DC Atrium Meeting June 10

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

DC Atrium meeting June 10, 2024 2:00 PM MEPF

1. Aconex uploaded on DAR


2. Two weeks activities for dimming layout
3. Removal of Fire Hose cabinet during walk thru by ST last week was already instructed
4. Markings already have based on the reference center line on LO1 at ceiling
5. Updating of photos on MEPF reports there should be no recycling of pictures
6. To check the connection of cove light on the walls first fix was installed and walls are all close
7. Ongoing remarks on the report should be replace and indicate date to complete.
8. According to MDCC there are marking on center line wall.
9. Arcadis want to know the balance of Volume damper and date delivery at the site
10. Arcadis want to know when will be the request of opening on ceiling for testing installation of
dimmer lights etc.
11. Status of a 200mm dia PVC pipe Downspout needed to install acoustic insulation at L01.
12. At L01 all walls should have all MEPF services install which will be close as per commitment date
which was on June 6, 2024.
13. MEPF report was STOPPED by Adolf due to recycled report, no progress reports
14. WIR was commented by Arcadis QAQC due to the termination of flexible conduits on trunking
which was not properly fix.
15. Status of Panel board location and routeing of feederlines.
16. Removal of temporary zocalo at ground floor which was used as temfacil.
17. Status of Smoke extracts installation at L01 and ground floor.
18. SV1 signed off on wall & elevation not yet approve at lower ground.
19. To validate all plumbings installation at SV2.
20. Specs of Sanitary fixtures for SV2 which MCC will supply
21. To finish Sealant on all pipes that runs thru wall at Ground & L1 lobby toilets etc.
22. To instruct all Cleaning of area updating the subcon responsibility.
23. Client Walk thru 9:30am June 11, 2024, System engr’s and ABSSI representative assigned at
Atrium must attend on this walk thru.

MDCC Issues
1. All Enclosure of walls and ceiling must have WIR submitted
2. Lift Lobby L01 priorities to check that all MEPF services at the site.
3. To confirm the all MEPF services are installed in Mock up vanity counter.
4. To removed all lighting fixtures at Atrium area which was temporary supply during FSIC.
5. Access panel for mock up zone 3 by MDCC
6. Provide shopdrawing on the portion where Fire hose cabinet located which at the back of it is the
EE room location is at the ground floor.
7. Advice MCC subcons not to remove the ceiling support at L1 zone 4 which can cause sagging of
ceiling.
8. For Relocation of subcons Fabrication at L2 zone 1.

You might also like