Akarohid 2017
Akarohid 2017
Akarohid 2017
Yuwadee Akarohid
Supervisor: Dr. Ali Arefi
Murdoch, 2017
© Murdoch University 2017
Author’s Declaration
I declare that this thesis is my own account of my research and contains as its main content
work which has not previously been submitted for a degree at any tertiary education institution.
[Author]
ii
Abstract
mission to arrange International standards. IEC TS 62257 introduced herein is one of those
series. It concerns about rural electrification which is further away from the national main
power line. It is very expensive to get a few single users to utilise a grid to meet cost-effective.
Therefore the stand-alone electrical systems are taken into account to serve better situations. In
these days, rural electrification is played one of the important strategies to maximise comfort to
This thesis focuses on overview of IEC TS 62257. The project purpose concerns to five
significant points. Firstly, to investigate and enable the choice of renewable energy based
electrification systems to meet the requirements of customers in the field of decentralised rural
electrification project. Secondly, to provide a technical specification for renewable energy and
hybrid systems. Thirdly, to evaluate the minimum sufficient requirements, relevant to the field
of application that is: renewable energy and hybrid off-grid systems corresponding to the high
standard safety. Fourthly, to review the methodology in the standard IEC TS 62257 to achieve
the best technical and economic conditions for acceptance, operation, maintenance and
replacement of equipment and complete system life cycle. Lastly, to learn about the combination
To attain an achievement of the five purposes as above mentioned, Rottnest Island case study
was taken as an example of rural or remote Electrification in order to compare it with IEC TS
62257 series in term of similarity and difference between them. Although this project is
Regarding to the most efficiency of the rural power project, the selection in which part of IEC
iii
Acknowledgements
First, I would like to thank my supervisor, Dr. Ali Arefi for his advice, expertise, and assistance
during this thesis project. I would also like to thank Dr. Martin Anda, for his arrangement of
Rottnest Island visit for me to do a case study. Thanks also to Dr. GM Shafiullah and Dr.Farhad
Shahnia for their knowledge in the electrical system during Rottnest Island site visit. It was
helpful to my thesis. I would also like acknowledge and appreciate Mr. Dino Ajid who worked
for Programmed Facility Management on Rottnest Island, for his answers about the setting up of
Rottnest Island power system and the Island standard, Laura Senge who worked for the Rottnest
I also would like to thank my family and friends who have encouraged and supported me
iv
Dedication
I dedicate this thesis to my family, my teachers and my friends who have supported me along
v
Table of Contents
Author’s Declaration .................................................................................................................... ii
Abstract ....................................................................................................................................... iii
Acknowledgements ..................................................................................................................... iv
Dedication .................................................................................................................................... v
Table of Contents ....................................................................................................................... vii
List of Figures ............................................................................................................................. xi
List of Tables.............................................................................................................................. xii
List of Abbreviations.................................................................................................................. 13
Chapter 1 Introduction ......................................................................................................... 15
1.1 Objectives of this thesis ...................................................................................... 15
1.2 The connection of IEC TS 62257 series ............................................................. 16
Chapter 2 Background ......................................................................................................... 17
2.1 The importance of IEC TS 62257 series ............................................................. 17
2.2 Decentralized rural electrification (DRE) ........................................................... 17
2.3 The difference in developing countries and developed countries ...................... 17
2.4 Case Study – Rottnest Island............................................................................... 18
2.5 Summary ............................................................................................................. 19
Chapter 3 To meet the customers requirement in decentralised electrification ................... 20
3.1 Off-grid electricity: which entrance to select? .................................................... 20
3.1.1 Master plan.......................................................................................................... 20
3.1.2 Remote electrification requiring a variety of systems ......................................... 21
3.1.3 Category of demand ............................................................................................ 21
3.1.4 Decentralized systems ......................................................................................... 21
3.1.5 Place and role of initial studies in a dispersed rural electrification project ......... 23
3.2 Summary ............................................................................................................. 23
Chapter 4 Minimum sufficient requirements to the field of application corresponding
to high standard safety ........................................................................................ 25
4.1 Useful description of a distribution subsystem ................................................... 25
4.1.1 Presentation of the costs ...................................................................................... 25
4.1.2 Data to be collected ............................................................................................. 26
4.2 Protection against electrical hazards ................................................................... 27
4.2.1 Protection against overcurrent............................................................................. 27
4.2.2 Protection against overload currents ................................................................... 27
4.2.3 Protection against short-circuit ........................................................................... 28
4.2.4 Protection against risk of fire .............................................................................. 29
vii
4.2.5 Protection against effects of lighting................................................................... 29
4.2.6 Protection against overvoltage ............................................................................ 29
4.2.7 Protection against direct lightning ...................................................................... 29
4.3 Over-current protective devices .......................................................................... 30
4.3.1 Earth termination (electrode) of lightning protection system. ............................ 30
4.4 Composition of a micro-power plant .................................................................. 31
4.4.1 Interconnection of generators .............................................................................. 31
4.5 Composition of a micro-grid ............................................................................... 31
4.5.1 Connections and accessories ............................................................................... 32
4.5.2 Isolating devices .................................................................................................. 32
4.5.3 Housing ............................................................................................................... 35
4.5.4 Requirements for dc parts of installation ............................................................ 35
4.5.5 Requirements for ac parts of installation ............................................................ 36
4.6 Voltage drop........................................................................................................ 36
4.7 Specific rules to wiring systems buried in earth ................................................. 36
4.8 User interface ...................................................................................................... 37
4.8.1 General operating conditions .............................................................................. 37
4.9 Summary ............................................................................................................. 37
Chapter 5 The methodology to achieve the best technical and economic condition ........... 39
5.1 Organizational issues .......................................................................................... 41
5.2 Maintenance actions ............................................................................................ 41
5.3 Replacement factors ............................................................................................ 41
5.3.1 Replacing equipment........................................................................................... 42
5.4 Physical ingress protection.................................................................................. 43
5.5 Current total harmonic distortion (THD) ............................................................ 43
5.6 Colour Characteristics ......................................................................................... 44
5.7 Summary ............................................................................................................. 44
Chapter 6 The combination of diesel generator system and solar energy ........................... 45
6.1 Generator boundaries .......................................................................................... 45
6.2 Generator requirements ....................................................................................... 45
6.3 Equipotential bonding ......................................................................................... 47
6.4 Considerations due to operating temperature ...................................................... 47
6.4.1 Insulation............................................................................................................. 48
6.4.2 Fuse holders ........................................................................................................ 48
6.4.3 By-pass diodes .................................................................................................... 49
6.4.4 Blocking diodes................................................................................................... 49
6.4.5 Location and installation requirements ............................................................... 50
6.5 Location: accounting for shadow ........................................................................ 52
