved three iteration processes where several of the factors were
deleted in order to make the model acceptable. The result of the analysis found that 𝑅2 value of the model is 0.422 which indicates
that the developed model has a substantial impact on cost performance. Based on the final form of the model, contractor’s site
management category is the most prominent in exhibiting effect on cost performance of large construction projects. This finding
is validated using advanced techniques of power analysis. This vigorous multivariate analysis has explicitly found the significant
category which consists of several causative factors to poor cost performance in large construction projects. This will benefit all
parties involved in construction projects for controlling cost overrun.
Likewise, Malaysian construction industry is also affected site mobilization, rigid attitude by consultants, extra work
by cost overrun burdens. Khamidi et al. [9] quoted from without approvals, frequent changes during execution, gold
the summary report of Malaysian Auditor General 2008 that plating, safety and health, and limited access to job sites.
electrification of double track rail project between Rawang Park and Papadopoulou [18] reported that most significant
and Ipoh has resulted in cost overrun of RM 1.43 billion. causes of cost overruns in infrastructure projects experienced
Endut et al. [10] in their study on 308 public and 51 private in Asia are contract awarded to the lowest bidder, inadequate
construction projects found that only 46.8% of the public site investigations, unforeseen site conditions, inadequate
projects and 37.2% of the private projects completed within pre-construction study, and inaccurate estimates.
the budget. Further, a survey conducted in the southern
region of Peninsular Malaysia highlighted that 89% of 140
respondents mentioned that most their projects faced cost 3. Conceptual Model
overrun [11].
In assessing the effect of inhibiting factors using PLS-SEM, a
Thus, cost overrun is a pertinent issue in the construction conceptual model is required. This model is explained in the
industry which needs serious attention in improving project’s relations between latent variables and their relative manifest
cost performance as the overrun is an additional burden variables. In this study, the conceptual model is developed
to all parties involved in the project. It is important to based on 35 inhibiting factors (also known as manifest
identify causative factors to cost overrun in order to manage variables) which are grouped into 7 categories (known as
the cost performance of the projects effectively. Hence, exogenous latent variables) named as Contractor’s Site Man-
this study focused on uncovering the inhibiting factors to agement Related Factors (CSM), Design and Documentation
cost performance of large construction projects in Malaysia. Related Factors (DDF), Financial Management Related Fac-
An advanced multivariate analysis method of Structural tors (FIN), Information and Communication Related Factors
Equation Modelling (SEM) which is a graphical equivalent (ICT), Human Resource (Workforce) Related Factors (LAB),
of a mathematical representation [12] was adopted for this Nonhuman Resource Related Factors (MMF), and Project
analysis as it is a very effective approach in analysing cause- Management and Contract Administration Related Factors
effect relations between factors [13]. (PMCA). Conceptual model showing relation between LV
and manifest variables is shown in Figure 1 where LVs are
drawn with oval shape while rectangular shaped elements
2. Inhibiting Factors to Cost Performance represent manifest variables. In PLS-SEM, generally the
Occurrences of poor cost performance in construction model is described by two components referred to as (1)
projects are due to various factors. These inhibiting factors measurement model or construct which relates manifest vari-
are referred to as cost overrun factors by many researchers. ables with relative LV and (2) structural model which shows
Literature reviewed on Kaming et al. [14] work indicates the relationship between various LVs [19]. The description of
that major factors affecting project cost in high-rise building each manifest variable is presented in path diagrams for each
projects are materials cost increased by inflation, inaccurate construct shown in Figures 2(a)–2(g).
quantity take-off, labour cost increased due to environment
restriction, lack of experience on project location, lack of 4. Data Collection and Sampling
experience of project type, unpredictable weather conditions,
and lack of experience of local regulation. In Chang [3] study, Method of data collection is governed by the conceptual
two reasons for cost increase in engineering design projects model that was developed earlier. For this study, the data was
are owner request of changes in scope and additional works. gathered using structured questionnaire survey. The survey
While in Koushki et al. [15] study on private residential was conducted amongst clients and consultants involved in
projects, the main contributors’ factors are contractor-related handling large construction projects in Malaysia. A total
problems, material-related problems, and owners’ financial of 300 questionnaire forms (150 among client firms and
constraints, Enshassi et al. [16] studied construction projects 150 among consultant firms) were distributed in 11 states of
specifying that main factors are increment of materials prices, Peninsular Malaysia. As a response, 156 completed question-
delay in construction, supply of raw materials and equipment naire sets were received, of which 12 questionnaire sets were
by contractors, fluctuations in the cost of building materials, incomplete and considered inappropriate. The analysis used
unsettlement of local currency, project materials monopoly 144 completed questionnaire sets which are sufficient based
by some suppliers, resources constraint(funds and associated on Hair et al. [13] rule of thumb for sample size required
auxiliaries, not ready), lack of cost planning/monitoring dur- in PLS-SEM. Based on the completed questionnaire sets,
ing pre- and postcontract stages, improvements to standard demography of the respondents is presented in Table 1.
