Bndp3 in Cscec p3c El XX Ms El 00005 Installation & Testing of Fo Cable
Bndp3 in Cscec p3c El XX Ms El 00005 Installation & Testing of Fo Cable
Bndp3 in Cscec p3c El XX Ms El 00005 Installation & Testing of Fo Cable
Type SD: Shop Drawing, SM: sample, GU: Guarantee, MD: Manufacturers data, CT: Certificate, TR: Test report, MS
Method Statement, ABD: As-Built Drawings, O&M manuals, WR: Warranty etc
SUPPLIER/MANUFACTURER: N/A
We certify that the documents/materials submitted herewith have been reviewed in detail and are in strict
conformance with the contract drawings and specification except as otherwise stated
CONTRACTOR (NAME):
SIGNATURE RECEIVED
Wang Wei
DATE:21-11-2022 DATE
□ Rejected (Code D)
ALD-OP-QM-PQP-FRM-00004 1 Rev: 01
Classification : Internal General Purpose
Detailed Review Comments
SI No: Engineer's Comments Contractor's Response/Compliance
QA/QC Comments
1 Refer to Mark-up comments in ITP and follow during the
execution
2 All testing shall performed as per project specification
requirements
HSE Comments:
1. Ensure winch machine is located away from
edges of excavation and it shall be regularly
inspected.
2. All materials shall be stored dedicated area
and not to be stored on the working area.
3. All excavations shall hard barricaded and shall
have blinking lights.
4. All excavations must have proper access and
egress.
5. If any work at height will be there, contractor to
include in risk assessment.
6. All in red fonts to be incorporated in this
document
Correction or comments made relative to submittals during this review do not relieve the contractor from compliance with the contract requirements and specifications. Any changes from previous revisions of the submittal or contract documents, unless spacifically highlighted are not necessarily reviewed and hence not necessarily approved. Page
Page 1 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
REVISION RECORD
Pramod Ahmed
Ibrahim Wang Wei
Punnadath Ghanem
Construction
Construction Deputy Project Project
Manager
Manager Manager Manager
0 21-Nov-22 (Electrical)
Page 2 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
Table of Contents
1 SCOPE & OBJECTIVE ............................................................................................................. 5
2 DEFINITIONS & ABBREVIATIONS.......................................................................................... 5
3 CODES AND STANDARDS ..................................................................................................... 6
4 REFERENCES .......................................................................................................................... 6
5 MATERIALS ............................................................................................................................. 6
6 PLANT & EQUIPMENTS REQUIREMENTS ............................................................................ 7
7 SEQUENCES OF WORSK ....................................................................................................... 7
8 DETAILED PROCEDURES ...................................................................................................... 7
9 HEALTH & SAFETY ................................................................................................................. 8
10 EMERGENCY ARRANGEMENTS ...................................................................................... 11
11 HAZARDS FACED WHILST CARRYING OUT THE WORKS ............................................ 11
12 ORGANISATIONAL RESPONSIBILITIES .......................................................................... 11
13 MANPOWER ....................................................................................................................... 15
14 DISTRIBUTION.................................................................................................................... 15
15 STATEMENT OF INTENT ................................................................................................... 15
Page 3 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
PREFACE
The purpose of this Method Statement is to establish, monitor and control all activities relating to the
Installation and Testing of Fiber Optic Cable for project including inspection, sampling and testing to be
conducted, in accordance to the requirements prescribed in the drawings and stipulated in the contract
Specification.
CSCEC presents this Method Statement for review and to notify those who are involved in the construction
to attain the consistency of work towards the common objectives.
This Method statement is a controlled document and only the current revision number is valid and
authorized.
All necessary parties involved in the execution of this method will be competent and authorized for their
respective roles and will be fully conversant with the contents of this document.
Signed:
Date:21.11.2022
Wang Wei
Project Manager
Page 4 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
The objective of this method statement is to define how the activities pertaining to Fiber Optic
Cable Installation and testing works are proposed to be carried out in a safe manner and to
ensure that the fundamental checks, inspections in conformance with contract requirements are
being carried out to prevent non-conformity in all stages of work.
2.2 ABBREVIATIONS
ITP - INSPECTION & TEST PLAN means the document which contains sequence of
activities in a process, highlights the applicable Quality Documents, and inspection criticalities.
Page 5 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
SITE means the place, designated by Client for further development, where the construction
activities shall be carried out by Sub-Contractor.
4 REFERENCES
4.1. Contract drawings /documents.
4.2. Approved Layout & Profile Drawings
4.3. ADWEA/ADDC/AADC STANDARD S-AAA-CAB-INST-CONT-FOC (Rev.0-2011)
4.4. ADWEA/ADDC/AADC STANDARD S-AAA-CAB-FOC (Rev.0-2011)
4.5. OSHAD SF EHSMS Manual, Mechanism, Technical Guidelines and Code of Practices
4.6. ALDAR EHSMS Rev.06
4.7. Project Specific Safety Plan (PSSP)
4.8. Construction Environmental Management Plan (CEMP)
4.9. Project Quality Plan
4.10. Traffic Management Plan
4.11. Contract Drawings/ Relevant Shop Drawings
4.12. CSCEC’s IMS
4.13. Environmental Aspect & Impact Register
5 MATERIALS
5.1. Fiber Optic Cable
Page 6 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
7 SEQUENCES OF WORK
7.1 Prior Activities
7.1.1 Orientation for all staff regarding safety and environmental requirements before sending to site
7.1.2 All personnel protective equipment must be available.
7.1.3 Obtaining approval from utility authority and relevant department’s prior commencement of work.
7.1.4 Obtaining existing utilities information and excavate trial pits to locate and confirm the existing
services at trench route as necessary.