6.6 Selection and erection generator ......................................................................... 54
viii
6.6.1 Generator set sizing ............................................................................................. 55
6.6.2 Derating factors ................................................................................................... 55
6.7 Design of the erection site ................................................................................... 56
6.8 Ventilation........................................................................................................... 56
6.9 Fuel storage ......................................................................................................... 56
6.10 Summary ............................................................................................................. 58
Chapter 7 Rottnest Island case study ................................................................................... 60
7.1 System selection and design................................................................................ 60
7.2 Protection against electrical hazards ................................................................... 62
7.3 Generator- PV generators.................................................................................... 62
7.4 Selection of generator sets for rural electrification system ................................. 65
7.5 Ventilation (air intake cross-section, speed-inducting) ....................................... 66
7.6 Cross-section of power cables ............................................................................. 67
7.7 Battery management system of a generator ........................................................ 67
7.8 Micro-power System ........................................................................................... 67
7.9 Functional layout for a micro-plant..................................................................... 68
7.10 Interconnection of generators .............................................................................. 69
7.11 Micro-grids.......................................................................................................... 69
7.12 Integrated system – User interface ...................................................................... 69
7.13 Integrated system – User installation .................................................................. 70
7.14 Selection of PV- individual electrification system.............................................. 70
7.15 Selection of lamps and lighting appliances for off-grid electrification
systems ................................................................................................................ 71
7.16 Lighting service targets ....................................................................................... 71
7.17 Summary ............................................................................................................. 72
Chapter 8 Conclusion .......................................................................................................... 75
Chapter 9 Future work ......................................................................................................... 77
References .................................................................................................................................. 78
Appendix A 81
A.1 Rottnest Island power system diagrams .............................................................. 81
A.2 Rottnest Island PV modules ................................................................................ 84
A.3 Rottnest Island generator .................................................................................... 86
A.4 IP ingress ............................................................................................................. 87
ix
List of Figures
Figure 1 the connection of IEC TS 62257 standards (IEC 2015a) ............................................. 16
Figure 2 general configuration of an electrification network (IEC 2015b) ................................ 22
Figure 3 Micro-grid consisting of a single-phase feeder (IEC 2006a) ....................................... 32
Figure 4 Micro-grid earthing scheme (IEC 2006a) .................................................................... 33
Figure 5 interface for user installations was supplied from an ac or a dc source (IEC
2006b) ................................................................................................................. 34
Figure 6 interface for user installations were supplied locally from ac or dc sources (not
from a micro-grid) (IEC 2006b).......................................................................... 35
Figure 7 general electrical configuration of a collective electrification system (IEC 2008a) .... 45
Figure 8 General functional configuration of a PV system (IEC 2010) ..................................... 47
Figure 9 Blocking diode implementation (example) (IEC 2010) ............................................... 50
Figure 10 PV string wiring with minimum loop area (IEC 2010) ............................................. 53
Figure 11 Functional diagram of a radial structure for rural micro-grid .................................... 61
Figure 12 Configuration C and E –PV alone IES or CES – P< 500W – with inverter – d <
15 m (IEC 2010) ................................................................................................. 63
Figure 13 Configuration D and F – Hybrid IES or CES – PV generator + inverter and
another generator – d < 15 m (IEC 2010) ........................................................... 63
Figure 14 PV array diagram – multi-string case (IEC 2010) .................................................... 64
Figure 15 Micro-power system limits (IEC 2008c) ................................................................... 68
Figure 16 Example of functional layout for a micro-power plant supplying AC energy
(IEC 2008c) ......................................................................................................... 68
Figure 17 Interconnection configuration with AC bus only(IEC 2008c) ................................... 69
Figure 18 Protection of people in an installation supplied from a micro grid according to a
TN-C-S system (IEC 2006c) ............................................................................... 70
Figure 19 Rottnest Island power station overview ..................................................................... 81
Figure 20 Rottnest Island Power Station Control Network ........................................................ 81
Figure 21 Rottnest Island Authority Cable Survey L.V. Reticulation Single Line Diagram
1 of 2 ................................................................................................................... 82
Figure 22 Rottnest Island Authority Cable Survey L.V. Reticulation Single Line Diagram
2 of 2 ................................................................................................................... 82
Figure 23 Rottnest Island power Station Metering and Protection ............................................ 83
Figure 24 Rottnest Island Power Station .................................................................................... 83
Figure 25 First Solar Specification (Rottnest Island Solar Panel) .............................................. 84
Figure 26 Rottnest Island Solar farm ......................................................................................... 85
Figure 27 multi-string case PV at Rottnest Island ...................................................................... 85
Figure 28 Rottnest Island fuel storage........................................................................................ 86
Figure 29 Detroit Generator at Rottnest Island Power Station ................................................... 86
Figure 30 Cummim Generator at Rottnest Island power station ................................................ 87
Figure 31 IP ingress shown on BarTech switchboards at Rottnest Island power station ........... 87
xi
List of Tables
Table 1 Minimum set of data to be collected (IEC 2015d) ........................................................ 26
Table 2 Functions ensured by various types of user interface (IEC 2006b) .............................. 34
Table 3 Maximum acceptable voltage drop values in connections (IEC 2006c) ....................... 36
Table 4 Climate condition (example) (IEC 2006c) .................................................................... 37
Table 5 AOMR actions (IEC 2015f) .......................................................................................... 40
Table 6 General inputs and outputs to be considered for generator specification
(IEC 2008a) ......................................................................................................... 46
Table 7 Functions fulfilled by the technical room (IEC 2010) .................................................. 47
Table 8 Disconnecting means requirement in PV array installations (IEC 2010) ..................... 51
Table 9 Location of disconnection devices according to system configuration, where
required (IEC 2010) ............................................................................................ 52
Table 10 Examples of derating factors for generator sets (IEC 2008b) ..................................... 65
Table 11 Generator set permitted noise levels (IEC 2008b) ...................................................... 65
Table 12 Cross-section of power cables (IEC 2008b) ................................................................ 66
Table 13 Suggested minimum values for IP and IK (IEC 2008d) ............................................. 71
Table 14 The Principles of Lighting service performance assessment (IEC 2015g) ................. 72
xii
List of Abbreviations
AS Australian standard
CCT Circuit
GS General Specification
IF Identification file
IMOD_REVERSE The current a module can withstand the reverse direction to normal
IP Ingress protection
ISC ARRAY The short circuit current of a PV array at Standard test Condition
ISC MOD The short circuit current of a PV module or PV string at Standard test
Condition
ISC S-ARRAY The short circuit current of a PV sub-array at Standard test Condition
13
P Active power
PE Protective conductor
PV Photovoltaic
RE Renewable Energy
S Apparent power
VOC ARRAY The open circuit voltage at Standard Test Conditions of a PV array
VOC MOD The open circuit voltage of a PV module at the coldest expected
operating condition
14
Chapter 1 Introduction
This thesis overviews IEC TS 62257 standard series and has various aims. The first aim is to
investigate the choice of renewable energy based electrification systems that is able to meet the
requirements of customers in the field of decentralized rural electrification project (IEC 2015a).
Secondly, provide a technical specification for renewable energy and hybrid systems(IEC
2008c). Thirdly, evaluate the minimum sufficient requirements, relevant to the field of
application that is: renewable energy and hybrid off-grid systems corresponding to the high
standard safety (IEC 2015d). Fourthly, review the methodology in the standard IEC TS 62257
to achieve the best technical and economic conditions for acceptance, operation, maintenance
and replacement of equipment and complete system life cycle (IEC 2015f). Lastly, the author
would like to learn about the combination of diesel generator system and solar energy during the
project.