drawings during the construction stage, design changes, and Table 3 shows that the participation of the consultant is
inaccurate quantity take-off. very high with 92 of 100 and only 52 are clients in the survey.
Nawaz et al. [17] conducted a survey among construc- Majority of the respondents (68%) had working experience
tions professionals, contractors, architects, design designers, for more than 10 years in handling construction projects.
suppliers, and subcontractors in Pakistan and identified 10 Also, 76% of respondents have attained engineering degree.
main factors which affect cost performance: corruption and Majority of respondents are handling directorate, managerial,
bribery, political interests, poor site management, delay in and engineering positions in their respective organizations.
The Scientific World Journal 3
LAB1 LAB2 LAB3 LAB4 LAB5 DDF1 DDF2 DDF3 DDF4 DDF5
LAB DDF
CSM1
CSM2
FIN1
CSM3
FIN2
Cost CSM4
FIN3 FIN performance CSM
CSM5
FIN4 CSM6
FIN5 CSM7
FIN6
CSM8
MMF
ICT PMCA
MMF1 MMF2 MMF3 MMF4 ICT1 ICT2 ICT3 PMCA PMCA PMCA PMCA
1 2 3 4
Table 1: Characteristics of the respondents. performance. PLS simulation of the model is carried out by
calculating and assessing various parameters which include
Cumulative
Characteristic Frequency Percentage item loading, reliability, and validity tests. It involves a 2-step
percentage
process as suggested by Henseler et al. [21] which involve
Experience calculating PLS model parameters separately by solving out
0–5 Years 23 16 16 the blocks of the measurement model and then estimating
6–10 Years 23 16 32 the path coefficients of a structural model [22]. Finally, overall
11–15 Years 30 20.8 52.8 model is validated power analysis test.
16–20 Years 15 10.4 63.2
>20 Years 53 36.8 100
Education Level 5.1. Measurement Model Evaluation. Measurement model
BE 110 76.4 76.4 evaluation is aimed to evaluate the consistency and valid-
BSc 8 5.6 81.9 ity of the manifest variables. Consistency evaluations are
Diploma 3 2.1 84.0 through individual manifest and construct reliability tests.
MBA 1 0.7 84.7 While validity of the variables is tested based on convergent
ME 3 2.1 86.8 and discriminant validity [23], individual manifest reliability
MSc 17 11.8 98.6 explains the variance of individual manifest relative to latent
PhD 2 1.4 100 variable by calculating standardised outer loadings of the
Working Position manifest variables [24]. Manifest variables with outer loading
Executives (directors) 50 34.72 34.72 0.7 or higher are considered highly satisfactory [21, 24]. While
Managerial personnel 35 24.31 59.03 loading value of 0.5 is regarded as acceptable, the manifest
Engineering staff 54 37.50 96.53 variables with loading value of less than 0.5 should be
Quantity surveying dropped [25, 26]. Hulland [27] argued that 0.4 should be the
5 3.47 100
personnel acceptable loading value where Henseler et al. [21] suggested
that manifest variable with loading values between 0.4 and 0.7
should be reviewed before elimination. If elimination of these
This indicates that the participants in the survey are compe- indicators increases the composite reliability then discard or
tent and hence the collected data is considered valid. otherwise maintain the factors. Even though for this study
the cut-off value taken for outer loading is 0.5, an iterative
5. PLS-SEM Evaluation/Analysis process is adopted for elimination of the manifest variables
by considering Henseler et al. [21] suggestion.
The developed conceptual model was drawn in SmartPLS Second parameter for consistency evaluations is con-
software [20] for simulation work in assessing the effect of structed reliability where it is evaluated by two measures,
manifest variables (inhibiting factors) on construction cost that is, Cronbach’s alpha and Composite Reliability (CR).