7.1.5 Obtaining the approval of shop drawing ,route approval and method statement prior to start activity
7.1.6 A copy of all the approval shall be available on site all time.
7.1.7 Check Calibration of Surveying Equipment’s.
7.1.8 All related shop drawings approved
7.1.9 Check Calibration of Surveying Equipment’s.
7.1.10 All related shop drawings approved
7.1.11 Check for existing utilities before excavation.
7.1.12 Check all the drums are free of damage.
7.1.13 Check the conduit through which cable pulled are smooth and free of any damage.
7.1.14 Check cable over drum for any damage.
7.1.15 All necessary approvals from different authorities shall be arranged by the contractor.
8 DETAILED PROCEDURES
8.1 Handling & Storing
8.1.1 Cables shall be delivered, handled and stored according to the manufacturer’s recommendations
along with the following provisions:
8.1.2 Transportation, handling and storage shall at all times be performed in a manner to avoid product
damage.
8.1.3 Check the dimensions & weight of the material to be off-loaded from supplier’s conveyance.
Page 7 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
8.1.4 Arrange suitable lifting facilities (Crane, Hiab etc.) and unload items at site store / installation
location, as applicable.
8.1.5 Only nylon slings shall be allowed for lifting, steel chains, clamps or cables shall not be allowed for
lifting purposes.
8.1.6 Cable drums are heavy and must only be lifted and lowered with suitable lifting equipment.
8.1.7 The individual drum weight is indicated on the stenciling on the drum itself. The lifting equipment
must have a safe working load greater than the drum weight.
8.1.8 To lift the drum, place a strap or wire rope through the central spindle hole and hook to the lifting
equipment. The angle that the straps form must always be more than 45 degrees. A wooden or
metallic spar, with a length greater than the drum width, must be placed between the lifting straps to
prevent the drum flanges being crushed.
8.1.9 When lowering drums always ensure that there are wooden stops in place to prevent the drum from
rolling.
8.1.10 If a drum has to be rolled, always ensure that it is rolled in the direction of the arrow on the side.
8.1.11 Visually inspect all material upon delivery and report any damage to the Engineer.
8.1.12 Any material damaged during delivery, storage or installation shall be marked and set aside.
8.2 Transportation:
8.2.1 The drums must be transported on either a “ flat bed” lorry or on a cable trailer. The gross vehicle
weight and carrying capacity of the individual vehicles must be observed.
8.2.2 Place wooden stops on either side of each drum as it is loaded.
8.2.3 Place two securing straps through each drum and tie them off in opposite directions.
8.2.4 It is not recommended to transport full drums of a cable stacked more than on high.
8.2.5 Never unload drums by rolling them off the back of Lorries.
8.3 Trenching and Backfilling:
8.3.1 It shall be ensured that the existing Underground services are identified by appropriate means prior
to start the excavation
8.3.2 Set out the cable route locations strictly according to the approved route plan, after getting approval
for the earth excavation from concerned authorities.
8.3.3 Hard Barricade to be provided along the proposed cable trench when the trench is close to the road
as per local authority’s requirement.
8.3.4 Provide appropriate hazard warning signs, for excavation and buried cables.
8.3.5 Provide flashers & blinkers when the trench is close to the road.
8.3.6 Protect the service lines as required.
8.3.7 Removal of trees, excavation in green area, etc. shall be carried out strictly in accordance with
authorities' specific requirements.
8.3.8 Excavate till the specified bottom level with suitable side slope.
8.3.9 Transport the excess excavated materials from the site to the designated area for disposal. Place
the required amount of excavated material to be used later for backfilling in the vicinity, but at least
1.5m away from the cable trench.
8.3.10 Provide sand bedding as per the specification.
8.3.11 Cable pulling shall be carried out as described in next section
Page 8 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
8.3.12 Dune sand shall be laid up to the level of Cable Cover Tiles
8.3.13 Place cable cover tiles.
8.3.14 After Cable cover Tiles, cover the tiles with sand and lay warning tape.
8.3.15 Backfill & compact the trench as shown in the drawing at every layer of 30cm with the use of roller /
plate compactor.
8.3.16 Implement necessary safety precautions and provide temporary access & detours as per ADDC
safety regulations.
8.4 Laying of Cables (Through PVC Conduit) :
8.4.1 Jack stand is used for the cable drums.
8.4.2 Once sand bedding is done in trench, preparatory works for laying of Pipe shall begin.
8.4.3 Ensure that the trench and the PVC Conduits to be pulled / laid with cables are inspected and
approved and clearance is given.
8.4.4 Check and ensure that the cable trench / ducts are clean, free from debris all along the route. Ducts
internal to be checked and cleaned by using rags tied to a rope and pulled back and forth from both
ends and check that it is free from any sharp edges. Mandrel test to be done prior to pulling of FOC
in ducts.
8.4.5 FO cable(s) shall be laid through separate PVC conduit(s) along one side of the service corridor in
parallel to the power cable (in the same trench) at 1 Mtr. depth. This is for easy construction of the
cable pulling pit and to avoid crossing with power cables. Accordingly, the cable pulling pit shall be
along one side of the corridor.