15
1.2 The connection of IEC TS 62257 series
Figure 1 is stated that IEC TS 62257 divided into two main pathways that is monitoring the
system and mechanical specification. In the series of this standard, there are sixteen books in
total. Each of these books is specified a different in content of rural electrification. The linkage
of them are such that: the controlling and execution (monitoring path) is included the standard
part 2 to part 6. The Mechanical specification path is involved the standard part 7 to 12. This
section is also allocated individual three groups of electrification system namely; Generators
from part 7 to 7-3, micro-system and integrated system in part 9-1 to 9-6 and lastly, lamp and
lighting appliances in part 12. Part 8-1, Selection of battery is based on the requirements from
part 7 to part 12. Hence it is located at the bottom of the flow diagram in figure 1. Part 1 of IEC
TS 62257 is stated the general introduction of this standard referred to every standard in the
series.
16
Chapter 2 Background
It is invented to direct and suggested to small renewable energy and hybrid systems for rural
project managers, system designers and technician to decide the correct system for the correct
venue, outline the network, execute the system and preserve the network (IEC 2015a).
connected to the central power urban zone. The functions were needed to be able to modify to
1. Spread towns with houses, DRE will support using standalone photovoltaic generators
(Transenergy).
2. For the intense of populations, then the electrification supply is given by solar, hydro, wind
rising as a developed country (S 2015). Developing Countries are the country that expertise
improvement for the first time (S 2015). If we discuss about developed countries, they are post-
industrial economies (S 2015). Consequently, The different between the two are being the rank
of the excellency of service and the demand energy magnitude that the client will be able to pay
17
2.4 Case Study – Rottnest Island
Rottnest Island is located 19 kilometres off the coast of Fremantle in Western Australia
(ExperiencePerth.com 2017). It is a destination for tourist attraction near Perth, the capital city
Since the electrification system in Rottnest is off-grid to the main land. It is then an excellent
place to use for a study case to this thesis project. Rottnest Island electrification is relied on
Australian standard ASN3000. Hence after been studied on IEC TS 62257, it is become an
opportunity to observe the similarities and any differences between existed power system on the
Phenomenon solar and constant wind resource is described as Rottnest Island weather condition
(Australia 2017). The solar farm and wind turbine are empowered to meet 45% of the island’s
8000 photovoltaic modules are connected on a secure array (Australia 2017). 98 percent
performance is usually in the morning. The production of power form those modules are 500
kW (Australia 2017). A 600 kW Enercon wind turbine is produced energy that chopping the
solar energy. If wind energy is increased, the solar energy is then decreased. The seven diesel
generator is produced energy during night time and when renewable source is not given energy
to meet the need. 18000L truck is brought in diesel which was shipped from the mainland. 20
inverter is converted ac to dc and dc to ac for wind to utility grid as well as dc to ac for solar to
utility grid. The Electricity was fed into the Island cable using an underground distribution
system.
18
2.5 Summary
The intention of IEC TS 62257 was to support Renewable Energy Engineers, project managers,
system designers and technician to decide the correct system for the correct venue, outline the
network, execute the system and preserve the network (IEC 2015a).
DRE is a power structure targeted to supply electricity to public, which stayed no power grid
connected to the central power urban zone. The functions were needed to be able to modify to
The different among the two are being the rank of the excellency of service and the demand
energy magnitude that the client will be able to pay for (IEC 2015a).
Rottnest Island’s electrification system has been chosen as a study case to the thesis. The Island
is relied on Australian standard ASN3000. The solar farm and wind turbine are empowered to
meet 45% of the island’s electricity demand from renewable sources (Australia 2017).
19
Chapter 3 To meet the customers
requirement in decentralised
electrification
3.1 Off-grid electricity: which entrance to select?
IEC TS 62257-1 is stated that predicting the target condition in the medium term (10
years) and long term (20 to 30 years) needed to consider the following;
1. Master plan for this region is built to outline the lowest life cycle cost solution (IEC
2015a).
2. Grid extension and independent system solution are taken into justification (IEC
2015a).
searched for the demand essential (IEC 2015a). The data from each village, urban
to receive the finest electrification which is judged the capital investment (IEC 2015a).
Decentralized system and GIS (graphical presentation of the master plan) is installed
cost-effectively (IEC 2015a). The village is identified by colour codes representing the
20
In term of Master plan, is prioritized for future arrangement of charge of electrification on
annually or 5 years period (IEC 2015a). The value of cost is taken as one of the most
important criteria (IEC 2015a). It is less significant in developed world but was vital in
Simulation is fluctuated all the applicable factors (IEC 2015a). The complete financial
analysis of the chosen network is received from there (IEC 2015a). The greatest cost-
effective solution is from economic calculation (IEC 2015a). The central of the village
2015a).
It is resulted that the cost per user to micro-grid was higher than the cost of the individual
is not cost-effective linked to national grids (IEC 2015a). It is depended on each remote area to
choose the most conventional electrification system to suit the area. Each remote area are not
randomly picked any system from all the existed product available.
Specific processes, isolated homes, collective facilities, business activities were those type of
21
2. Individual Electrification system (IES) is sent electricity to consumption spots (usually
CES is matched for rural as it is quite highly peopled areas (IEC 2015b).
IES is matched for rather thinly peopled areas and/or remote homes (IEC 2015b).
Moreover CES is for many users that incorporating three system namely;
- A demand subsystem with the in-house wiring and user’s electrical applications (IEC
2015b).
IES and CES is displayed the network similarly to the general configuration of an
22
The answer of CES or IES is justified through calculation the discount (IEC 2015b). As well as
the appropriate sociogical and cultural characteristics is taken into consideration(IEC 2015b).
Other consideration is effected final decision (IEC 2015b). For example operating time of
gensets is often operated limited intervals throughout the day (IEC 2015b).
desires of the local residents such as their demand, their capacity and their prepared to pay for a
current energy deal. Once, all socio-economic data are accessible (IEC 2015b). Then those data
are properly collected and managed for this purpose (IEC 2015b). If this is not happened, the
suggestion of a preliminary study is recommended (IEC 2015b). That is the first stage in the
recognized of feasibility study for dispersed rural electrification project (IEC 2015b). The job is
to gain more understanding in the region through several project specialists. In term of the data
needed for technical evaluations, economic, financial and legal analyses and for carrying project
in general are then accessible (IEC 2015b). Some of those are then obtained from intellectual
3.2 Summary
The option to select off-grid electricity is based on a method called “master plan” (IEC 2015a).
The plan is outlined the lowest life cycle cost solution (IEC 2015a). Therefore it is needed to
study sociological, economical and geophysical data in the particular remote area to adjust
capital investment for the finest electrification (IEC 2015a). The most cost-effective solution is
received from economic calculation that the micro-power stations and micro-grids are run (out
23
Decentralised systems are divided into two categories namely; Collective Electrification
system (CES) and Individual Electrification systems (IEC 2015b). CES is electrified power
from one or multiple resource point (IEC 2015b). It is suited for highly population area (IEC
2015b). Whereas IES is usually supplied power with a single energy resource point (IEC
The electrification project is needed to follow the desires of the local residents and organisations
for a present energy deal (IEC 2015b). If the social-economic data are not accessible then a
preliminary study is suggested (IEC 2015b). It is helped to gain more understanding in the area
through several project specialists (IEC 2015b). Some of the data such as technical evaluation,
economic, financial and legal analyses are obtained from intellectual organization before
24
Chapter 4 Minimum sufficient
requirements to the field of
application corresponding to
high standard safety
4.1 Useful description of a distribution subsystem
Complete functions are achieved through a distribution subsystem (or rural micro-grid) (IEC
2015d). An electric power distribution service is delivered consisting of connecting the rural
micro-power plant to the application points (IEC 2015d). This function is assembled everything
(IEC 2015d). So it is guaranteed that the terminal application points generating from the rural
micro-power plant energy supply point, while adjusting to the energy requirements of the
different forms of customer (individuals, economic activities, local collective authorities, public
lighting, etc.) (IEC 2015d).Comprised and set up the Method is then observed rural micro-grid
It is significant that the costs allied to the project presented in a way visibly identify by the
All cost calculations are varied subject to the organisation for whom the cost calculations are
delivered (IEC 2015d). The battery replacement cost is not expected to recognize who is leasing
a particular system (IEC 2015d). Since, this is the concern of the lease issuer (IEC 2015d). Thus
the only object that delivering to the consumer is the monthly service fee (IEC 2015d).