4 The Scientific World Journal
(a)
FIN1: cash flow and financial difficulties
faced by contractors
FIN2: poor financial control on site
DDF1: frequent design changes
FIN3: financial difficulties of owner
DDF2: mistakes and errors in design FIN
FIN4: delay in progress payment by owner
DDF3: incomplete design at the time of tender
DDF FIN5: delay payment to supplier/subcontractor
DDF4: poor design and delays in design
FIN6: contractual claims, such as extension of
DDF5: delay preparation and approval of drawings time with cost claims
(b) (c)
LAB1: labour productivity
(d) (e)
MMF1: fluctuation of prices of materials PMCA1: poor project management
MMF2: shortages of materials PMCA2: change in the scope of the project
MMF PMCA
MMF3: late delivery of materials and equipment PMCA3: delays in decisions making
MMF4: equipment availability and failure PMCA4: inaccurate quantity take-off
(f) (g)
Cronbach’s alpha and CR indicate how well a set of manifest to measurement errors. Barclay et al. [30] and Hair et al.
variables appraises a single latent construct. However, com- [13] argued that a minimum 50% of the variance from
pared to Cronbach alpha, composite reliability is considered manifest variable should be captured by latent variables. This
a better measure of internal consistency because it employs implies that AVE value of the construct should be greater
the standardized loadings of the manifest variables [28]. than 0.5. Discriminant validity is carried out to confirm
Nonetheless, the interpretation of composite reliability score that the manifest variable in any construct is relevant to the
and Cronbach’s Alpha is the similar. Litwin [29] suggested designated latent variable where its cross-loading value in LV
that value of cronbach alpha should be higher than 0.7 and for is higher than that in any other constructs [25].
composite reliability, the value of 0.7 is suggested as “modest” Based on the above criteria, measurement model is
[13]. evaluated by iterative process to discard the weak manifest
For the validity of the variable, the variables are tested on variables from the developed model. Hence, a total of 3
convergent and discriminant validities. Convergent validity iterations were involved in this study where each of the
is carried out by Average Variance Extracted (AVE) test on iterations was assessed based on the criteria and resulted in
variables [28]. It determines the amount of variance captured discarding 6 manifest variables. Table 2 summarizes the first
by latent variable from its relative manifest variables due and final iterations only.
The Scientific World Journal 5
In the first iteration of Table 2, three constructs ICT, 5.2. Structural Model Assessment. Structural model assesses
LAB, and MMF have parametric measurement above the cut- relationship between exogenous and endogenous latent vari-
off values. While the other 4 constructs (CSM, DDF, FIN, ables through evaluating R2 value, that is, coefficient of deter-
and PMCA) have achieved satisfactory measurement values mination [23] and also 𝛽 value, that is, path coefficients of
except AVE which is below 0.5. Following iterations has dis- the model [25]. R2 corresponds to the degree of explained
carded 6 weak manifest variables in 4 of the constructs which variance of endogenous latent variables [31] while 𝛽 indicates
are CSM02, CSM03, DDF04, FIN03, FIN04, and PMCA01.
the strength of an effect from variables to endogenous latent
Once the iteration process completed, the final model
variables [32]. According to Cohen et al. [33, 34] for a
is checked for discriminant validity based on cross loading
values generated from the final iteration as shown in Table 3. good model, the value of R2 of endogenous latent variable
Cross loading of all the manifest variables has higher values should be more than 0.26. Since R2 value for the developed
on their relative latent variable as compared with other model is 0.422 which is higher than the suggested value, the
constructs as in the Table 3. This verifies that the manifest model is considered to have substantial degree of explained
variables in each construct represent the assigned latent variance of cost performance by inhibiting factors. Next step
variable testifying the discriminant validity of the model. is assessing the path coefficient of all latent variables (paths)
6 The Scientific World Journal
by comparing 𝛽 values among all the paths. The highest 𝛽 Results from Table 4 demonstrate that all the paths
value symbolizes the strongest effect of predictor (exogenous) attained t-value are higher than the cut-off point for a signif-
latent variable towards the dependent (endogenous) latent icance level of 1 percent, that is, 2.58. This implies that all the
variable [35]. However, 𝛽 value has to be tested for its paths in the model have a strong effect on cost performance.