8.4.6 A cable pulling rope shall be installed inside the upvc duct and available for connection to the cable
at the end of ducts and pulling pits
8.4.7 The manhole/pulling/splicing pit shall be installed at every 200m interval as required by DMS for
easy pulling of the FO cables and for future connectivity to third party and at every 90 Degree
deviation of cable route. Additional FO cable (Appx. 5 Mtr.) shall be placed within the pit as loop.
8.4.8 Cables to be applied with an approved pulling compound for smooth and easy pulling when entering
cable ducts.
8.4.9 During installation the drum turning/rolling will be slowed down / stop / controlled manually by hand
or by using a wooden friction brake so as to prevent the turns of the drum from becoming loose and
scrapping on the floor.
8.4.10 A good communication measures / devices shall be used / maintained for a good and safe cable
pulling / laying operation. Two-way radio (walkie – talkie) will be used for communication. Proper
cable puller to be used and pulling tension shall not exceed the limits
8.4.11 Both ends of the cable to be capped / taped / sealed with heat shrinkable caps. Ensure that a
sufficient overlap of cable is provided on either side to reach furthest termination point with proper
looping (Appx 20 Mtr.).
8.4.12 Any jointing / splicing shall be with approved suitable splice boxes as detailed in the approved
drawings.
8.4.13 The laid cables to be arranged / dressed along the route and proper clearance to be maintained as
per the approved drawings.
8.4.14 Necessary loops shall be kept at termination ends (Appx. 20 Mtr.) and at future termination points, if
any.
8.5 Fiber Optic Splicing / Termination:
Page 9 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
8.5.1 Splicing of all fiber optic cables will be carried out by means of fusion – splicing machine and
optical fiber cleaver and will be done by ADDC approved slicer.
8.5.2 Once all the cables have been spliced, each individual splice loss shall be measured in both
directions by means of OTDR with checks at 1550nm and 1310nm.
8.5.3 Patch panels will be used as termination points in side Substation. Pigtails of 1 Mtr. length will be
fusion spliced on the individual fibres and will be terminated in the patch panel
8.6 Fiber Optic Cable Testing Procedure:
8.6.1 Every newly installed fiber should be measured after the installation has been completed. The
quantity of cable and each of fiber of the line area are tested.
FOC Drum Test
8.6.2 Before taking drum to site test each drum/cable in drum for their optical continuity attenuation &
damage due to improper handling of drum.
8.6.3 Flanges are stenciled for various parameters such as cable Length code, meter marking,
manufacturer’s name, fiber count and fiber type. Check correct Drum for Drum no, length, fiber
count, fiber type as mentioned in Plan before dispatching it for installation site.
8.6.4 Open drum & inspect Drum for Optical continuity & attenuation before taking drum to the site. If any
deviation found inform supplier immediately & plan another drum with matching requirements
of Original plan.
OTDR Test
8.6.5 OTDR testing for all 32 fibers will be carried out for each fiber at both directions (back scatter) and
both wave lengths ie., 1310 & 1 550nm. The average of these two measurements gives the real
value of the fiber under test. These two measurements are compared to specific value to determine
acceptable as per approved SAT procedure.
8.6.6 This test will be mainly used to verify the continuity and the length of the cable.
Power Meter Method (End to End Test)
8.6.8 Test and Commissioning of Fiber cabling system along with Client and consultant / ADDC
representative
8.7 Inspection and Testing
8.7.1 Inspection and Test Plan for Cable Installation shall be conducted in reference to attached ITP and
in conjunction with relevant approved ITP’s
9 HEALTH & SAFETY
The works will be carried out according to the requirements set out in the Project Specific Safety Plan
(PSSP). For further details refer to the PSSP.
Page 10 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
A risk assessment analyzing the potential risks and hazards, and their mitigation measures is
attached to this Method Statement in Appendix D.
12 ORGANISATIONAL RESPONSIBILITIES
12.1 The Sr. Project Manager / Project Manager
• Liaise with Client / Consultant for execution of the works as per construction program.
• Ensure the works are carried out according to the specification and approved shop drawings.
Page 11 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
• Liaise and coordinate with subcontractors including MEP for the agreed sequence of works with
respect to the construction program.
• Be responsible for all interfaces and other communications as required during the execution of
all activities
• Review the method statements prior to execution and explain the same to his subordinates
ahead of the job plan
• Manage and lead his workforce to ensure good workmanship and a quality product.
• To ensure that project works are carried out in accordance with company policies and in
accordance with the requirements of the project specification and authorities compliances.
• To ensure that all the equipments required executing the works according to the construction
program are available, in good condition, and provide any additional equipment that might be
required.
• Attend the Client & Consultant meeting and monthly progress meeting.
• Responsible for finalising ITP’s as per Hold point requirement along with method statement
submission
• Ensure that all the inspections at site are following the Method Statement and conducted by site
teams.
• Ensure the use of latest drawings is being used at site and available for use at site.
• Ensure material Inspection for all the permanent materials received at site.
• Liaise with the laboratory team to ensure compliance of materials and tests to the project
specification.
• Monitor the logs developed and updated by document control and other sections
• Organize and conduct the training/Induction programme to the project staff
• Review, analyse the Non-Conformance Reports and appraise the Project Management Team
for improving operational efficiency
• Attend Engineer/Employer QA/QC meetings
• Liaise with the Engineer for any issue to be resolved at site with regard to quality of the work.