25
The purchaser of a complete system is required to recognize all of the associated costs over the
All these cost are deliberated in calculating the actualized discounted cost (IEC 2015d). It is run
down not only the different costs mentioned above, but also the income from sale of energy
It is allowed the run down difference (income-cost) comparing for diverse technical solutions
It is the relationship of the different demands of info as presented above, table 1 is listed the
minimum data that is collected from the power system (IEC 2015d).
Data
Battery current ●
26
Data
the system
Protective devices are offered to break any over-current flowing in the cct conductors (IEC
2015e). It is prior such a current causing a danger due to thermal of mechanical effects or a
temperature increase and made harmful to insulation, joints, and termination (IEC 2015e).
𝐼𝐵 ≤ 𝐼𝑛 ≤ 𝐼𝑧
27
𝐼2 ≤ 1.45 ≤ 𝐼𝑧
where
𝐼2 is the current ensuring effective operation in the conventional time of the protective device
(IEC 2015e).
For cable and isolated conductors, each short-circuit protective device is seen both of the
following state:
The breaking capacity is not less than the potential short- circuit current at the place of
its installation, excluding where another protective device taking the necessary breaking
All current is produced by a short-circuit happening at any spot of the circuit should be
interrupted in a time not exceeding that which brings the conductors to the admissible
limit temperature (IEC 2015e). For short- circuit with interval up to 5 s, the time t, in
which a given short- circuit current is increased the conductors from the highest
𝑆
√𝑡 = 𝐾 × 𝐼 Eqn 1)
Where
𝑡 is the duration in s;
𝐾 is a factor raking account of the resistivity, temperature coefficient and heat capacity of the
conductor material, and the appropriate initial and final temperatures (IEC 2015e).
28
4.2.4 Protection against risk of fire
Where there is a risk of personal injury or property is harm due to fire causing by an earth fault
in the system, a residual current protective device is delivered at least at the origin of the user’s
installation (IEC 2015e). The rated operating residual current is less than or equal to 300 mA.
Choices for lightning protective provision (lightning rod, surge protective devices, etc.) is based
on risk assessment, taking reason of the lightning frequency statistics, the characteristics and
position of the structures, the length of the overhead lines, if any, the cost and the demanded
Where protection against overvoltage (for example due to indirect lightning) is demanded, an
SPD(s) is connected both at the distribution board of the micro-power plant, and at the origin of
Minimizing the voltage is induced by lightning, the zone of all wiring loops are as small as
Where protection against direct lightning is required. The following necessities are applied:
in case of wind powered generation, the lightning is connected at the summit of the
direct lightning is general achieved by placing the panels inside the pick-up zone of the
29
where PV generation is alone, the panels are protected by installing a protective wire
above the PV panel or lightning rod/s with an appropriate pick-up area (IEC 2015e).
Fuses (gPV types) or circuit -breakers with appropriate range of instantaneous tripping
are used (IEC 2015e). Protective devices are preferably of a type ensuring in protection
(IEC 2015e). The range of installation tripping for a circuit -breaker is selected referring
Overcurrent protective devices are preferably of a type ensuring protection against both
overload and short circuit current and capable of acting as isolating switch in the open
that a suitable coordination is attained (IEC 2015e). The selection between protective
shape and the dimensions of the earth termination system of an LPS are more significant
than the value of the resistance of the earth electrode (characteristic applicable for dc or low
1. either conductors of the same nature and same cross-section as the down-conductor
is laid out in the form of a large crow’s foot: 3 conductors 7m to 8 m long buried
2. or a set of 3 vertical rods 2 m in length is coupled together and set off at the tips of
30
The earth termination system of the LPS is joined to the earthing arrangement with short
A micro-power plant is included one or several generators, a storage devices (if needed) and
- energy converter;
- main board;
- interfaces (between generator, between the micro-power plant and the micro-grid or
- switches;
4.4.1Interconnection of generators
It is depended on the category of energy sources and the type suiting of equipment to deliver
(IEC 2008c) through more than one generator is used. And their outputs are connected in
Single-phase power system output is a single – phase feeder with multiple single phase
31
Figure 3 Micro-grid consisting of a single-phase feeder (IEC 2006a)
Connections between conductors and between the conductors and other equipment are ensured
2. The number and the shapes of the conductor cores (IEC 2006a).
It is included for the isolation of the micro-grid to allow servicing, checking, fault location and
Isolation is carried out by a device installed for other purposes (cct-breaker, etc.) (IEC 2006a).
Isolation devices are armed with a suitable locking device namely; earthing arrangement,
The PEN conductor is earthed at both ends of the network and repeatedly every 200 m as
32
Figure 4 Micro-grid earthing scheme (IEC 2006a)
33
Table 2 Functions ensured by various types of user interface (IEC 2006b)
Function Description
F Earthing terminal
G Distribution of ccts
Figure 5 and 6 are illustrations of setting up and functions ensuring by the user interface
Figure 5 interface for user installations was supplied from an ac or a dc source (IEC
2006b)
34
Figure 6 interface for user installations were supplied locally from ac or dc sources (not
from a micro-grid) (IEC 2006b)
4.5.3 Housing
All the equipment for the user’s interface whose functions are defined earlier in one container,
including the interfaces for the set of cables connecting the electrical power source and the
The housing is not be in contact with the active parts of the equipment which it was contained;
the housing is fulfilled the obligation of protection index IP54 and IK 4 for mechanic effect
(IEC 2006b).
The protection index of housing is not distressed by the mounting system or by penetration of
cables. The housings are armed with pre-shaped inputs equipped with accessories for path of the
35
4.5.5 Requirements for ac parts of installation
If the features of the protective devices are fault of negligible impedance occurring wherever in
the connection between a phase conductors and a protective conductor or exposed conductive
A residual current protective device, with a rated operating residual current not exceeding 30
mA is delivered as extra protection for each connection (IEC 2006c). It is positioned in the
The maximum voltage drop is not greater than those shown in table 3 (IEC 2006c).
the conduits is at least three times the diameter of the cables (IEC 2006c). After laying
the cable, the ends of the sleeve are secure to avoid jam (IEC 2006c).
The compensation for the effects of the settling of the soil, the cables are buried at a
in areas reachable to vehicles (IEC 2006c). A red plastic grid is placed 10 cm above the
36
These depths are less in rocky terrain or if sleeves are used designing to make sure that
the cables did not intend to endure the settling effect of the soil (IEC 2006c).