significance level through t-value test. The test is achieved by The highest 𝛽 value is 0.718 for contractor’s site management
performing nonparametric bootstrapping technique [25, 36, related factors. This most significant construct (group of
37]. Bootstrapping technique computes t-value by creating factors) influences critically in affecting cost performance of
prespecified number of samples. Hair et al. [13] suggested that construction projects.
acceptable t-values for a two-tailed test are 1.65 (significance
level = 10 percent), 1.96 (significance level = 5 percent), 5.3. Model Validation. The developed model is validated to
and 2.58 (significance level = 1 percent). In this study, check its usefulness. The validation is carried out by checking
bootstrapping generated 5000 samples and these samples are the stability of the model through calculating adequacy of
used to compute t-values as presented in Table 4. sample size with power analysis test. Power analysis (1 − 𝛽)
The Scientific World Journal 7
1
0.9850.9940.9980.999 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 11
0.959
0.898
0.8
0.761
Power (1 − 𝛽 err prob)
0.6
0.486
0.4
0.2
0.079
test is to check the stability of the model’s parameters with the explained variance of cost performance by inhibiting
sample size used for the analysis [25]. It is to confirm whether factors.
the sample size used is sufficient for generating a stable (iii) The sample size of 144 involved in the study was
model. The test is conducted by calculating the power of adequate and validated through power analysis test.
the model through G∗ Power 3.1.2 software package [38, 39].
Input parameters required for the software are at significance (iv) Most significant category of inhibiting factors affect-
level (𝛼) of the test, sample size (N) of the study and effect size ing cost performance in the construction industry is
(ES) of the population. Effect size is calculated using Cohen Contractor’s site management.
et al. [34] equation as below: In contractor site management group there are 7 fac-
2 tors which are significant for the contractors to give more
𝑅
Effect Size = , (1) emphasis for achieving successful completion of the projects
1 − 𝑅2 undertaken by them.
where R2 is the coefficient of determination.
Input parameters for this study are significance level as Conflict of Interests
0.01 (i.e., 99% of confidence level), sample size (N) as 144, and
effect size (ES) as 0.73. The generated values of power analysis The authors declare that there is no conflict of interests
for various sample sizes are shown in Figure 3. Figure 3 regarding the publication of this paper.
indicates that the power of the overall model increases as the
number of samples size increases. It achieved 100% power at Acknowledgment
sample size of 50 since this study used 144 samples and it
is obvious that it is more adequate for achieving substantial The authors would like to thank Centre of Research and
power. Innovations, Universiti Tun Hussein Onn Malaysia, for
encouragement and support in carrying out this research
6. Conclusion work. The authors also pay especially thanks to respondents
participating in the survey, without whose cooperation and
This study highlighted the cost performance in the construc- precious time the completion of this work was not possible.
tion project affected by various inhibiting factors. These fac- A. H. Memon is thankful to Quaid-e-Awam University of
tors are grouped and modelled into 7 categories in SmartPLS Engineering, Science and Technology also for granting per-
software where it was analyzed for assessing the effect on cost mission to carryout research work at Universiti Tun Hussein
performance. Major conclusions drawn from this study are as Onn Malaysia.
follows.
(i) 29 inhibiting factors have a strong effect on cost References
performance, major conclusion drawn from study.
[1] W. J. Angelo and P. Reina, “Megaprojects need more study up
(ii) R2 value of the model is more than 0.26 and classified front to avoid cost overruns,” 2002, http://flyvbjerg.plan.aau.dk/
as a good model where it has substantial degree of News%20in%20English/ENR%20Costlies%20150702.pdf.
8 The Scientific World Journal
[2] X. Meng, “The effect of relationship management on project [18] Y. I. Park and T. C. Papadopoulou, “Causes of cost overruns in
performance in construction,” International Journal of Project transport infrastructure projects in Asia: their significance and
Management, vol. 30, no. 2, pp. 188–198, 2012. relationship with project size,” Built Environment Project and
[3] A. S.-T. Chang, “Reasons for cost and schedule increase for engi- Asset Management, vol. 2, no. 2, pp. 195–216, 2012.
neering design projects,” Journal of Management in Engineering, [19] M. Tenenhaus, V. E. Vinzi, Y.-M. Chatelin, and C. Lauro, “PLS
vol. 18, no. 1, pp. 29–36, 2002. path modeling,” Computational Statistics and Data Analysis, vol.
