0% found this document useful (0 votes)
18 views7 pages

Problem RR

Problem and solution on Round Robin Algorithm

Uploaded by

dhavan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views7 pages

Problem RR

Problem and solution on Round Robin Algorithm

Uploaded by

dhavan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Consider the set of 5 processes whose arrival time and burst time are given below-

Process Id Arrival time Burst time

P1 0 5

P2 1 3

P3 2 1

P4 3 2

P5 4 3

If the CPU scheduling policy is Round Robin with time quantum = 2 unit, calculate the
average waiting time and average turn around time.

Solution-

Gantt Chart-

Ready Queue-
P5, P1, P2, P5, P4, P1, P3, P2, P1

Now, we know-
 Turn Around time = Exit time – Arrival time
 Waiting time = Turn Around time – Burst time

Process Id Exit time Turn Around time Waiting time

P1 13 13 – 0 = 13 13 – 5 = 8

P2 12 12 – 1 = 11 11 – 3 = 8

P3 5 5–2=3 3–1=2

P4 9 9–3=6 6–2=4

P5 14 14 – 4 = 10 10 – 3 = 7

Now,
 Average Turn Around time = (13 + 11 + 3 + 6 + 10) / 5 = 43 / 5 = 8.6 unit
 Average waiting time = (8 + 8 + 2 + 4 + 7) / 5 = 29 / 5 = 5.8 unit

Problem-02:

Consider the set of 6 processes whose arrival time and burst time are given below-

Process Id Arrival time Burst time

P1 0 4

P2 1 5

P3 2 2
P4 3 1

P5 4 6

P6 6 3

If the CPU scheduling policy is Round Robin with time quantum = 2, calculate the
average waiting time and average turn around time.

Solution-

Gantt chart-

Ready Queue-
P5, P6, P2, P5, P6, P2, P5, P4, P1, P3, P2, P1

Now, we know-
 Turn Around time = Exit time – Arrival time
 Waiting time = Turn Around time – Burst time
Process Id Exit time Turn Around time Waiting time

P1 8 8–0=8 8–4=4

P2 18 18 – 1 = 17 17 – 5 = 12

P3 6 6–2=4 4–2=2

P4 9 9–3=6 6–1=5

P5 21 21 – 4 = 17 17 – 6 = 11

P6 19 19 – 6 = 13 13 – 3 = 10

Now,
 Average Turn Around time = (8 + 17 + 4 + 6 + 17 + 13) / 6 = 65 / 6 = 10.84 unit
 Average waiting time = (4 + 12 + 2 + 5 + 11 + 10) / 6 = 44 / 6 = 7.33 unit

Problem-03:

Consider the set of 6 processes whose arrival time and burst time are given below-

Process Id Arrival time Burst time

P1 5 5

P2 4 6

P3 3 7

P4 1 9
P5 2 2

P6 6 3

If the CPU scheduling policy is Round Robin with time quantum = 3, calculate the
average waiting time and average turn around time.

Solution-

Gantt chart-

Ready Queue-
P3, P1, P4, P2, P3, P6, P1, P4, P2, P3, P5, P4

Now, we know-
 Turn Around time = Exit time – Arrival time
 Waiting time = Turn Around time – Burst time

Process Id Exit time Turn Around time Waiting time

P1 32 32 – 5 = 27 27 – 5 = 22
P2 27 27 – 4 = 23 23 – 6 = 17

P3 33 33 – 3 = 30 30 – 7 = 23

P4 30 30 – 1 = 29 29 – 9 = 20

P5 6 6–2=4 4–2=2

P6 21 21 – 6 = 15 15 – 3 = 12

Now,
 Average Turn Around time = (27 + 23 + 30 + 29 + 4 + 15) / 6 = 128 / 6 = 21.33 unit
 Average waiting time = (22 + 17 + 23 + 20 + 2 + 12) / 6 = 96 / 6 = 16 unit

Problem-04:

Four jobs to be executed on a single processor system arrive at time 0 in the order A, B,
C, D. Their burst CPU time requirements are 4, 1, 8, 1 time units respectively. The
completion time of A under round robin scheduling with time slice of one time unit is-
1. 10
2. 4
3. 8
4. 9

Solution-

Process Id Arrival time Burst time

A 0 4

B 0 1

C 0 8
D 0 1

Gantt chart-

Ready Queue-
C, A, C, A, C, A, D, C, B, A