The PE protection conductor is linked to the PEN conductor or the micro-grid in the
user interface housing upstream of the RCD, on a terminal provided for this purpose
(IEC 2006c).
The project implementer is defined the operating conditions to which the PV-IES was
Celsius)
Humidity at 28 degree 5 to 95
Celsius (%)
(hPa)
4.9 Summary
The complete power systems are achieved through rural micro-grid (IEC 2015d). The terminal
application points generating from the rural micro-power plant energy supply point with
adjusting the energy requirements to the different forms of customer (IEC 2015d). It is also
All calculation are varied due to the organization whom delivered (IEC 2015d). The only
37
The protection against electrical hazards are prevented from overcurrent, short-cct, risk of fire,
Over-current protective devices are preferably of a type that making sure in protection from
potential short-cct current such as fuses or circuit –breakers with appropriate range of
Composition of a micro-grid is depended on the maximum active power value serving (IEC
2006a). The connection between the conductors to conductors and other equipment are for
electrical continuity and suggesting appropriate mechanical resistance (IEC 2006a). Isolating
All equipment for the user’s interface are in one container called housing (IEC 2006b). It is not
allow to be in contact with the active parts of the equipment which it is contained (IEC 2006b).
In the ac parts of installation, if protective devices are exposed conductive part then auto
disconnection will arise within 0.4 second (IEC 2006c). In the other hand of dc parts of
installation is a simple separation, at least is not provided the dc side and the ac side of a
The maximum voltage drop is less than 3 % installation from supplied from a 120 or 230 V
distribution micro-grid grid and 5 % of standalone installation with dc source (IEC 2006c).
The specific rules to wiring systems hidden in earth, the cable shall be buried at a depth of at
38
Chapter 5 The methodology to achieve
the best technical and
economic condition
Stand-alone power system is built to generate power to isolated communities or loads in the
3. collective electrification systems (CES) (multiple user load or application) (IEC 2015f).
In order to fulfil the various energy requirements both in terms of quality and quantity,
39
Table 5 AOMR actions (IEC 2015f)
40
5.1 Organizational issues
In this area, it is stated system limit description of the AOMR domain. An understandable
definition of the physical limits of the three parts of the system (production, distribution,
demand) related to operation, maintenance and replacement actions are made (IEC 2015f). The
identification of the appropriate personnel or companies accountable for the diverse subsystems
is necessary (IEC 2015f). This is required for both categorises and safety bases (IEC 2015f).
Within most micro-power systems maintenance is to complete on each component as well as the
guidelines for their specific component but no general maintenance guideline was provided for
In most circumstances, replacement actions are needed for distinct power plant sections as
linked to the whole network (IEC 2015f). An individual factor is replaced possibly with a
but the rest of system is leave out no charge (IEC 2015f). Irregularly the whole micro-power
follows:
more cost effective to replace the complete power system comparing to the
society are vital to a better quality of supply than is delivered through the
41
c) Load was increased: the community loads were increased to the level that
illustration is more cost effective to replace the whole power system. The
old power system is then moved to a new community with lower power
e) Change in plant site: if the plant site is altered for any intention (IEC
2015f).
a) Prior replacing a piece of apparatus, the first thing to do is disjointed it from all
sources of power. In case of small systems, lead to the turn-off of the entire
network and hence facility operators are required to be qualified in conduct all
parts of the system. In bigger network, service staff is able to isolate objects
from the rest of system without needing to shut down the entire network (IEC
2015f). The system documents are stated in IEC TS 62257-4 that needed to
b) Prior removing equipment, a copy of all logged data, parameter settings, status
etc.) are made (IEC 2015f). If this are not completed through an electrical
interface, but are made through noting all reachable data that found in display
menus and by checking internal switches, settable device, etc. (IEC 2015f). All
the latest settings is then known and noted (IEC 2015f). The recording of
configurable parts inside the device is only be completed after the device was
c) Brand, model, type and serial number data from the fundamental and
42
d) After any new device is connected, the hardware conformation is carried out
reference with the records as earlier made (IEC 2015f). For devices regulated
(IEC 2015f). It is regularly that devices are partially attached to the network for
this reason (IEC 2015f). The commands are given in the manufacturer’s
condition, it is then be the duty of the service technician designing the new
e) After appropriately arrange and connect into the network, as requested in the
class. Physical ingress protection is vital for user safety along with product functionality
(IEC 2015g).
The current total harmonic distortion is the calculated of harmonic content in device’s current
waveform (that was how much the current waveform was diverged from a real sine wave) (IEC
2015g). High levels of harmonic current is affected heating in power generation and distribution
apparatus waveform, negatively impacting the functioning of other equipment coupled to the
The colour features of light are involved the colour rendering index(CRI), a degree of how
accurately the light renders colours, and the correlated colour temperature (CCT), a degree of
5.7 Summary
Stand-alone power system is built to generate power to isolated communities (IEC 2015f). The
systems are divided down into three classes; process electrification system, individual
electrification system and collective electrification system (IEC 2015f). Six AOMR actions are
Organisation issue is accountable for the diverse subsystem safety (IEC 2015f). Maintenance
action, equipment manufacturers are provided maintenance guidelines for specific component
(IEC 2015f). Replacement is needed for distinct power plant sections as linked to the whole
network (IEC 2015f). Irregularly the whole micro-power network is necessity to experience
Physical ingress protection is an explanation of the protection from the disturbance of foreign
Current total harmonic distortion is indicated how much the current waveform is diverged from
Colour Characteristics are involved two types namely; CRI is a degree of how accurately the
light renders colours, and the correlated colour temperature CCT, a degree of the colour of the
44
Chapter 6 The combination of diesel
generator system and solar
energy
6.1 Generator boundaries
The generator is expressed entirety essential to make electric power consistent to the needed
features of voltage, frequency, harmonics, power and consumption of the clients, referring to the
When defining the generator characteristic the following “inputs” and “outputs” are taken into
45
Table 6 General inputs and outputs to be considered for generator specification
(IEC 2008a)
Regulations/ Standards
Assessment of energy
demand
Assessment of energy
quality requirement
46
Figure 8 General functional configuration of a PV system (IEC 2010)
Function Description
A Interface: connection between PV generator and technical room
B Interface: isolation of the technical room from the PV generator
C Other functions of the technical room + energy conversion, energy
management, storage, if any
D Interface: isolation of the application cct from the technical room
E Interface: connection between technical room and the application cct
F Earthing of exposed conductive part if required
irregular potentials as overvoltage across them (including lightning overvoltage) (IEC 2010).
The cable of the equipotential bonding between the generators and the technical room is linked
as physically close as possible to live conductor to keep away from any wiring loops that are
The connections to earth is made as close as possible to the equipment to earth (IEC 2010).
PV modules ratings are specified at standard temperature conditions (25 degree Celsius). Under
normal operating conditions, 25 degree Celsius is a usual steady state temperature increasing
47
with regard to the ambient temperature for crystalline silicon PV modules operating at the
maximum power point under 1000 W/m2 and when modules are operating on a very hot day
(IEC 2010).
The two main requests on the PV array strategy are developed from this operating feature of PV
modules.
rising.