• Assist the Sr. QA/QC Manager – C&ID to manage the internal and external audits in project
liaising with the Corporate/divisional QHSE department.
• Coordinate with Engineer/Employer QA/QC team for quality matters resolution on day to day
construction activities
• Review the project QA/QC reports and submits to the Quality Manager/Engineer.
• Monitor the QA/QC department performance on a regular basis.
• Raise NCR (CAPAR) once when the activities are deviated from the project specifications and
approved documents
Page 13 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
• Provide the necessary information, material, equipment, and machinery to subordinates to carry
out the job.
• Maintain proper survey records.
• Coordinate the preparation of survey data and sketches in an agreed format for transfer/
handover of information.
• Verify and arrange the necessary calibrations of survey instruments.
• Control subcontractor’s surveyor’s daily work and data.
12.11 Flagman
• Ensure to control the traffic of all vehicle movement
• Safe way control of Heavy equipments in coordination with HSE.
12.12 Builders
• To ensure the work is carried out as per the approved shop drawing and submittals
• Responsible to carry out all the activities as per Quality and HSE standards
• Coordination and communication between client/ consultant/ contractor
Page 14 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
14 DISTRIBUTION
• Project Manager
• Construction Manager
• Site Manager
• Consultant
• Asst. QA/QC Manager
• QA/QC Engineer
• Safety Officer
• Sub-Contractor - if required
15 STATEMENT OF INTENT
CSCEC are committed to comply with national and local regulations and the Client’s requirements to
ensure that the project is delivered on time within budget and to the agreed quality requirements. The
consultant will be notified of any changes required on site and approval will be obtained prior to the
works being carried out.
APPENDIX
Appendix A: Check List
Appendix B: Inspection Test Plan
Appendix C: Quality Risk Matrix
Appendix D: Risk Assessment
Page 15 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
APPENDIX A
CHECK LIST
Page 16 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
INTEGRATED MANAGEMENT SYSTEM FORMAT
Location: Date
Consultant’s Comments:
APPENDIX B
Page 17 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
ALDAR PROJECTS
INSPECTION AND TEST PLAN
PROJECT TITLE: BANIYAS NORTH DEVELOPMENT PHASE 3 PROJECT NO:P151106/2022/C002 DATE 21.11.2022
BNDP3-IN-CSCEC-P3C-EL-
CLIENT / PMC: ALDAR PROJECTS LLC CONSULTANT: MOTT MACDONALD LIMITED DOC. REF
XX-MS-EL-00005
CONTRACTOR: CHINA STATE CONSTRUCTION ENG’G CORP ME (LLC) SUBCONTRACT NO: N/A REV NO P00
SUBCONTRACTOR: HELIOPOLIS ELECTRIC CO ITP NO: 00005
Pre-qualification of
DESCRIPTION: FIBER OPTIC CABLE INSTALLATION Sub-contractor and TPI
QUALITY
REFERENCES
ITEM PROCESS FREQUENCY OF INSPECTION ACCEPTANCE CONTROL
(SPECIFICATION, METHOD COMPANY CONSULTANT CONTRACTOR SUBCON TPI
No. DESCRIPTION TEST (Mode of CRITERIA FORMS DATA
STATEMENTS, OTHERS
measurement)
1 Documentation Phase
Gen. Requirements
SECTION 013300 -
Shop Drawing Approved upon
1.1 Prior to Start the Submittal Procedures Approved shop H R/A H H -
Approval review
activity Doc. Review Rev. 0 drawing
Gen. Requirements
SECTION 013300 -
Method Statement Approved
1.2 Prior to Start the Submittal Procedures H R/A H H -
Approval Approved upon Method
activity Doc. Review Rev. 0
review Statement
Gen. Requirements
SECTION 013300 -
Material Submittal Approved
1.3 Prior to Start the Submittal Procedures H R/A H H -
Approval Approved upon Material
activity Doc. Review Rev. 0
review Submittal
Gen. Requirements
SECTION 013300 -
1.4 QCP Prior to Start the Approved upon Submittal Procedures Approved QCP H R/A H H -
activity Doc. Review review Rev. 0
2 Pre-Construction Phase
LEGENDS:
W – Witness H – Hold R – Review A – Approval S – Surveillance TPI – Third Party Inspector Agency
ALDAR PROJECTS
INSPECTION AND TEST PLAN
ADWEA/ADDC/AADC A
Materials Receiving As per approved STANDARD S-AAA- MIR/Delivery
Testing/Doc. H W/A H H -
2.1 at Site Each Delivery Material Submittal CAB-FOC (Rev.0-2011) Notes/Test
Review
Reports
ADWEA/ADDC/AADC
As per
STANDARD S-AAA-
2.2 Material Storage manufacturer W S W H -
Each Delivery Visual CAB-FOC (Rev.0-2011) MSDS
recommendation
ADWEA/ADDC/AADC
Free from Lumps
Development of Testing/Doc. STANDARD S-AAA-
2.3 1500CM or unwanted Test Reports H W/A H H -
Stockpile Review CAB-FOC (Rev.0-2011)
material
3 EXCAVATION WORKS
ADWEA/ADDC/AADC
After the
As per approved STANDARD S-AAA-