[4] V. Žujo, D. Car-Pušic, and A. Brkan-Vejzović, “Contracted price 48, no. 1, pp. 159–205, 2005.
overrun as contracted construction time overrun function,” [20] C. M. Ringle, S. Wende, and S. Will, “SmartPLS 2.0 (M3) Beta,”
Technical Gazette, vol. 17, no. 1, pp. 23–29, 2010. Hamburg 2005, http://www.smartpls.de.
[5] N. Gupta, “Avoiding time and cost overruns in the construction [21] J. Henseler, C. M. Ringle, and R. R. Sinkovics, “The use of
of Rohtang tunnel,” 2009, http://www.idsa.in/idsacomments/ partial least squares path modeling in international marketing,”
AvoidingTimeandCostOverrunsintheConstructionofRohtang- Advances in International Marketing, vol. 20, pp. 277–319, 2009.
Tunnel ngupta 141209. [22] V. E. Vinzi, L. Trinchera, and S. Amato, “PLS path modeling:
[6] J.-K. Lee, “Cost overrun and cause in Korean social overhead from foundations to recent developments and open issues for
capital projects: roads, rails, airports, and ports,” Journal of model assessment and improvement,” in Handbook of Partial
Urban Planning and Development, vol. 134, no. 2, pp. 59–62, Least Squares, V. E. Vinzi, W. W. Chin, J. Henseler, and H. Wang,
2008. Eds., Springer Handbooks of Computational Statistics, pp. 47–
[7] O. A. Olatunji, “A comparative analysis of tender sums and final 82, 2010.
costs of public construction and supply projects in Nigeria,” [23] J. F. Hair, M. Sarstedt, C. M. Ringle, and J. A. Mena, “An
Journal of Financial Management of Property and Construction, assessment of the use of partial least squares structural equation
vol. 13, no. 1, pp. 60–79, 2008. modeling in marketing research,” Journal of the Academy of
[8] R. Apolot, H. Alinaitwe, and D. Tindiwensi, “An investigation Marketing Science, vol. 40, no. 3, pp. 414–433, 2012.
into the causes of delay and cost overrun in Uganda’s public [24] O. Gotz, K. Liehr-Gobbers, and M. Krafft, “Evaluation of
sector construction projects,” in Proceedings of the 2nd Interna- structural equation models using the Partial Least Squares
tional Conference on Advances in Engineering and Technology, (PLS) approach,” in Handbook of Partial Least Squares, V. E.
pp. 305–311, 2008. Vinzi, W. W. Chin, J. Henseler, and H. Wang, Eds., Springer
[9] M. F. Khamidi, W. A. Khan, and A. Idrus, “The cost monitoring Handbooks of Computational Statistics, pp. 47–82, 2010.
of construction projects through earned value analysis,” in [25] W. W. Chin, “The partial least squares approach to structural
Proceedings of the International Conference on Economics and equation modeling,” in Modern Methods for Business Research,
Finance Research (IPEDR ’11), vol. 4, IACSIT Press, Singapore, G. A. Marcoulides, Ed., pp. 295–336, Erlbaum, Mahwah, NJ,
2011. USA, 1998.
[10] I. R. Endut, A. Akintoye, and J. Kelly, “Cost and time overruns [26] J. F. Hair, C. B. William, J. B. Barry, and R. E. Anderson,
of projects in Malaysia,” 2009, http://www.irbnet.de/daten/ Multivariate Data Analysis, Prentice Hall, Englewood Cliffs, NJ,
iconda/CIB10633.pdf. USA, 2010.
[11] I. A. Rahman, A. H. Memon, A. A. A. Azis, S. Nagapan, and [27] J. Hulland, “Use of Partial Least Squares (PLS) in strategic
Q. B. I. Latif, “Time and cost performance of costruction pro- management research: a review of four recent studies,” Strategic
jects in southern and cenrtal regions of Penisular Malaysia,” in Management Journal, vol. 20, no. 2, pp. 195–204, 1999.
Proceedings of the IEEE Colloquium on Humanities, Science & [28] C. Fornell and D. F. Larcker, “Evaluating structural equation
Engineering Research (CHUSER ’12), pp. 46–51, December 2012. models with unobservable variables and measurement error,”
[12] B. M. Byrne, Structural Equation Modeling with AMOS Basic Journal of Marketing Research, vol. 18, no. 1, pp. 39–50, 1981.