(For crystalline silicon solar cells the maximum power is fallen between 0.4 and 0.5% per each
degree Celsius increase in operating temperature). Therefore satisfactory exposure to the sun of
the PV array is a strategy aim, certifying best performance for both modules and related
b) All the components and equipment that in direct contact or near the PV array
(conductors, inverters, connectors, etc.) are required to capable of resisting the expected
c) The voltage is increased in cold state, crystalline silicon technology based cells (IEC
2010).
6.4.1 Insulation
The insulation cables are used inside the PV array were intended to:
light through proper protection, or the cables are set up in UV-resistant conduit;
By-pass diodes are used to avoid PV modules from being reverse biased and consequent hot
spot heating. If by-pass diodes are used, and not fixed in the PV module encapsulation, they are
It is intended to use but they are not a standby for overcurrent protection (IEC 2010).
In network that is obtained battery. It is suggested that some components is built to get out of
reverse current leakage from the battery into the array during night time (IEC 2010). A number
of explanations are occurred to attain this as well as blocking diodes (IEC 2010).
If blocking diodes are used therefore needing to obey with following requested:
- A current rating is at least 1.45 times the short current at STC of the cct. It is intended to
protect;
diodes in PV strings of the PV array, these diodes are connected as displayed in figure 9 (IEC
2010).
Disconnecting means
It is delivered in PV arrays according to table 8 and table 9 to separate the PV array from the
power conditioner and vice versa and letting preservation and review jobs to perform safely
(IEC 2010).
Installation
The appropriate rated circuit-breakers are considered for overcurrent protection. It is supported
load breaking separating services (IEC 2010). Other disconnection and isolation devices are got
the features as stated prior could been used as disconnections means (IEC 2010).
50
Fuse network is taken for overcurrent protection. Those are acceptable non-load breaking
disconnecting means, in the case that they were changeable fusing element, rather using a
According to the location of disconnection devices in table 8, it is specified with detail of the
network formation where the disconnecting mean is intended to build and using this connecting
51
PV array Voltage Cct or sub-cct Type of Requirement
disconnection
device
a
‘Lockable’ disconnection device is a switch or cct breaker that has provision for
insertion of a mechanical device to prevent the switch being closed by an
unauthorised person. A Mechanical device in this context could constitute sealing
with plastic cord, a pin, a wire or other device that prevents operation of the switch.
b
A lockable disconnection device is not required if the whole cct is visible from the
location of the switch
Environmental
Shadowing of the PV array is lessened or rather removed over the whole day with reflection
52
A shadow blanking off a PV cell is made defeat of about the entire assembly of this module,
On flat roofs, PV modules are positioned in rows (IEC 2010). The first row fully is uncovered to
sunlight and therefore the shadow is created disturbing the next row and so on (IEC 2010).
As a rule of thumb, no shadow would be produced from one row to the next (IEC 2010).
Wiring loops
The reduction of the value of lightning-induced over-voltages, the PV array wiring is placed in a
term that the space of conductive loops is at least as possible, e.g. by laying cables in parallel as
String wiring
Among the modules, they are completed without laying lines in conduit, offering that the
53
- Insulated and enclosed lines are applied, and
- The line is secured to let go strain to avoid the conductor from pending free from the
The following necessities are related to the setting up of wiring network in junction boxes:
Wherever conductors are go into a junction box without conduit (IEC 2010). A tension relief
network is got to avoid cable disconnections inside the junction box (e.g. by using a gland
All cable entrances, when it is connected in tending to maintain the IP rating of the enclosure
(IEC 2010).
For LV PV arrays, where some return conductor is directed over module junction boxes (IEC
2010). Those return conductors are intended to be a single-core double-insulated cable, and the
cable and its insulation are mean to preserve double insulation status over its whole length,
mostly through junction boxes (i.e. these running was also related to any linkages) (IEC 2010).
Many of technologies are existed on the market of machines. From the modest to the most
For small size (below 5 kVA) the most frequently use technology is gasoline engines.
For greater size, the most frequently used technology is diesel engines (IEC 2008b).
The engine is made either for 3000 rpm (for small machine) or 1 500 rpm (for larger machine)
The other technologies such as small fuel turbines are intended to be in existing (IEC 2008b).
The project implementer is meant to choose the suitable technology consistent to the requested
level of quality of the service, the skill of the maintenance staff, the level of equipment available
at the maintenance centre, the spare parts that easily obtained, and all exact restrains of the
a) The alternator is skilled of delivering the nonstop and surge load apparent power (VA):
b) The engine is skilled of sending the power requested of the alternator and the
mechanical losses of the entire system (alternator + coupling system) (IEC 2008b).
It is for the project designer to exactly describe the generator set minimum operating
circumstances:
the maximum nominal productions, the matching interval and load issue;
the electrical load features (power factor, permitted voltage range, current harmonic
The collection and sizing of generator set are intended to the deliberation of the supplied
6.6.2Derating factors
The generator set is requested on to function, so forth be its manner of setting up. It is possibly
to disturb its certified characteristics (IEC 2008b). It is in the story through the project
If the location state are unidentified and vice versa specified, the subsequent nominal conditions
- temperature coolant for the boosting air 25 degree Celsius (IEC 2008b).
55
6.7 Design of the erection site
The generator set was connected to both in the open air or in a surrendered building (IEC
2008b).In case of the service was an individual electrification system. It was then fit outside the
house (IEC 2008b).In all situations, the flooring of the site was intended to let the generator sets
6.8 Ventilation
As far away as achievable from the engine gas exhaust, especially the fresh air entry (IEC
2008b). The withdrawal of hot air is built through the upper ventilation and the fresh air entry
For a generator set that is set up in an surrounded and soundproofed area, the room is then
allowed appropriate delivering to the combustion engine and cooling air (IEC 2008b). It is also
supported the generator set at the ambient temperature restraining to when it is stated.
The generator set air consumption is informed through the constructor (IEC 2008b). If it is not,
The air intake cross-section is intended to be the same as that of supply and define as follows:
The size of the minor fuel storage is used in the generator set room being sufficient for two or
three days of the independence generator set (IEC 2008b). The dominant fuel storage is
intended to build in alternative building or tank that is situated at three meters away from the
56
The capacity of the main tank is capable to support the essential independence reference of the
generator set size, the length of the service and the local potentials of refuelling (IEC 2008b).
For instance, in some locations it is likely to refuel throughout the rainy period. The volume of
The fuel storage is intended to fulfil with the local guidelines if there is any (IEC 2008b). If the
local guidelines are not appeared, the following requests were then observed:
The class of diesel fuel that stored in the generator set room, are not suggested from
IEC TS 62257 to go beyond 500 I, if the quantity stored is over 500 I, the storage are
The class of petrol that kept in the generator set room is not intended to above 25 I
The volume of C liters of the minor fuel storage, a drip tray with capacity of (c+20%) I
was intended to build in the generator set room meaningly a 600 I tray for a 500 I
The main fuel storage tank is obeying with the following keys:
- storage site ground is intended to hydrocarbon leak proofed (coating, sheet, etc.);
- tank earthed and equipotential bonded with the exposed-conductive parts of the
Both minor and main fuel storage tanks are intended to stay at least one meter away from any
heat supply or apparatus that producing arcs sparks or hot particles. The tanks location is
intended to get away from any dripping or leak fuel on hot sections (IEC 2008b).