3.1 Survey Setting-out Excavation Each Visual/Technical Survey Report W W/A W H -
drawing CAB-FOC (Rev.0-2011)
Sub Station
ADWEA/ADDC/AADC
Formation to be
Dewatering STANDARD S-AAA-
3.2 Each Location Visual dried, Approved Checklist W S W H -
(Where applicable) CAB-FOC (Rev.0-2011)
MSRA
4 SAND BEDDING
Bedding Sand
Approved shop
ADWEA/ADDC/AADC H H
4.1 Laying & Each area Visual STANDARD S-AAA-CAB- Check List W W/A W H -
drawing
Compaction FOC (Rev.0-2011)
6 BACKFILLING
ADWEA/ADDC/AADC
Approved Shop
6.1 Sand Over cable Each span Visual STANDARD S-AAA-CAB- Checklist W A W H -
Drawing S
FOC (Rev.0-2011)
LEGENDS:
W – Witness H – Hold R – Review A – Approval S – Surveillance TPI – Third Party Inspector Agency
ALDAR PROJECTS
INSPECTION AND TEST PLAN
ADWEA/ADDC/AADC
H S H
Installation of Cable Each Length of Approved Shop STANDARD S-AAA-CAB-
6.2 Visual WIR/Checklist W A W H -
Cover Tiles Installation Drawing FOC (Rev.0-2011)
ADWEA/ADDC/AADC
H H
Installation of Each Length of Approved Shop STANDARD S-AAA-CAB-
6.3 Visual WIR/Checklist W A W H -
Warning Tape Installation Drawing FOC (Rev.0-2011)
ADWEA/ADDC/AADC H
H
Approved Shop STANDARD S-AAA-CAB- WIR
6.4 Final Backfilling Each span Visual Checklist W A W H -
Drawing FOC (Rev.0-2011)
in layers with compaction
ADWEA/ADDC/AADC H W H
Approved Shop STANDARD S-AAA-CAB-
6.5 Jointing of FO cable Each Cable Visual/Technical WIR/Checklist W A W H -
Drawing FOC (Rev.0-2011)
ADWEA/ADDC/AADC
H H
Termination of FO Approved Shop STANDARD S-AAA-CAB-
6.6 Each Termination Visual/Technical WIR/Checklist W A W H -
cable Drawing FOC (Rev.0-2011)
7 FO CABLE TEST
ADWEA/ADDC/AADC
Approves Test
7.1 OTDR Test Each Core / cable Testing STANDARD S-AAA-CAB- Test Report H W/A H H H
Procedure
FOC (Rev.0-2011)
8 Test reports
ADWEA/ADDC/AADC
Submission of Test After completion of Testing/Doc.
8.1 Code A & B STANDARD S-AAA-CAB- Test Reports H A H H -
Report Each work Review
FOC (Rev.0-2011)
LEGENDS:
W – Witness H – Hold R – Review A – Approval S – Surveillance TPI – Third Party Inspector Agency
Ref No. BNDP3-IN-CSCEC-P3C-EL-XX-
MS-EL-00005
Revision No. P00
Date: 21 November 2022
APPENDIX C
Page 18 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
QUALITY RISK MATRIX
Mitigation After mitigation
Past occurrence Prior mitigation action Effect Responsibility
action action plan Residual
Sr no Description of Risk Risk Type Risk Rating Remarks
Severity risk
Yes/NO Severity rating Probability LT/MT/ST Probability
rating
Quality Risk Direct
1.Engagement of competent supervisor
2.Production of coordinated shop drawings and
obtaining approval from engineer prior to
Deviation from specification execution of works.
A1 Yes Internal Major Likely 12 LT 3.Provision of training to supervisor and Project based management Major Rare 4
/approved drawings
execution staff prior to start of works
4.Use of control forms for inspection and
approvals
1. Engagement of competent supervisor.
2.Issuance of advance controlled copies of
production document if there is a minor design
change or issuance of stop work if there is
A2 Use of unapproved Materials Yes Internal Major Likely 12 LT major design change, Project based management Major Rare 4
Provision of trainings for supervision and
execution staff prior to execution of works.
Periodic audits on site based staff for document
usage.
1. Engagement of competent supervisor.
2.Issuance of advance controlled copies of
production document if there is a minor design
change or issuance of stop work if there is
major design change,
Provision of trainings for supervision and
A3 Use of unapproved drawings No Internal Major Likely 12 LT execution staff prior to execution of works. Project based management Major Rare 4
Periodic audits on site based staff for document
usage.
Use of control forms for inspection and
approvals.
RISK MATRIX
Severity
Probability
Insignificant(1) Minor(2) Moderate(3) Major(4) Catastrophic(5)
Rare(1) 1 2 3 4 5
Possible(2) 2 4 6 8 10
Likely(3) 3 6 9 12 15
Often(4) 4 8 12 16 20
Almost Certain (5) 5 10 15 20 25
Absolutely unacceptably high
15-35 Extreme Risk
Activity should not proceed in the current form
Unacceptably high risk activity
8-12 High Risk
To be modified to include remedial planning, action subject to
Acceptable but must be managed at 'As low as reasonably
4-6 Moderate Risk
practicable'
Acceptable without further action. No further action required
1-3 Low risk
unless escalation of risk is possible
APPENDIX D
RISK ASSESSMENT
Page 19 of 19
China State Construction Engineering Corporation (Middle East) (L.L.C.)
