7a. Appendix I - Booster Compressor Requirements
7a. Appendix I - Booster Compressor Requirements
7a. Appendix I - Booster Compressor Requirements
CONTRACTOR shall include, but not limited to, the design requirement and expectation
below. Anyhow, requirement below shall not relieve CONTRACTOR’s responsibility and duty
to meet and comply industrial requirement e.g. API standard and PTS guideline as well as
specifications stipulated in other documents e.g. compressor specifications and datasheet etc.
CONTRACTOR to refer compressor spec and datasheet doc for more details in specification
and requirements.
Scope includes
i. Provision of Lease of One (1) Compressor Skid, which comprises
• Gas Engine Driver
• Reciprocal Compressor
• Suction and Discharge Scrubber
• Fuel Gas Conditioning System
• Air Coolers for Engine, compressor, gearbox and process gas coolers
whichever applicable (direct shaft is preferred over motor driven)
• Hydraulic System for Control
• Compressor Control Panel for Control and Safeguarding System
• In-skid piping and necessary instruments, fittings, and manual/actuated valves
for control and integrity safeguarding
• Exhaust system with silencer and spark arrester
ii. Lease duration One (1) year, with option(s)
• To extend up to one (1) year extension
i. Extension after 1 year shall be based on monthly basis up to 12 months
• Lease to purchase at end of contract
iii. Delivery of Compressor package to Labuan
iv. Offshore hook-up and commissioning
v. Offshore Operation and maintenance
vi. Onshore support
vii. Decommissioning of the booster compressor package at the end of lease
As part of the project design and execution assurance, CONTRACTOR is required to provide
design information below during bidding, including but not limited to, for COMPANY to check
and review
• Process and piping design and operation philosophies (including auxiliary system)
i. PFD, P&ID, C&E, Utility drawing e.g. fuel gas, hydraulic system, cooler etc.
ii. Compressor performance and operating envelope (head/capacity)
iii. Minimum turndown capacity via recycle valve or/and compressor speed control
(CONTRACTOR to confirm the compressor skid minimum turndown, if it can
operate at full recycle mode)
iv. Operation and control philosophy to maintain at desired injection rate e.g.
pressure control, flow control by suction/discharge FCV, recycle control or/and
compressor speed control etc.
v. Process safeguarding philosophy e.g. material design rating (#600/#900
rating), temperature trip, pressure trip, level trip, PSV, SDV, FGS etc. for
process and auxiliary system. CONTRACTOR to demonstrate that the system
is full rated to the system operating pressure.
vi. Fuel gas handling capacity
vii. Fuel gas conditioning system liquid/water capacity
viii. Compressor gas engine gas quality acceptance criteria
• Instrument
i. Instrument zone classification e.g. EX ‘eb’, Ex d, ExEx ‘de’ etc , IP55, IP66?
ii. Control system details (type/tech)
iii. Instrument SIL (SIL analysis will be carried out after PO award. However,
during Bidding process, CONTRACTOR need to mention SIL basis for
reference)
iv. Manual and remote monitoring, control and intervention capacity
v. Instrument interface summary
vi. Compressor gas engine gas quality acceptance criteria
• Mechanical/Structure
i. Space and weight breakdown (dry/wet) e.g. total weight, modular weight. Load
list.
ii. Lifting strategy and lifting plan and strategy e.g. dedicated lifting frame and
lifting lug design for each module, as well as sufficient crane clearance for lifting
iii. Actual footprint and clearance
iv. Exhaust insulation design
v. Noise and vibration data
a. Noise level as per AKTA KESELAMATAN DAN KESIHATAN
PERKERJA 1994 SEKSYEN 66 [AKTA 514]-PENDEDAHAN BISING
b. All vibration monitoring protection trip channels shall be operational at
the appropriate set points as specified by the manufacturer (OEM)
vi. Interface summary. Mechanical drawings and interface tie-in direction/location
(to ensure the tie-in point direction is not crashing with other equipment)
• Electrical
i. Load List and total power consumption
ii. Single Line Diagram for Local Control Panel power distribution
iii. Specification and data sheet for electrical equipment
• Execution plan
i. Organization chart for key person/role details for different project phases
a. Project execution and delivery
b. HUC and Commissioning (including personnels for rigging and
scaffolding during hook-up)
c. Operation phase (both on-shore support team and off-shore
personnels)
ii. Key personnel qualifications (refer to Appendix II for minimum requirement)
iii. Project schedule and delivery duration
iv. Project review, milestone (CONTRACTOR to propose the review session,
COMPANY may review and align)
a. Design drawing confirmation
b. Workshop e.g. design review, HAZOP, HAZID, SIL analysis, Tech
safety workshops, FAT, SAT
• CONTRACTOR to identify and advise on key deliverables (design and operation) e.g.
i. P&ID, Line list, C&E, Equipment Layout, HAZOP, Ops/Mtce Manual, Pre-comm
and Comm Procedure, Process Control, Blowdown calculation report, lifting
calculation and design report, SIL analysis report, HAZID report etc
ii. COMPANY shall perform the updating of safety drawings and facilitate safety
workshops (such as HAZID, HAZOP, SIL, HER, BT etc). CONTRACTOR shall
comply/incorporate the recommendations from the outcome of these
studies/workshops.
• Other information
i. Bedding requirement (normal operation and maintenance)
ii. Any requirement/request for tools or space e.g. Desktop, or space/cabin for
operation or for keeping spare item
iii. Fuel consumption estimate
iv. Maintenance and shutdown estimate (Planned and unplanned) e.g. frequency
and duration. CONTRACTOR to demonstrate that the design can meet 98%
uptime
v. CONTRACTOR experience
vi. Compressor history (if this compressor has been used in Malaysia or regional
water)
vii. Compliance to requirements stipulated in compressor datasheet, compressor
specification doc, and requirements in other Appendices and documents