57
6.10 Summary
The generator boundary is showed entirety essential to make electric power consistent to the
needed features of voltage, frequency, harmonics, power and consumption of the clients,
referring to the required value of facility (IEC 2008a). In table 6 is stated general inputs and
Equipotential bonding is used to avoid irregular potentials as overvoltage across them (IEC
2010). The earth is made as close as possible to the equipment to earth (IEC 2010).
condition (IEC 2010). The temperature will increase with regard to the maximum operating
point at 1000 W/m2 in a hot day (IEC 2010). All components are required resisting the expected
Insulation, fuse holders, by-pass diodes and blocking diodes are used to prevent PV module to
get any fault such as hot spot heating, burning and securing from degradation (IEC 2010).
Disconnection mean is referred to table 8 and 9. It is to separate PV array from the power
The considerations on accounting for shadow of the PV array are environmental, one line of PV
modules over the other, wiring loops, String wiring and wiring fitting in junction boxes (IEC
2010).
The generator below 5 kVA (small size) is usually used gasoline engine (IEC 2008b). The
Generator set sizing have had two primary requirement such as alternator and engine (IEC
2008b). The alternator is to deliver the nonstop and surge load apparent power (IEC 2008b).
The engine is to send the power requested of the alternator and the mechanical losses of the
58
Derating factors are possibly manner to disturb the generator characteristics. These are regarded
In order to produce good ventilation, the withdrawal of hot air is built through the upper
ventilation and the fresh air entry across the lower one (IEC 2008b).
The main fuel storage is intended to build in alternative building that is sit 3 meters away from
the generator set (IEC 2008b). The tank is supported to capable to handle the potentials of
refuelling (IEC 2008b). The tanks location is intended to be far away from any dripping or leak
59
Chapter 7 Rottnest Island case study
Chapter 7 is illustrated a case study of electrification in a remote area in Western
Hence it is a good opportunity to learn how power system is setting up on the island. In
this chapter is explained the power system details of the island that is matched to IEC
TS 62257.
The function of Island power distribution subsystem is included energy conversion from
primary energy, electric conversion from dc to ac, and energy measurement (IEC
2015d).
Presently, there is no energy storage in the system. A functional diagram for rural
micro-grid of Rottnest Island is gotten the same impression as figure 11 but more
complicated than as shown. Those diagrams that represented the Rottnest Island power
60
Figure 11 Functional diagram of a radial structure for rural micro-grid
In the case of recycle, they are normally organized for every 32 years period. It is
depended on RIA (Rottnest Island Authority) the owner of this power system.
For the operating temperature, normally the condition to operate generator set is about
In summer, both sides of the door must be opened to get natural air run the system at
normal state. In a hot day, a loss of voltage is about 1-2 V each time when there is a
61
7.2 Protection against electrical hazards
short circuit, the risk of fire, the effect of lightning, overvoltage and direct lightning
The electrical system at the terminals of any user’s electrical equipment at Rottnest
Island is AC voltage, 0.9 x 230 V < U (AC) < 1.10 x 230 V (IEC 2015e).
The island is consumed Renewable energy and hybrid type of generator (IEC 2015e).
Surge protection devices of the Island are relied on Australian standard ASN3000.
The earth termination system is constituted of either conductors of the same nature and
the same cross-section as the down-conductor is laid out in the form of a giant crow's
Protection against lightning overvoltage was at all times compulsory when the linear
distance between the PV array and the mechanical room is about 15 meters (IEC 2010).
The surge arrester is positioned as close to the PV array and the mechanical room (IEC
2010). In Rottnest case, everything is 11 kV earth to the ground. This was the ability
that the earthing would be handled any fault from the network.
from IEC standard. By an additional wind turbine and a generator connecting to this
Hybrid IES or CES – PV generator + inverter and another generator – d < 15.
62
Figure 12 Configuration C and E –PV alone IES or CES – P< 500W – with inverter
63
The Rottnest PV array diagram was a multi-string case as in figure 14 (See appendix A.2).
The island was using thin film Cadmium telluride (CdTe) as they are given from other
renewable energy site. Its photovoltaics at the maximum power point under 1000 W/m2 .Even
though IEC TS 62257 is recommended to use to use Crystalline Silicon (IEC 2010). These two
types of PV modules is gotten the same maximum power point hence it is acceptable to use thin
film Cadmium telluride (CdTe) photovoltaics. The specification of PV multi string module is
64
7.4 Selection of generator sets for rural
electrification system
Generators are run 1500 rpm with the set type of Coupled (two or more generator sets
Derating factors for generator sets refer to ISO 8528-1. The details are
On the island is used Detroit and Cummins generators see appendix A3. For set noise
levels, they are gotten less noise levels than both values on the table. As the Island is
102
P ≤ 2 kVA
100
2 kVA < P < 240 kVA
65
4 doors of opening exit from generator set area at the island is suited to IEC TS 62257
Adequate space provides near a generator set on all sides where people are to pass in
order to enable all equipment to safely and effectively operate and adjust” (IEC 2008b).
At Rottnest Island case is acceptable to “The size of doors and opening (height, width
(m)) for the generator set are from a generator set area with a height of not less than
1.98 m from the floor or walked-on surface and a width of not less than 0.75 m” (IEC
The air intake cross-section should be the same as that of delivery and determine as follows:
From generator to main switchboard the island is used the connecting cables for a three-phase
The island is used the same variable as table 12 from generator to main switch board.
20 and 30 6
40 16
66
Power kVA Cross-section/ phase mm2
50 16
60 25
80 35
100 35
There is residual current of protection devices allowed a use of 30 mA residual current device to
In Rottnest Island, it is checked the battery electrolyte by automatic colour code reading in
which it is linked to a generator. In this case, there is no needed water filling and last for a year.
Micro plant system limit (composition of micro plant) is gotten the same item as the
figure 15. The generator is generated power to micro-power system. Then the power is
run through micro-grid to the end of the line that is loaded. Generator is included such
as wind energy, solar energy or fuel. Wind energy and solar energy are operated
chopping off each other. Meaningly when the wind energy is in used, the solar is not.
67
Figure 15 Micro-power system limits (IEC 2008c)
In Rottnest Island Case, the application is different from the following that is illustrated
68
7.10 Interconnection of generators
Interconnection configuration with AC bus only in figure 17 is matched to the Rottnest Island
7.11 Micro-grids
Maximum value voltage drop in micro-grid is on individual service connection line (IEC
2006a). Rottnest Island configuration of micro-grid (diagram) and Micro-grid earthing scheme
is shown in Appendix A.1. Installation of poles (arrangement, setting up) with 11 kV with 3
phase horizontal and 11 kV cable. Overcurrent protection device of the island is used Spag
69
7.13 Integrated system – User installation
Protection of people in an installation supplied from a micro grid according to TN-C-S system
and user's electrical installation are built according to a TN –S system as figure 18 (IEC 2006c).
In Rottnest Island case MEN (multi earth neutral) is used. All MEN was set at 30 mA.
If there any fault is occurred in the system, it then will be just feel it and gone.
For the Rottnest Island case, it is all within the range of on table 13.
70
Table 13 Suggested minimum values for IP and IK (IEC 2008d)
Protection degree Minimum suggested value
34
IP
8
IK
Rottnest Island’s IP was at about 65, see appendix A.4. The IK was passed the
Australian standard when the authority people are at the island and conducted the
testing.