P.O.Box: 63932 Dubai, U.A.E. Tel: 04-4537268 Fax: 04-4537368
P.O.Box: 130933 Abu Dhabi, U.A.E. Tel: 02-6501566 Fax: 02-6501360
Risk Assessment Ref: BNDP3-IN-CSCEC-P3C-EL-
RISK ASSESSMENT XX-MS-EL-00005, Rev.P00
PROJECT: Baniyas North Development – Phase 3
Contractor : M/s. China State Construction Engineering Corporation Middle East LLC
Subcontractor: M/s Heliopolis Electric Company Rev No: 0
Client : M/s ALDAR PROJECT LLC Date: 06-11-2022
Activity : Installation of Fiber Optic Cables
Page 1 of 9
Company Name: China State Construction Engineering Corporation Middle East LLC.
Project Title: Baniyas North Development – Phase 3
Work Description: Installation of Fiber Optic Cables Date: 21.11.2022
Page 1 of 9 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
Risk Assessment Ref: BNDP3-IN-CSCEC-P3C-EL-
RISK ASSESSMENT XX-MS-EL-00005, Rev.P00
PROJECT: Baniyas North Development – Phase 3
Contractor : M/s. China State Construction Engineering Corporation Middle East LLC
Subcontractor: M/s Heliopolis Electric Company Rev No: 0
Client : M/s ALDAR PROJECT LLC Date: 06-11-2022
Activity : Installation of Fiber Optic Cables
Page 2 of 9
• Never work on live road without permit and adequate safety arrangements / Shadow
vehicles/TMA
• Provision of flag man and barricading while working adjacent to live road.
• 6 points- Helmet, Hi-Viz jacket/cover all with strips, hand gloves, safety shoe, safety glass
Working adjacent to moving and face mask
public vehicles - Hit by moving • Steel pins shall not be driven more than 15cm in the ground
vehicle, • Rebar caps shall be provided for the marker pins and warning tapes to be tied for
identification
Existing manholes, hidden
Survey and • Area shall be thoroughly inspected by the supervisor and the survey in charge before
cavities- Falling into unidentified
2 setting up work on 4 4 16 H engaging the workers. 1 3 3 L
cavities and manholes
• See the area and de mark the driving routes
site
Use of steel pins as survey • Check the identification both visually and by the existing drawings for any services or man
marker - Penetration injuries holes.
• Proper planning and necessary precautions should be taken prior to start survey work
Reptiles / desert insects - Snake • Site induction shall be carried out for the workers and adequate information must be given to
or reptile bites, stings from insects all about the site and the possible risk associated with task and location
• Do not touch anything with bare hand
• Do not rest or sit or lie down on sandy area / near bushes
• Provision of drinking water, toilets, shaded area etc. shall be ensured. Additional control
measures shall be ensured for cavity prone areas.
• Mechanical aids to be used for offloading the blocks work materials
• Blocks shall be stacked on proper pallets and secured with straps from the manufacturer
• Block shall be stored in safe manner on designated area with levelled and compacted ground
and no double stacking allowed.
• 3rd party trained banks man shall be deployed with all moving plants to control man-machine
Material shifting / Falling materials interfaces
Offloading, Slip trip fall
Sharp edges • Loading and unloading from site and Motor Vehicles Each workman shall be instructed for
stacking and
shifting of Heavy manual labour and manual the proper method of loading and unloading from site and equipment vehicles, and provided
3 materials. handling 3 4 12 H with necessary equipment for safety. Supervisors shall ensure that the required number of 1 3 3 L
Loading and un- Caught between load and vehicle workmen based on the weight and the distance involved in each job is available and
loading of Minor or major injuries, crush engaged for the particular job
injury, Back ache • Ensure designated access/egress made safe for the people, vehicle, plant and machinery.
materials. Traffic accidents
• Ensure proper barricade along with signage provided.
• Standard stair access shall be provided to access and exit.
• Separate access and exit to be provided for vehicle movement.
• Pickup truck should park inside the site at safe area away from the excavation premises.
• HSE induction for drivers
Page 2 of 9 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
Risk Assessment Ref: BNDP3-IN-CSCEC-P3C-EL-
RISK ASSESSMENT XX-MS-EL-00005, Rev.P00
PROJECT: Baniyas North Development – Phase 3
Contractor : M/s. China State Construction Engineering Corporation Middle East LLC
Subcontractor: M/s Heliopolis Electric Company Rev No: 0
Client : M/s ALDAR PROJECT LLC Date: 06-11-2022
Activity : Installation of Fiber Optic Cables
Page 3 of 9
Page 3 of 9 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
Risk Assessment Ref: BNDP3-IN-CSCEC-P3C-EL-
RISK ASSESSMENT XX-MS-EL-00005, Rev.P00
PROJECT: Baniyas North Development – Phase 3
Contractor : M/s. China State Construction Engineering Corporation Middle East LLC
Subcontractor: M/s Heliopolis Electric Company Rev No: 0
Client : M/s ALDAR PROJECT LLC Date: 06-11-2022
Activity : Installation of Fiber Optic Cables
Page 4 of 9
Page 4 of 9 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
Risk Assessment Ref: BNDP3-IN-CSCEC-P3C-EL-
RISK ASSESSMENT XX-MS-EL-00005, Rev.P00
PROJECT: Baniyas North Development – Phase 3
Contractor : M/s. China State Construction Engineering Corporation Middle East LLC
Subcontractor: M/s Heliopolis Electric Company Rev No: 0
Client : M/s ALDAR PROJECT LLC Date: 06-11-2022
Activity : Installation of Fiber Optic Cables
Page 5 of 9
• Competent cable winch operator with valid 3rd party certificate only allowed to operate cable
winch.