Concepts, Applications, and Programming, Taylor and Francis, [29] M. S. Litwin, How to Measure Survey Reliability and Validity,
2010. Sage, Thousand Oaks, Calif, USA, 1995.
[13] J. F. Hair, C. M. Ringle, and M. Sarstedt, “PLS-SEM: indeed a [30] D. Barclay, R. Thompson, and C. Higgins, “The Partial Least
silver bullet,” Journal of Marketing Theory and Practice, vol. 19, Squares (PLS) approach to causal modeling: personal computer
no. 2, pp. 139–151, 2011. adoption and use as an illustration,” Technology Studies, vol. 2,
[14] P. F. Kaming, P. O. Olomolaiye, G. D. Holt, and F. C. Harris, no. 2, pp. 285–309, 1995.
“Factors influencing construction time and cost overruns on [31] S. Akter, J. D. Ambra, and R. Ray, “An evaluation of PLS
high-rise projects in Indonesia,” Construction Management and based complex models: the roles of power analysis, predictive
Economics, vol. 15, no. 1, pp. 83–94, 1997. relevance and GoF index,” in Proceedings of the 17th Americas
[15] P. A. Koushki, K. Al-Rashid, and N. Kartam, “Delays and cost Conference on Information Systems (AMCIS ’11), Detroit, Mich,
increases in the construction of private residential projects in USA, 2011.
Kuwait,” Construction Management and Economics, vol. 23, no. [32] C. Lleras, “Path analysis,” Encyclopedia of Social Measurement,
3, pp. 285–294, 2005. vol. 3, pp. 25–30, 2005.
[16] A. Enshassi, J. Al-Najjar, and M. Kumaraswamy, “Delays and [33] J. Cohen, Statistical Power Analysis for the Behavioral Sciences,
cost overruns in the construction projects in the Gaza Strip,” Lawrence Erlbaum Associates, Hillsdale, NJ, USA, 2nd edition,
Journal of Financial Management of Property and Construction, 1988.
vol. 14, no. 2, pp. 126–151, 2009. [34] J. Cohen, P. Cohen, S. G. West, and L. S. Aiken, Applied Mul-
[17] T. Nawaz, N. A. Shareef, and A. A. Ikram, “Cost performance tiple Regression/Correlation Analysis for the Behavioral Sciences,
in construction industry of Pakistan,” Industrial Engineering Lawrence Erlbaum Associates, Mahwah, NJ, USA, 3rd edition,
Letters, vol. 3, no. 2, pp. 19–33, 2013. 2003.
The Scientific World Journal 9
Rotating
Machinery
International Journal of
The Scientific
Engineering Distributed
Journal of
Journal of
Journal of
Control Science
and Engineering
Advances in
Civil Engineering
Hindawi Publishing Corporation Hindawi Publishing Corporation
http://www.hindawi.com Volume 2014 http://www.hindawi.com Volume 2014
Journal of
Journal of Electrical and Computer
Robotics
Hindawi Publishing Corporation
Engineering
Hindawi Publishing Corporation
http://www.hindawi.com Volume 2014 http://www.hindawi.com Volume 2014
VLSI Design
Advances in
OptoElectronics
International Journal of
International Journal of
Modelling &
Simulation
Aerospace
Hindawi Publishing Corporation Volume 2014
Navigation and
Observation
Hindawi Publishing Corporation
http://www.hindawi.com Volume 2014
in Engineering
Hindawi Publishing Corporation
http://www.hindawi.com Volume 2014
Engineering
Hindawi Publishing Corporation
http://www.hindawi.com Volume 2014
Hindawi Publishing Corporation
http://www.hindawi.com
http://www.hindawi.com Volume 2014
International Journal of
International Journal of Antennas and Active and Passive Advances in
Chemical Engineering Propagation Electronic Components Shock and Vibration Acoustics and Vibration
Hindawi Publishing Corporation Hindawi Publishing Corporation Hindawi Publishing Corporation Hindawi Publishing Corporation Hindawi Publishing Corporation
http://www.hindawi.com Volume 2014 http://www.hindawi.com Volume 2014 http://www.hindawi.com Volume 2014 http://www.hindawi.com Volume 2014 http://www.hindawi.com Volume 2014