INDRAMAYU SPP PROJECT

SCP-JO DOC. No : P-T3109-EI-026


TEST PROCEDURE
GENERATOR LEAK TEST REV. No : 00

GENERATOR LEAK TEST PROCEDURE


3 X 330 MW POWER PLANT PROJECT
INDRAMAYU - WEST JAVA

DOCUMENT NO : P-T3109-EI-026

ORIGINATED BY REVIEW BY APPROVED BY DISTRIBUTION

- SDCC : Original
- All Div : Copy
- All Dept : Copy
- CNEEC : Copy
B. Winarko Iman. P Agus S - PLN : Copy

REV.
ISSUED DATE EFFECTIVE DATE BRIEF OF REVISION
NO
00 26 May 2009 26 May 2009
INDRAMAYU SPP PROJECT
SCP-JO DOC. No : P-T3109-EI-026
TEST PROCEDURE
GENERATOR LEAK TEST REV. No : 00

TABLE OF CONTENT

No. Descriptions Page

COVER 1

1 TABLE CONTENT 2

2 PREFACE 3

3 REFERENCE DOCUMENT 3

4 EQUIPMENT TO BE USED 3

5 PREPARATION WORKS 3

6 TEST 4

7 SINGLE LINE DIAGRAM GENERATOR LEAK TEST 5

8 SAFETY MEASURES 6

9 ATTACHMENT 6
INDRAMAYU SPP PROJECT
SCP-JO DOC. No : P-T3109-EI-026
TEST PROCEDURE
GENERATOR LEAK TEST REV. No : 00

1. PREFACE

This procedure is guidance for site test and commissioning of Generator and
to assure that the requirements of leak test are meets the codes
requirements and contract specifications

2. REFERENCE DOCUMENTS

2.1. T.J.E Quality Manual


2.2. Applicable Manufactures Manuals/Standards
2.3. Contract Specifications and Construction Drawing
2.4. Standard, Codes and Recommended Practices
2.5. GB – China Codes

3. EQUIPMENT TO BE USED

3.1 N2 Tank.
3.2 Pressure Gauge
3.3 Hand Tools
3.4 Detector
3.5 Radio Communicator (HT)

4. PREPARATION WORKS

4.1 All necessary precautions shall be taken before, during and after test.
4.2 Gas such as nitrogen or air shall be applied.
4.3 Check of pressure gauge indicator on generator showing 0 MPa
4.4 Checking all of tightness of generator like joints, seal, pipe connection
etc are operating correctly.
4.5 This test can be carried out simultaneously with test for corresponding
equipment.

5. TEST

5.1 Leak test are simultaneously carried out.


5.2 The Air tightness test pressure shall be kept for five minutes. Check
leakage on connecting sections with soap water.
5.3 In case gas is applied for test, care shall be taken not to give pressure
abruptly. Abrupt application of pressure produces danger.
5.4 Open and raise of valve of N2 tank with smoothly
5.5 Closed the valve if nitrogen pressure become up until 0.35 MPa
INDRAMAYU SPP PROJECT
SCP-JO DOC. No : P-T3109-EI-026
TEST PROCEDURE
GENERATOR LEAK TEST REV. No : 00

5.6 When the pressure exceeds the pressure allowed by the pressure
gauge, seat it as allowable by the measuring instrument
5.7 Keep the pressure until 24 hours
5.8 Check leakage on connected sections with soapy water with the
pressure as table below

Leakage Result Test


Hold Pressure
NO CHECKING No Status
(hours) Good
Good Repair
1 Joints 24
2 Hose 24
3 Flange 24
4 Welding 24
5 Seal 24

5.9 If the fall in pressure is more than 0.04 MPa in 24 hours, fill generator
with N2 and try and locate the leakage
5.10 As soon as the leak has been identified, ensure that’s its repairs
should be done and the leak test shall be started up again when the
nitrogen tightness is correct.
5.11 Recheck all connected, welding, hose, seal etc after 24 hours, if all
condition good that leak test meaning already done.
5.12 The single line diagram of generator leak test as per drawing
showing.
INDRAMAYU SPP PROJECT
SCP-JO DOC. No : P-T3109-EI-026
TEST PROCEDURE
GENERATOR LEAK TEST REV. No : 00

5. SAFETY MEASURES

6.1. Only persons qualified by training and familiar with Leak test involved
and lead by field engineer
6.2. Be sure that the safety equipment shall be used during test and use
safety barrier for personal isolation
6.3. The output of this N2 tank is high pressure, Ensure that tool and
equipment test are required
6.4. Worker should be used PPE (helm, safety belt etc)

6. ATTACHMENT

6.1. Job Safety Analysis (JSA)


6.2. Inspection Data Form
INDRAMAYU SPP PROJECT
SCP-JO DOC. No : P-T3109-EI-026
TEST PROCEDURE
GENERATOR LEAK TEST REV. No : 00