• Inspect rigging and winch at beginning of each shift.
• The condition of guage shall be good.
• Do not exceed the maximum pressure stated in the hydraulically driven winch. Trained
Winch Operator only allowed for the activity.
Damage of wire sling while pulling • Ensure the stability of cable rollers especially the corner ones.
Detachment of pulling eye from • Personnel who are responsible for hand signals are clearly visible in view of the operator and
Cable Pulling the cable while pulling. that the signals to be used are thoroughly understood by everyone.
6 (using winch) Movement of Cable Trailer and 4 4 16 • While pulling cable through the ducts, ensure that the ducts are clean and conduct mandrel 1 3 3 L
H
Cable Winch from its place test in order to avoid any nip points in the cables.
Nip points in the cable • Protect both ends of the laid cables in proper manner until the jointing activities
Pinch points • Ensure First Aid and Fire Extinguishers.
• Always use "hand-over-hand" techniques, being careful to keep hands and clothing away
from winch drum and rollers.
• Do not allow personnel near winch line under tension. Keep safe distance.
• Check suitable I-Shackle. Valid test certificates for the same and winch are mandatory.
• Wear appropriate PPE like dust mask, Goggles.
• Clean the wind screen, no curtains or blinds in the cabins and driver shall have proper vision
outside the cabin.
Loose soil at the side of • Competent operators with valid 3rd party certificate and certificate and licence only allowed to
excavation operate plants.
Uncontrolled equipment • Maintain barricading around excavation.
movement • Provide Flagman to control movement of plants
Excavation, Back
7 Untrained and uncertified 4 4 16 H • Prior to excavation spraying water to reduce dust at work site. 1 4 4 M
filling equipment • Wear appropriate PPE like dust mask, Goggles.
Fatality • Carry out pre use inspection of plants
Equipment falling in to • All systems - brake, reverse alarm, revolving lights etc.. shall be fully operational.
excavations
• Valid 3rd party certificate of plant and Registration shall be available
Page 5 of 9 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
Risk Assessment Ref: BNDP3-IN-CSCEC-P3C-EL-
RISK ASSESSMENT XX-MS-EL-00005, Rev.P00
PROJECT: Baniyas North Development – Phase 3
Contractor : M/s. China State Construction Engineering Corporation Middle East LLC
Subcontractor: M/s Heliopolis Electric Company Rev No: 0
Client : M/s ALDAR PROJECT LLC Date: 06-11-2022
Activity : Installation of Fiber Optic Cables
Page 6 of 9
Major and minor injuries, property • Ensure the continuous monitoring and proper supervision
damage
Use of damaged hand tools • All hand tools shall have valid color code indicating its in sound condition for use
Sharp edges of the hand • Operatives shall be skilled and well versed in use of hand tools
tools • Remove the damaged hand tools from use.
• Store keeper shall issue the inspected and color-coded hand tools to site
Use of wrong tool for the job
8 Use of hand tools 4 3 12 H • Hand tools with sharp edges shall be used with sufficient care (trowels etc.) 1 3 3 L
(such as spanner used for • Hammers shall be checked prior to each use, the chances of its head detaching from its
hammering etc.) body shall be vital part to be looked into for compliance
Penetration injury from • Work location shall be free from obstructions and trip hazard
piercing of hand
• Trained operators’ operators only allowed to operate power tools
• Disconnect when not in use
• Store in safe manner after use
• Trailing cables routed in safe manner to avoid cable damage and trip hazard
• Barricade the area
• ELCB in the circuit
• Proper insulation of all cables
• DBs/Generators used for power tools shall be equipped with 30mA RCD device.
9 4 4 16 H • All power tools shall be inspected daily, monthly and color-coding system shall be 1 3 3 L
Use of power implemented.
tools Use of electrically operated tool, • Electrical power tools shall be implemented with PAT on quarterly basis.
Rotating parts • Task specific PPEs shall be used.
Electric shock, Major Injury, • Fire extinguishers available in the area
Entanglement, Fire • All flammables and waste generated removed from site
• Disconnect power when changing bits
• No repair allowed on tools
• Damaged tools not allowed to be used on site, return them to store.
• All guards in place
• 3rd party certificate of generator shall be provided and posted
• 30mA RCD to be provided with DBs assigned for power tool operation
• Trip-tray and secondary bunds shall be provided to avoid spillage
• Spill kit shall be provided with all generators.
• Inspection and color coding shall be provided
Use of temporary • Approved electrician details to be posted
Electricity, Noise, Land • Safety signs shall be installed
electrics - electric contamination and air pollution
• Earthing shall be ensured
Generator for hazards.
• All rotating parts covered and hot surfaces protected from contact and fire
Electric shock
10 power supply Burn injury
3 5 15 H • Fire extinguisher available 1 4 4 M
with cabling and Smoke allergies • Barricade the area
Fire / Explosion • Competent persons to operate
DBs • No repair / modifications on site
Hearing problems
• No work / fueling while engine is running /hot
• Appropriate PPE like ear plug to be used
• Inspect and tag as per current color coding
• Faulty generator not to be used
• By maintaining the work equipment at regular interval to reduce the noise produced by the
equipment.