- outdoor-only systems design specifically for outdoor use, meaning they intend to mount
The third roll criteria on table 14 is matched to Rottnest Island case. Through the aspect
71
Table 14 The Principles of Lighting service performance assessment (IEC 2015g)
Light output criterion Aspects Requirement
Luminous flux ≥ 25 Im
General illumination
Luminous efficacy ≥ 40 Im/W
Luminous efficacy
Light distribution ≥ 0.1 m2 area of
Task lighting service
characteristics illumination
≥50 lux when the lamp of
lighting appliance is
self-supported on the
task surface or
suspended from a 0.75
m distance from the
surface.
7.17 Summary
Rottnest Island in Western Australia is chosen as a case study in the thesis. The electrification
on the island is based on ASN3000 standard. The comparison between Rottnest Island’s power
The functional diagram of a radial structure for rural micro-grid of the island has the same idea
In ASN3000 has the same electrical hazard protection systems to IEC TS 62257. In the Island
are used TN, TT, Double and Extra low voltage systems.
Earthing system arrangement of the island is matched to IEC TS 62257 configuration C and E –
PV alone IES or CES – P< 500W-with inverter- d< 15 m, and Configuration D and F-Hybrid
IEC or CES-PV generator + inverter and another generator-d<m. Also PV array diagram in the
In the Island set noise level is compiled to IEC TS 62257 generator set permitted noise levels in
table 11.
72
Micro-power system of the island is the same idea as figure 15 micro-power system limits of
IEC TS 62257.
Functional layout for a micro-power plant supplying ac energy of the Island is not the same as
The Island’s interconnection of generator is matched to configuration with AC bus only in IEC
TS 62257 standard.
The protection degree at minimum suggested value in term of Selection of PV-IES is matched
Categories that the island’s lamp and lighting appliances is indoor/outdoor products design and
At Rottnest Island lighting service targets, the aspect of light distribution characteristics is at
least 0.1 m2 of the area is illuminated. At least 50 lux when a light appliance is self-supported
73
Chapter 8 Conclusion
This thesis has investigated the recommendations from IEC TS 62257 in term of off-grid
electrification in the remote area. A case study of Rottnest Island has chosen to support the idea
this system’s type. The project has five aims. Each of the aims are explained in a separated
chapter namely;
Chapter 3 has reviewed ways to set up the renewable energy system to meet the customers’
requirements in rural area. In the chapter has presented a method called “master plan”. The
method is to collect important data for the upcoming remote electrical project to find cost-
effective solution.
In chapter 4, the electrical network in term of minimum sufficient requirements of high standard
safety to electrical power application has been review. Since No one would like to pay big
money for less sufficient electrical system. Hence the project presentation such as cost and data
to be collected from the power system has been specified in this section. The method to connect
and access at the lowest cost to make system well arrange for micro-power plant, micro-grid
and user interface is shown with requirements for dc and ac parts of installation. In order to
fulfil satisfactory to people in the renewable energy project’s area, the protection against
electrical hazard such as; preventing from overcurrent, short-cct, risk of fire, effect of lighting,
The technique to achieve the best technical and economic is shown in chapter 5. It is described a
processed called “AOMR actions” to meet both quality and quantity energy requirements. This
section has explained light’s colour characteristics in details which involved two types namely;
CRI is a degree of how accurately the light renders colours, and the correlated colour
temperature CCT, a degree of the colour of the light conveyed as a temperature in kelvin. In
addition, it has also stated the physical ingress protection in general to any enclosure involving
75
The combination of diesel generator system and solar energy is explained in Chapter 6. It is
shown generator boundary as well as things to consider due to operating temperature for these
type of system. Those are insulation, fuse holders, by-pass diodes, blocking diodes and location
and installation requirements. In order to reflect on the selection and election of a generator
needed to cover on generator set sizing and deration factors. For these two combination to last
long, a good ventilation and plenty of fuel storage is also a main point to study in this area.
In chapter 7 has illustrated Rottnest Island case study. It is explored most of IEC TS 62257
details to match the Rottnest power system. The recommendation of battery system in IEC TS
62257 is excluded herein since Rottnest Island battery network is not available. Mainly, the
IEC TS 62257 series are a worldwide accepted and adapted to an area undertaking rural
electrification project. In order to receive the most efficiency to the power project, the selection
76
Chapter 9 Future work
Even though the overview of IEC TS 62257 on Rottnest Island is completed, there might be
First and foremost, in order to gain a more understanding in rural electrification economic. We
needed to know “what are the best choices of power source to produce sufficient power as well
as cost friendly?”. In fact, the most suitable programme for renewable energy finding is
HOMER. It is famous for producing fuel curve, efficiency curve and excellence in data
manipulation. Throughout this programme, the search for the best combination of energy source
such as diesel generator only, solar energy only, wind energy only or a mix of both could be
Second, the future research of Rottnest Island would be on load profile and the limitation on the
Third, an expansion of this thesis would be on the other criteria to this such as “is there anything
that Rottnest Island power network does not meet the suggestion from IEC TS 62257?”
And last, it would be interesting in comparing between Australian standard ASN 3000 and IEC
TS 62257 to see the similarity and any different between these two principles.
77
References
Australia, The Government of Western. 2017. Rottnest Island Water Renewable Energy Nexus
Project. In The Government of Western Australia
Australia: The Government of Western Australia
78
Geneva Switzerland: IEC.
IEC. 2015d. IEC TS 62257-4. In Recommendations for renewable energy and hybrid systems
for rural electrification - Part 4: System selection and design. Geneva Switzerland:
IEC.
IEC. 2015e. IEC TS 62257-5. In Recommendations for renewable energy and hybrid systems
for rural electrification - Part 5: Protection against electrical hazards. Geneva
Switzerland: IEC.
IEC. 2015f. IEC TS 62257-6. In Recommendations for renewable energy and hybrid systems for
rural electrification - Part 6: Acceptance, operation, maintenance and replacement.
Geneva Switzerland: IEC.
IEC. 2015g. IEC TS 62257-12-1. In Recommendations for renewable energy and hybrid
systems for rural electrification -Part 12-1: Selection of lamps applications for off-grid
electricity systems. Geneva Switzerland: IEC.
S, Surbhi. 2015. "Difference Between Developed Countries and Developing Countries."
KeyDifferences, Last Modified 18/6/2017 Accessed 18/8/2017.
http://keydifferences.com/difference-between-developed-countries-and-developing-
countries.html#Conclusion.
Transenergy. "Decentralized Rural Electrification." Accessed 14 August.
http://www.transenergie.eu/uk/erd.php.
79
Appendix A
A.1 Rottnest Island power system diagrams
81
Figure 21 Rottnest Island Authority Cable Survey L.V. Reticulation Single Line Diagram 1
of 2
Figure 22 Rottnest Island Authority Cable Survey L.V. Reticulation Single Line Diagram 2
of 2
82
Figure 23 Rottnest Island power Station Metering and Protection
83
A.2 Rottnest Island PV modules
84
Figure 26 Rottnest Island Solar farm
85
A.3 Rottnest Island generator
86
Figure 30 Cummim Generator at Rottnest Island power station
A.4 IP ingress
87
The end
88