Page 6 of 9 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
Risk Assessment Ref: BNDP3-IN-CSCEC-P3C-EL-
RISK ASSESSMENT XX-MS-EL-00005, Rev.P00
PROJECT: Baniyas North Development – Phase 3
Contractor : M/s. China State Construction Engineering Corporation Middle East LLC
Subcontractor: M/s Heliopolis Electric Company Rev No: 0
Client : M/s ALDAR PROJECT LLC Date: 06-11-2022
Activity : Installation of Fiber Optic Cables
Page 7 of 9
• Prepare a lifting plan and get approval for all heavy lifting
• For lifting of cabins, spreader beams to be used.
• Crane will have a valid 3rd party certificate and fitted with warning aid i.e., Safe Load
Indicator, anti-two block system, reverse Alarm/Revolving Lights.
Uncertified crane and lifting • Operator will have a valid 3rd party competency certificate in addition to valid driving license.
accessories • Crane will be positioned on levelled and stable ground fully extended outriggers resting on
. load spread base plates/pad.
Untrained operator and rigger
• Certified Riggers and Banks Men will control the Rigging and Signalling to the operator.
Un compacted terrain
Overload lifting • All Lifting Slings with inspection certificates will be available with current colour code. Third
Property damage and serious party certified Lifting Supervisor Will be made available.
Lifting operation – injuries • Area will be barricaded; walkways and designated routes will be established and proper sign
13 Lifting of Cable Overturning of Equipment 4 4 16 H board will be in place. 1 4 4 M
property damage and fatality
Drum • OSHAD SF CoP 34 shall be complied.
resulting
Overturning of Equipment • Working areas will be properly cordoned off and proper signboard will be in place.
property damage and fatality • During crane operation maintain safe distance of the boom and counter weight from adjacent
resulting plants and structure.
Overturning of Equipment • Load being lifted will be controlled by providing Tagline.
property damage and fatality • Load shall not be lifted above personnel
resulting • Sudden or jerky movement will be avoided.
• Personnel shall remain in safe distance from the load.
• Authorized and designated rigger only will give signal to the operator
• Lifting operation will be STOPPED when wind speed exceeds 36 kmph /19 knots
• Project lifting plan shall be developed and followed after approved from MML
Page 7 of 9 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
Risk Assessment Ref: BNDP3-IN-CSCEC-P3C-EL-
RISK ASSESSMENT XX-MS-EL-00005, Rev.P00
PROJECT: Baniyas North Development – Phase 3
Contractor : M/s. China State Construction Engineering Corporation Middle East LLC
Subcontractor: M/s Heliopolis Electric Company Rev No: 0
Client : M/s ALDAR PROJECT LLC Date: 06-11-2022
Activity : Installation of Fiber Optic Cables
Page 8 of 9
• Appointed person for lifting shall be appointed with valid 3rd party certificate from ADM
approved service provider
• The crane and lifting equipment’s, lifting gears and tackles shall be inspected and certified by
ADM approved service provider.
• PTW system for lifting shall be implemented
• Crane more than 10 years old shall be provided with NDT certificate
• Trained lifting crew such as lifting supervisor, rigger, operators and banks man shall be
deployed.
• Provision of safe working system, Information, instruction, supervision.
• Aclimatisation
• Arrange job rotation, dequate rest should be provided, provide adequate cold water to drink.
• Provision of PPE and its proper usage.
• Electrolyte solutions should be provided
Heat related illnesses Heat
stroke, Nausea, head ache and • Mid day break rule strictly complied, no work in open areas between 12.30 to 3pm during 15 th
even fatality. June to 15th Sep as per government order.
Working in hot Heat exhaustion due to loss of • Provide shelter near the work area for taking breaks between the workEnsure the continual
14 5 4 20 H 1 4 4 M
and humid climate body fluids, Heat cramp, Heat monitoring and proper supervision.
rashes
• Make sure there is heat stress safe work plan with reasonable working hours and
communicated to all.
• Ensure provision of first aid facility
• Arrange adequate supervision
• Identify early symptoms of heat illness
• Educate workers to monitor urine colour by individuals, dark colour indicates dehydration
No lone working
Page 8 of 9 Appendix 5
ALDAR OSH/EHSMS Rev 06/ 01-07-2019
Risk Assessment Ref: BNDP3-IN-CSCEC-P3C-EL-
RISK ASSESSMENT XX-MS-EL-00005, Rev.P00
PROJECT: Baniyas North Development – Phase 3
Contractor : M/s. China State Construction Engineering Corporation Middle East LLC
Subcontractor: M/s Heliopolis Electric Company Rev No: 0
Client : M/s ALDAR PROJECT LLC Date: 06-11-2022
Activity : Installation of Fiber Optic Cables
Page 9 of 9
Acceptable but must be managed at “As Low As Reasonably Practicable” (ALARP) Activity or process can operate subject to management
4–6 Moderate Risk and / or modification
Acceptable without required further action
1 -3 Low Risk
No action required unless escalation of risk is possible
Hierarchy of Control (Controls identified may be a mixture of the hierarchy in order to provide minimum operator exposure):
Elimination Eliminate the hazard.
Substitution Provide an alternative that is capable of performing the same task and is safer to use.
Administrative Controls Develop policies, procedures practices and guidelines, in consultation with employees, to mitigate the risk. Provide training, instruction and supervision about the hazard.
Personal Protective Equipment Personal equipment designed to protect the individual from the hazard.
Signature: Signature:
Company’s Stamp: