DPRLashpath
DPRLashpath
) COMPANY
Nodal Agency
JAKEDA
Some of the important features included in the Project report are enumerated as under:-
All the minor issues relating to environment related with the project have been taken
into consideration while conceiving the scheme including necessary release of
sacrificial discharge for aquatic life/irrigation requirement beyond Diversion site.
There is no. Submergence of any land at u/s of Head works even during floods.
b. Monthly and annual and rain fall Not available for the catchment.
and temperature data for the
catchment.
d. Gauge and discharge data for Gauge and discharge data near
tributaries and the main river. diversion site collected for two lean
seasons with some additional years
available.
j. Silt discharge, showing maximum, Silt samples collected for one season
minimum and average silt and sediment grain size and chemical
intensities analysis given.
6. Has a detailed survey map of the dam site 2 metre contour interval map
been prepared (scale 1/5000 to 1/1000) attached at scale 1H:1V.
showing the following :
10. Have the main structures and appurtenant Yes, to the extent necessary in a DPR.
works e.g. dam, spillway, outlets, coffer
dam etc. been designed and the following
appended.
c. Load survey giving details of major Discussed in the report power shall
loads to be served, future peak and evacuated to Sate inter connection
energy demands, and anticipated point.
system load factor.
c. The current schedule of rates in the The prevailing rates for labour,
area and rates proposed, material and equipment have been
comparison with rates obtaining adopted.
on similar works.
I yearly 2 3 15 45
II yearly 2 3 15 45
(half)
10 Un-Skilled Persons.
ii District Ganderbal
Access Road
Jammu-Srinagar (NH-1A) Srinagar-
iv Sonamarg Road.
v Village Shitkari
2 Geographical Coordinates
Latitudes 34°19'57.73"N
ii Basin-Longitudes 75°13'57.09"E
Latitudes 34°19'56.93"N
Latitudes 34°19'56.93"N
iv Powerhouse-Longitudes 75°15'0.90"E
Latitudes 34°19'44.38"N
3 River Catchment
ii Nallah/Stream Lashpathri
4 Hydrology
ii Climate Data
a) Max. 320C
5.1.1 Weir
iii. Length 15 m
iv. Width 2 m
7 De-silting Tank
Type of Structure
i. RCC common structure with Forebay
iv. Width 9 m
Depth of water in main part of Tank
v. (FSD) 4.26 m
9 Forebay
iv. Size
a) Length 40 m
b) Width 9.6 m
10 Penstocks
i. Number 1 number
11 Power House
i. Type Surface- RCC framed structure
ii. Head
a) Gross 182.58 m
b) Net 174.45 m
b) Width 15 m
c) Height (m) 13 m
v. Turbines
b) Number 2 number
12 Tailrace
13 Power
14 Switchyard
i. Voltage level/basic undulation level 3.3/11/33KV
iii. Size :-
(a) Length 13 m
(b) Width 10 m
15 Transmission Line
ii. Length 9 km
1.0 Hydro power is a renewable, economic and non-polluting source of energy. Hydro power
stations have inherent ability of quick starting, stopping and load variations offering
operational flexibility and help in improving reliability of power system. Hydro stations are
the best choice for meeting the peak demand. The generation cost is not only inflation free
but reduces with time. Hydroelectric projects have long useful life extending over 50 years
and help in conserving scarce fossil fuels. They also help in opening of avenues for
development of remote and backward areas. Development of hydro power resources is
important for energy security of the country. It is therefore necessary to prepare a long
term plan of hydropower development.
Central Electricity Authority (CEA) has already covered planning of hydro power projects
during 11th & 12th Plan period. This is one of the major sources of energy throughout the
world and is considered to be a cheapest option. India is particularly interested in this
source of power.
The first systematic and comprehensive study to assess the hydro-electric resources in the
country was undertaken during the period 1953-1959 by the Power Wing of the erstwhile
Central Water and Power Commission. This study placed the economical utilizable hydro
power potential of the country at 42100 MW.The Reassessment study completed in 1987
revealed that the Hydro Electric Power Potential of the country was of the order of about
84,000 MW. In the 11th Plan of Hydro Development a capacity addition of 78,700 MW
comprising of 59,693 MW from thermal projects, 15,627 MW from hydro projects and 3380
MW from nuclear projects was approved during the 11th Plan period. Out of 15,627 MW
hydro projects, 8654 MW was proposed in Central Sector, 34810 MW in State Sector and
3491 MW in Private Sector.
Latest as per the studies carried out by CEA to assess the requirement of additional capacity
during the 12th Plan (2012-2017), the requirement of installed capacity to meetthe all India
peak demand and energy requirement at the end of 12th Plan would require a capacity
addition of over 90,000 MW in the 5 years period of 2012-17. In pursuing low carbon
growth strategy, it would be our endeavour to maximize exploitation of hydro power
potential. This is also necessary for energy security of the country. Availability of Hydro
Projects for benefits during 12th Plan
Nature has gifted our state of Jammu and Kashmir with vast Hydro Power Potential in the form of
snow fed rivers of Chenab, Chenab, Indus and other major tributaries thereof. Although, the
STATE SECTOR
Kishtawar 2x3+2x4.5 15
Karnah 2x1 2
Chenab Basin
Chennai-II 2x1 2
Bhaderwah 2 x 0.5 1
Ravi Basin
Sewa-III 3x3 9
Indus Basin
Igo-Mercellong 2x1.50 3
Haftal 2x0.50 1
Stakna 2x2 4
Total 759.2
CENTRAL SECTOR
Total 1560.0
Estimated Capacity
S.No. Name of the Project Name of the Basin
( MW)
Ujh
10. Multipurpose Ravi 280
Project
PakulDul 1000
11. Chenab
(Central Sector)
Bursar (Central 1020
12. Chenab
Sector)
Kishenganga 330
13. Chenab
(Central Sector)
10.00
2. Athwathoo Bandipora (commissioned)
10.00
3. Tangmarg Baramulla (Commissioned)
Ranjala 15.00
9. Doda (Commissioned)
Dunadi
Hanswar 6.00
11. Kishtwar
Paddar
Pomai 4.00
24. Kulgam
Aridajan
1.3 JAKEDA
Taking steps by J&K Government for Speedy Development of Small/Mini Hydro Electric
Power, Government has invited private entrepreneurs to undertake hydroelectric power
generation and has provided mandate to JAKEDA “Jammu and Kashmir Energy
Development Agency” as nodal agency under Department of Science and Technology for
co-ordinating and promoting development of mini hydro power schemes.
JAKEDA has invited various agencies to bid for identified projects for the development of
this sector. These will be termed as Independent Power Producers (IPP). These would
include any of the private sector entities, central power utilities, state governments or any
other government entities and their joint ventures. The Projects have been reserved for
execution by IPPs that are permanent residents of State of Jammu and Kashmir. This would
include such IPPs in which permanent residents of J&K hold majority stake. This condition
shall, however, be relaxed, in case the bidding process of the projects so reserved does not
result in adequate & competitive response. The eligibility of the interested parties is being
evaluated on the basis of pre-qualification criteria. Proposals of only those parties are being
considered for bidding who qualify the pre-qualification criteria.
1.3.2 The Project will be developed by Mass-N-Ergy Pvt. Ltd, The findings along with the
proposal for augmentation of the installed capacity was incorporated in form of a Project
report and is being submitted to JAKEDA for approval.
Lashpathri - IMHP scheme has been identified as a run of the river scheme onright side of the
Nallah. Power house site is located at a distance of about 44Km from Tehsil Kangan and62
km from District headquarter Ganderbal. Lashpathri - Imini hydropower project is one of
the mini hydro power sites identified for investigation by the Consultants for harnessing the
vast mini/micro and small hydro potential of the Kashmir region. The location of the
Lashpathri - IMHP and adjoining villages is shown in the site plan. The scheme proposes to
generate gross energy of 36million units of power in a 75% dependable year. The installed
capacity of the scheme is proposed to be 8500 KW from 6.38 Cumecs of discharge with
174.45m net head.
Lashpathriis primarily a snow melt based stream with some contribution from rain falls during
some months of the year which improves seasonal flows. The duration curve of the
assessed flows in a 75% dependability year is shown in figure 3.1.2 which gives the
characteristics of the flow. Very lean monsoon flow and substantial summer flow is
received over nearly 30% of the year followed by a 'knee zone' leading to much lower level
of dry season flow over nearly 45% of the year.
A comparative examination has been made of the energy generation possible with different
installed capacities and corresponding different values of installed capacities. Table 4.2 to
4.4 which give the details of energy generation possible in years of 50%, 75% and 90%
dependability for utilisation with some selected design discharges and corresponding
installed capacity.
The selection of the particular reach of the stream for hydro development has been made
on the basis of topographical and geological considerations. taking into account detailed
topographical surveys that were conducted, with updated recorded discharge series up to
Aug 2014, it was seen that optimum advantage is obtained by location of the reach with
diversion weir at El 3123.60m and power house at Ground Level El 2942m. chosen weir sites
and power house locations have been found minimal affected due to floods which have
occurred in Past one or two decades which is very important for such schemes.
Further as per the available topographical features it has been decided to provide Forebay and
De-silting Basin as a common structureat a safe place very near to the Diversion weir. The
scheme involves long Length of penstock with length/Head ratio more than 1/4,which isnot
in line with norms preferably adopted, however the matter stands discussed with the
Leading Turbine machine suppliers and it has already been confirmed that such technical
issues shall be handled in the design of equipmentto be provided by them.
Water conductor system shall have no power channel as the alignment which needed to be
adopted in such case would not have been safe due to rugged topography along the
alignment with apprehensions of snow slides in certain patches along with falling of
shooting stones in some of the reaches. Normal water conductor would involve bigger
sections as compared to Penstock diameter adopted thereby involving some deep cutting
into the hill making it more susceptible to landslides.
Therefore, the scheme proposal is preferred by making it a penstock scheme where in the
penstock has been aligned at lower levels than WCS normal alignment all along the Right
The severe floods have not washed away any nearby part of the alignment adopted.survey works
were undertaken and established that to make the project viable, alignment was shifted to
the right bank of Lashpathrias the Right Bankdoes not provide features suitable for Hydel
project development. After detailed studies of the topography and the available alternatives
the diversion structure comprising of a trench weir and an intake structure on the rightbank
has been ideally located. The location is comparatively in straight reach. The banks of the
stream provide suitable strata for proper anchorage of the weir. Comparatively a very flat
terrain along the alignment of the water conductor close to the intake has been chosen for
location of the Forebay cum de-silting tank. This location is 42.63 m away from intake. A
suitable terrace at the end of the Supply channel has been chosen for these structures. The
penstock has been aligned along a hill slope below the Forebay. The power house has been
located at a suitable location on a solid shingle boulder bench, which is above the
anticipated estimated flood level of the Nallah.The tailrace has been suitably aligned to
lead the discharges from power house to the source Nallah.
As such to overcome the above problems associated with raised-crest weir herein for this
scheme, the most common type of weir adopted in such boulder streams for MHP was
found trench weir. This is a weir by way of having a Reinforced Cement concrete Trench
almost throughout width of stream. The top of the weir is covered with bottom rack bars,
Water while flowing over it, passes through the bottom racks and enters into the trench
and collected in an intake well located at bank to end of the weir. The top edge of the
diversion weir has almost been flushed with the natural bed slope of the stream. The
bottom racks shall be consisting of heavy flat steel bars laid on edge over structural steel Z
piece members securely fixed in concrete side walls and placed parallel with the river flow
on the bed level. The bottom rack bars have been proportioned to carry the weight of the
heaviest boulders that are likely to flow down during the maximum probable flood.
This type of weir has the definite advantage as it does not affect the general bed level of the
stream. Post-Flood clearance of the boulders and debris collected in the trench of the weir
may be found obligatory. It needs to be mentioned here that in spite of the annual
maintenance requirement, this type of weir has been widely adopted in the SHP/MHP
schemes, built in Arunanchal Pradesh, Sikkim, Himachal Pradesh, and Uttaranchal and in
few projects of J & K.
The estimated peak discharge using various methods and take the most reasonable of them
as design discharge for trench weir for a conservative design. Flow in the stream at its
different stages is analysed using the manning’s equation with appropriate value of
rugosity coefficient along with Flows over broad crested weir. Water while passing over the
It has been assumed that the specific energy of flow shall be constant all over the
longitudinal bottom rack, and from the structural consideration, flat bars have preferred
over rounded bars as flat bars have more flexural rigidity. There is considerable effect of
ratio of thickness of bars t and their clear spacing, i.e. t/s and inclination of bars, the value
of Cd increases with increase of t/s ratio; however, it decreases with the increase of
inclination of bars (SL) for constant value of t/s ratio.
Intake structure herein called as Intake Well with vertical lift gates has been proposed on
the right bank to draw water from the pond created in the Trench weir. Intake structure will
have 2 no gates as Bulk head and Intake Service gate. The Gates shall be operated through
a lifting arrangement by Chain pulley mounted with Hoisting arrangement. During floods
Gate operation has to be properly ensured for its adjustment in height of opening to avoid
excess water entry to the water conductor system. The Intake well shall be made of RCC
rectangular chambers having provision for flow control to the supply channel and Shingle
flushing system. The height of the well has been fixed as per the worked out HFL at
Diversion site.
Practical and economic considerations dictate that the Lashpathri - Iwater conductor
system leading to powerhouse must be designed and constructed to accommodate
combined flows for Intake well which shall include silt and shingle flushing discharges
besides requirement of water for the overload generation requirements.The trash rack
provided at the crest of the weir has 30 mm nominal size openings. The diverted water may
therefore carry sediments up to 30 mm nominal size. It is advisable that majority of these
Lashpathri-I M.H. Project (2x4.25 MW) Part I Page 36
Consultant: EnCon Group
particles are eliminated before the water enters the inlet channel and further to the
sedimentation chambers. To this end, a shingle excluder has been provided at the end of
the trench weir in the Intake well on the right bank to arrest the entry of the shingles
moving along the bed of the trench weir into the inlet channel. Near this end, the trench
weir bed has been given a curved profile to facilitate rolling down of the bed load (shingles)
into a pit. A1000 mm wide lip may be provided to prevent shingles and other particles
collected in the pit to enter the Feeder Channel. From time to time, shingles accumulated in
the pit will be flushed back into the stream through a shingle flushing MS Pipe of 500 mm
diameter, provided at about right angle to the trench weir axis. The pit may be provided
with a slope of 1:11 towards the flushing pipe.
The flushing Pipe also has a slope of about 1 in 10 is considered to be adequate to generate
non-settling velocity for particles up to 30 mm size. The flushing channel runs along
therightbank of the Stream for a length of about 20m before it discharges back into the
source stream, at above HFL.
To facilitate intermittent flushing, a- 1 m x 1.0 m (H) gate is provided in the shingle flushing
channel. The gate will normally be kept closed and will be fully opened to flush the shingles.
Following the shingle excluder is the water intake, with a 2.0m wide and 2.0m high gate,
along with its control structure. The gate will be operated using a Chain pulley
arrangement. A 0.6 m x 1.4 m opening in the hoist floor slab provides access to the intake
bed. It may be noted that, the water conductor system is on surface; all the structures will
be of cut-and-cover type in adjacent to Intake structure. The maximum flow which shall
pass through the intake shall be 6.38Cumec.
The proposed RCC Box line shall be provided with Expansion joints (along with I number
Manhole at appropriate location)with de-silting tank and Intake well, as per requirement.
The RCC Box has been proposed to rest on solid foundation. The Supply channel shall have a
length of 100 m and in the design roughness coefficient for flow has been adopted as
0.018;this is in line as per the Guidelines for Hydro Electric Projects. It has been proposed
that there shall be no permanent road along this part of the water conductor, however a
berm and proper drain shall be provided towards hills side, and the berm may be used for
making any inspection during the plant operation. The hill slopes are stable as such 1:1
slope may be manageable with existing soil conditions. RCC Box construction for the reach
shall help in having support to the hill slope and with more improvement if covered with
earth fill ultimately.
• Hardness of particles
• Size of particles
• Shape of particles
• Turbine head
While the conventional settling basin has almost always been employed as preferred
desander in hydroelectric projects, use of vortices for removing sediment load from water
has largely been restricted to irrigation projects, with very limited application in
Between the two settling type basin arrangements, the DuFour type is not found suitable at
places like Shatkari. Design calculations show that the length of Dufour type desanding
basin is more than the single bay hopper type arrangement and does not suit the
topography of head works area. The structure will extend into higher natural ground and
would entail significantly higher quantity of excavation.
Design calculations for the conventional hopper type basin arrangement are presented hereafter.
The system would have the following characteristics.
One settling basins is provided to improve reliability and enhance operating flexibility, basin
in form of rectangular tank and provided with sectional area to reduce the velocity of flow
comprising of bed raft laid at 45 degrees each , with a total length of 18 m on either side of
the Tank inclined towards gutter at the centre of De-silting Basin , this bed raft has been
considered below the water level of full supply depth adopted in tank design shall slip all silt
contents into the gutter. The Gutter shall be provided with 2% bed slope which is found
sufficient to carry the silt particles along with flushing discharge. Since the structure shall be
constructed in combination to the Forebay as such a partition wall has been created at the
end of De-silting Tank part with silt settlement assumed to be well before it and clean water
to pass over the crest of this partition wall. The depth of flow as FSD in De-silting Tank has
been adjusted to be the same as operating depth required in Forebay tank.
• The flow through velocity in the tank has been taken as1.87m/sec.
• The settling velocity for 0.2mm size particle is taken as 2.5 cm/sec at 0º C (the water in the
stream is mostly from snowmelt.)
• The flushing discharge is taken as 20% of the plant discharge. And mostly the operation shall be
required during period when discharges are high in the stream as otherwise silt content in
the stream is found to be in significant.
Lashpathri-I M.H. Project (2x4.25 MW) Part I Page 40
Consultant: EnCon Group
• In order to dispense with the conventional 90º bend in flushing pipes (which makes it
difficult to clean in case of choking of the pipes), a 0.8m wide and 1.0m high flushing gallery
with a silt flushing channel (cunette) is proposed at the end of Gutter which will be laid
underneath Forebay raft. The flushing flow will remain concentrated in the silt flushing
channel.
As such the de-silting tank is single bay rectangular tank with flushing gutter type of RCC
construction having 39.0m (length) x 9.00m (breadth) x 4.26m (water depth in main Tank)
has been proposed at RD42.63m. It has been designed to remove 0.20mm and abovesize
silt particles. MS Pipe 600mm diameter with min. slope 2% is proposed to be provided for
flushing the silt and the flushing is controlled by 600 mm diameter sluice valve. The De-
silting Basin has been provided with a free board of 600 mm. The Tank shall have upstream
transition only as other end is directly merged with same width Forebay tank.
1.4.4 Forebay
TheForebay tank has been adopted as simple RCC Rectangular section having a common partition
with de-silting tank. The tank will have an overall depth covering minimum water seal
required to avoid any vortex formation in the Tank, this shall be located at the end of the
de-silting tank part as discussed earlierbut the design discharge in case of Forebay has been
taken to be 6.38Cumecs only. Further Tank is provided with sufficient bottom seal under the
bell mouth in Forebay pool to take care any undue material that may go into Forebay
including provisions for silt depositions. The tank has the basic purpose of absorbing the
fluctuations in the water supplies providing cushion for sudden tripping of the machines.
The Forebay is designed for a storage capacity time of 2 minutes with live storage full
supply water level and minimum draw down water level. The design discharge for Forebay
shall be 6.38 Cumecs which includes 20% additional discharge for overload power
Generation, The Forebay is provided with an Intake gate arrangement to control flow into
Penstock as per the size of Bell mouth, the hoisting arrangement will be of Double Rope
drum electrically as well as manually operated, further provisions for removal of any silt
accumulated have been kept by way of providing 300mm diameter MS pipe with control
. The average width available for the Forebay from the toe of the excavated slope on the
hill side is limited to an excavated depth of 4 m to 8 m at an appropriate location on the
valley side where ground level is not lower than the floor level of the Forebay. The sill level
of the intake has been fixed on the basis of requirement of water cushion above the intake
opening. Retaining walls forming the intake structure connect to the excavated slopes to
form the Forebay. The retaining wall has a maximum height of 6.76 m. The Forebay is lined
with Reinforced cement concrete. The Forebay intake is provided with a bell mouth opening
for the penstock and would be of RCC construction. An earth fill cover has also been
provided on the downstream of the retaining walls of the Forebay. LDPE film sheets may be
used for the walls and sides of the Forebay structure to serve as a water proofing
membrane. The excavated hill slope behind the Forebay is also proposed to be stabilized
without causing any damages to an existing road passing nearby to Forebay site on hill
side. Further these safeguards are done as an abundant measure of caution to minimize
distress due to seepage and provide additional stability for the critical Forebay structure.
The FSL of the Forebay is EL3122.58 m and the surplus escape located near the Forebay
comes into operation to release the discharges during the sudden rejection of the load by
the turbines.
A sharp crested Escape Bowl stands provided in Forebay for collection of any over flows
during emergency shutdown or for other reasons. The collected water shall be taken to
source Nallah nearby through proposed MS Pipe arrangement.Individual part of Forebay in
combined structure with de-silting tank is proposed to be of size 40m x 9.6m, having an
overall depth of 8.27 m.The Tank is provided with live storage for 2 minutes. And it has been
assumed under draw down conditions there shall be no silt content flow from De-silting
basin as both the structures have been designed independently for dimensioning of both
structures.
1.4.6 Penstock
As discusses in above Para’s the scheme has been developed as a “so called” penstock scheme
wherein penstock length is found long for its “length verses head ratio”. All care shall be
taken in pressure rise due to such issue, proper care for pressure relive arrangement is
recommended to be adopted at detailed design stage with due consultation with the
Turbine manufactures/suppliers. However the penstock has been designed against the
Lashpathri-I M.H. Project (2x4.25 MW) Part I Page 42
Consultant: EnCon Group
actual pressure rise due long penstock which shall be provided even if PRV is kept in place.
MainPenstock with 1600mm diameter and thickness varying from 28mm to 8 mm thick MS
Plates with symmetrical bifurcation at the lower end of 1132 mm diameter with 28 mm
thickness MS plates for each pipe for feeding two machines in the powerhouse has been
adopted.
The penstock has been aligned as per the topography available along the Nallah
bank with sufficient safety margins from HFL in the Nallah point of view. Almost the entire
length of penstock has been kept buried for its safety however suitable number of manholes
at appropriate intervals for any inspection has been recommended through RCC well to be
provided through back fill part. The penstock shall be having bituminous wrapping around it
from outside to safeguard it from anycorrosion.For every change of alignment Anchor
blocks of RCC shall be provided. The Penstock Liner shall be rested on saddle blocks.
1.4.7 Powerhouse
The proposed power house has been placed at relatively flat and stable terrace with turbine floor
level --- m. The Power house shall be of RCC framed structure with brick work in form of
panels in walls. The power house is surface type with Bed Raft/Floor of Reinforced cement
concrete M20 grade. Walls of power shall be of RCC 0.6m above maximum tailrace water
or backfill level. A single leaf gate shall be provided for 2 number draft tubes Gate openings
with chain pulley arrangement for lifting. The power house shall have to be safe guarded by
providing flood protection Bund. The power house building has been dimensioned in such a
way so that full space is utilised for accommodating two number units of 4.25Mw each
along with connected arrangements of Hydro mechanical and Electro mechanical
equipment’s and the structure has been divided into three parts i.e. service bay , Machine
hall and Control room with HT/LT room. The battery bank has also been provided adjacent
to Control room and further more office and on one number wash room has also been
adjusted in the power house building.
The centre of turbine is fixed taking into consideration of the hydraulic parameters of the
horizontal Francis type turbine and the minimum/Maximum tailrace water level has been
provided accordingly with respect to the bottom level of Turbine. The floor layout is so
designed to accommodate the trenches to run the power cables from the generators to
the control panels in the control bay. One number E.O.T. crane 30T capacity is provided in
the power house with facility to operate in longitudinal and transverse directions, to
handle the E and M equipment during construction as well as operation stages.
This structure is used for sending the tailrace waters from power house to Source
Nallah / stream. The tail race channel has been designed as RCC structure with discharge
capacity of 40% of one unit discharge under minimum tail water condition and 120% of
full design discharge of both the turbines under normal and maximum tail water level
condition with free board of 0.6 m. The discharging capacity in each case is determined by
Manning’s formula. The channel has been designed as a rectangular RCC structure up to
the bank of the stream and thereafter on crate construction in the stream bed making it
flexible and repairable after flood seasons. The Tail pool shall as per the power house
layout arrangement wherein the two individual draft tube exits shall deliver discharge into
the pool, initial 4m in bed raft has been kept plain after which reverse grade in the bed
raft has been provided to meet the bed level of Tailrace channel so as to maintain the
minimum tailrace water level from Cavitations’ stand point. The section of tailrace pool
shall converge in accordance with Channel size. The tailrace channel shall be rectangular
in shape.
1.7.1 Location
The Proposed Project site can be approached through Srinagar-Ganderbal-
SonamargRoad.The road lengthto becovered involves 21 Kmfrom Srinagarupto district HQ
Ganderbal. Thereafter, the Project site is located at village Shatkari on Kangan-Sonamarg road,
44 km from Tehsil Kangan &62 km from District HeadquarterGanderbal.
The project site is connected through all-weather Road from National Highway NH-1A via
Srinagar-Sonamarg.During the construction of the project existing kacha access road shall
be upgradedand shall need to be taken right up to the Powerhouse site. Existing bridle path
from Powerhouse to Forebay and to Headworks shall be strengthened for uninterrupted
access to all components. The proposed headwork’s is presently approachable from the
main roadthrough a bridle path only. However an option shall be explored to have rope way
arrangement for shifting materials to the location were road may not be made as the
project in small. However option shall be taken up and decided upon as per space made
available during the execution of Penstock and construction materials can be shifted along
the plat form created after taking up excavation of penstock alignment as such the trench
work and erection of penstock shall be managed in conjunction to the requirements of
dumping materials for construction of Diversion weir, Common De-silting basin and Forebay
to the nearby locations.
The project area is sparsely populated with the people mainly involved in small
agriculture activities. The population of nearby villages including Shatkari is around 7000.
The resources of the area are mainly green virgin forests clustered with Deodar, Kail and
Fur trees in upper catchment area. Except for water resources, no other natural resources
of any commercial significance are available in or near the project area. The forest
resources are also very limited in project area.
The forest comprises mixed jungles, mainly of pine Trees. The economy of the hill areas of
J&K is agriculture (Paddy) based. Some of the people from this area serve in bigger towns
where infrastructure for industries and commerce exists. The remaining people work on
small terraced fields. In general, the socio-economic condition of the people is poor.
Development of tourist activities can be explored as the area has got tremendous Scenic
beauties, the state tourist department is involved in various development activities of the
area which can enable locals to get involved in some works.
1.8 Climate
The climate of Jammu and Kashmir varies greatly owing to its rugged topography. In the south in
the Jammu region the climate is typically monsoon very hot and can reach up to 45°C.
Towards north in the Kashmir Valley across from the Pir Panjal range, South Asian
monsoon is no longer a factor and most precipitation falls in the spring from southwest
cloud bands. Because of its closeness to the Arabian Sea, Srinagar receives as much as
average 1200 millimetres of rain from this source with March to May being the wettest
months with around 100 millimetres per month. Winter precipitation falls in the form of
snow depending upon altitude and other meteorological conditions. As the catchment is
located in high altitudes the maximum temperature does not go beyond 320C, the winters
being severe with minimum temperature of -50C.
1.8 Hydrology
For correct estimation of hydrology and selection of proper site for the power plant,
especially in case of a hill schemes, about 18 months’ time are required for recording the
discharge of two seasons. For the purpose of preparation of the Project Report and with a
view to reduce the duration of project development, lean discharge is calculated by
correlation of the discharge data having similar geographical and geological features based
on the catchment area.
Lashpathriis a perennial Nallah starting from an altitude of 4550m of Glacier peaksabove
MSL (Glacier) and is joined by a number of small tributaries. The precipitation in the area
is seasonal/flashy rainfall during summer and spring: The run-off contributed by melting
of snow starts increasing from March-April and gradually reaches its peak in the month of
July and August. This gradual increase in the runoff from March to August coincides with
the increasing trend of air temperature. In October the discharge starts diminishing and
by the remaining months of the winter, the discharge fluctuates and shows a minimum
discharge sometime in the month of Nov, Dec and Jan.
Due to low winter temperatures, the glacial sources of the Nallah freezes. However, the
water continues to flow underneath. Total catchment area of the Nallah up to the
proposed diversion site has already and previously has been established to be 35 Sq Km.
This has been confirmed by satellite imagery and internet maps. An Ordinary Gauge and
discharge station has been installed in 2012to measure the discharge in Lashpathritill
August2014.
Nearly two and a half years discharge data has been used to formulate the project
report. Firm discharge series from 2012 to 2014 has been used for dependability and
optimization calculations. During the stage of execution, the hydro- logical data series will
be updated further for computing the dependability of the discharge, the ten daily mean
discharges have been tabulated and unrestricted energy has been calculated.
The 10 – daily discharges of the 75% dependable year have been used to arrive at the
optimum and the best beneficial installed capacity of 8.5MW.
1.12.1 Needs
Inadequate power infrastructure has been the major factor for the underdevelopment of
the State. The local area of Lashpathri is economically backward with no industrial
development. Lashpathri - IMini-hydropower project if followed by appropriate policy of
economic development will act as trigger for the economic development of the villages
providing avenues for the villages.
6.1.1 All components of the project including the diversion weir, intake and approach
channel, de-silting tank, forebay, penstock, switchyard, powerhouse and tail race
have been located on the right bank of LashpathriNallah on the basis of
topographical, geological, soil, ecological and environmental study. The layout
has been fixed to maximize the exploitation of available discharge and head.
6.1.2 Diversion weir site has been proposed at appropriate location on the topographic
survey sheet on a stable and relatively flat bed slope of the Nallah.
6.1.3 The location of Intake, Forebay and the alignment of , de-silting tank, and
penstock are primarily based on the basis that power channel has been avoided
due to reasons discussed in preceding Para’s and topography of the area using
the optimum hydraulic computation in adopting it as a penstock scheme.
6.1.4 Although many possibilities of the water conductor system alignment exist but the
final alignment has been based on the most efficient and cost effective system
after studying the geology, topography and hydraulic features in case of present
proposal. RCC Box Contraction has been recommended for water conductor up to
De-silting Tank. The Forebay and De-silting Tank shall be one Structure with
design features for its purpose have been taken care independently as per the
requirement as per general norms. The proposed alignment is based on the
techno-economic comparisons of all the possibilities available at the site and to
avoid certain UN avoidable encumbrances.
The width of the stream at this location at pond level elevation of 3122.8 m is 25.0 m. The
abutments are of hard shingle boulder strata still necessary support at the ends has
been provide. The intake structure is at the end of the trench weir adjacent to the right
bank. The trench is below the bed level El 3120 with a top width of 2.0 m and bottom
width 2.0 m as well and a depth uniformly varying from 1.0 m at the right abutment to
3.0 m at the right abutment where the intake structure is located. A trash rack grill has
been provided on top of the trench opening sloped in the flow direction so that stones
and pebbles do not settle but would roll away with the stream flow. The trench itself is
provided with a bed slope of 1 in 12.5 in the flow direction of the diverted water so that
sufficient velocity is generated to carry away heavy silt that may find entry into the
trench through the trash opening. The intake structure is located on the right bank
sufficiently away from the midstream so that the regime of the river is not affected
during normal high flood level conditions. Two openings are provided in the intake
structures, one of 2.0m x 1.80m for carrying the design discharge through to the de-
silting tank and the other of size 1x1 m with shingle flushing pipe 500mm diameter
The protection works in the river bed both upstream and downstream of the weir
consist of wire boulder crates 1500 mm x 1500 mm x 1500 mm in size and PCC concrete
M15 Blocks of size 1500mmx1500mmx900mm size. These are extended on the
upstream and on the downstream. Concrete toe walls, one on the upstream and two on
the downstream of the trench of different heights as per requirement serve as a
safeguard against dislodging of the blocks and consequent erosion.
Lashpathri - Ialternatives of gated weir, trench type weir, boulder weir and RCC weir
were considered. For steep rivers a feature of the Himalayan Rivers fully gated weirs
are not suitable, as they are prone to damages due to rolling bed load and the flashy
floods. Trench weirs herein has been adopted and it is envisaged that it should be able
to perform optimally though may get filled-up with debris during storm flows, But will
not be a matter of concern in the long run as may be simultaneously cleaned very easily.
Further the abutment work has been adopted to be in crate work with concrete grouting
on front face, the concrete as such will protect the wire mesh from tearing.
6.2.1Design
The height of Trench type weir is governed by the full supply depth of water in approach
channel and elevation of bed at the start of this channel. The entry of rolling stones and
boulders into approach channel is proposed to be restricted as it shall have tendency to
roll over the Trench covered with reasonably strong Trash rack on it. Thus,
Invert level of intake at end of weir = Bed Level at start of Feeder channel +0.2m.
On the upstream side of the Nallah at right bank and just adjacent to the Trench weir a
stone Masonry wall has been proposed which guide the flow and will safeguard the Intake
well including the initial part of Feeder channel.
E= (Q/CL)2/3 Ii
Where,
L is Width of Stream
E1 = ratio of opening/Total area of trash rack
surface over trench = 0.5
E2 is area of opening in the trash rack likely to be
clogged = 0.5
Area =Txd = 2 xd
Velocity head at the end of Trench hσ is given as,
hσ = n/(n+1) xA/2T
where A = 2 xd
g = 9.81
h = 0.167 xd
which is = 1 8.9
Mannings Formula is
Q =A* R2/3S1/2/n
Q = 76.434 Cumecs
Safe
Area = 2.55 sq m
OK
Width = 2.3 m
Design Calculations
6.3.1 General
Since the de-silting basin has been proposed very near to The Diversion weir as such
supply channel/approach shall found to be very short length. The total length involved is
42.6 m, this has been ended at allocation to suit the location of de-silting basin at RD
42.63m. The supply channel has been provided with Rectangular section of RCC Box
with internal dimensions ofBox as 1.8x1.8 m.The Concrete section shall produce velocity
of flow as 1.52 m/sec producing a full supply depth of 1.4m in the RCC Box. The bed
grade of the channel is 1 in 550 m/m and the roughness coefficient of 0.018 has been
adopted for Concrete section. Since the de-silting basin has been provided near Intake
structure and due tosteep bed gradient in main stream, as such only a length of
42.6metres has got involved in supply channel. This has even facilitated the flushing of
About 20% of the water shall be used for flushing the silt back to the source Nallah through
the silt- flushing duct at De-silting Basin; thereby the supply channel shall a design
discharge of 7.54Cumecs which also includes 10% over load requirement wherein it has
already been adopted that 10% discharge shall also be absorbed in the free board of the
channel which has been put at 0.4 metres.
The RCC Box shall be placed on firm ground over lean concrete 75 mm thick which will
provide base for the placement of Reinforcement steel.
The alignment has been adopted as per contour alignment of channel reach to involve
minimum cutting but at the same time stability of plat form by providing cushion to the
RCC Box on hill downside has duly been taken care.
6.4.1 Generals
Formost part of the year silt content in LashpathriNallah water is almost insignificant with the
silt factor of 6-6.5. Monsoons have very marginal effect on the flow in Nallah but in
storms it carries boulders, small stones / pebbles and silt particles. . Since it is
proposed to keep bed level of shingle flushing duct below the invert of water
conductor system by 0.6m, boulders /pebbles and debris shall not enter the Supply
channel and only the silt particles suspended in water shall enter the approach
channel. These silt particles need to be removed from water before its entry into
Forebay For this purpose considering project capacity a simple single bay de-silting tank
has been proposed. Flushing of silt shall be done through 400 mm Diameter MS pipe
and shall discharge back into main stream above HFL.
The location of de-silting basin has been adopted in a location wherein comparatively
plain terrain is available and is placed very near tointake structure, the deepest level in
de-silting ductas shown in drawing, wherefrom silt flushing pipe has been proposed to
It is recommended as per the guide lines to remove silt particles of size 0.2mm and
above through the process in which flow through velocity and moderate settling
velocities have been adopted as 0.197m/sec and 0.025m/sec respectively. The length of
the main tank is worked out to be 25.0 m with de-silting basin width of 6.0 m, the depth
of flow called as Full Supply depth of water is 4.26m.All these dimensions have been
adopted in such a way so as to suit the site conditions besides requirements from
Forebay stand point.
Where,
= 0.0253 m/sec
Therefore, Settling length of Tank
shall be = 33.1 M
6.4.2.1 The de-silting basin for this scheme is proposed at RD 100 with 12.6m upstream
Transition..
6.4.2.2 No transition (contraction) has been provided as the flow is proposed to flow
with same width of Forebay structure over a sharp crested weir which is of width
found sufficient to carry maximum discharge...
6.4.2.3 Along the centreline of de-silting tank, a trench 0.60 m wide with its depth increasing
from the beginning to the end has been provided for passing the silt which shall be
flushed through MS pipe 500 mm diameter back to LashpathriNallah by opening the
sluice Valve. Most likely regular operation of De-silting basin shall be in some of the
summer months only.
6.5 Forebay
Forebay has the basic purpose of providing water regulation in case of load rejection
fulfilling the immediate water demand at the start of generating units. For Lashpathri
- Imini-hydropower project it is proposed to provide a minimum storage volume above
The Forebay Tank shall be of RCC grade M20 and shall have an Escape Bowl as
well which could have been avoided in this case but has been included from
environmental point of view along with laying of Escape arrangement kept in form of
a short length of Escape Pipe and is constructed in monolithic to the structure with
height equal to the Forebay pool height. In Forebay depressed part called as Forebay
pool has been provided to accommodate height of bell mouth which in this case is1.36
m fixed in proportion to the penstock diameter of 0.85 m, further bottom sill of 0.44m
and Water seal measuring from FSL to MDDL which will avoid any vortex formation in
pool along with creation of live storage. The Forebay pool is also equipped with Trash
rack arrangement for full height of Intake to avoid and Trash entry into penstock. An
air vent pipe of 300 mm diameter will be fixed downstream of Intake service gate in
the Intake wall. Design of Forebay has purely been made of section to suite site
conditions and also to suit the De-silting Basin requirements as per the requirements
of the scheme, which shall involve a overall cutting depth of 4 to 8 metres and with
available soil condition should not of any major concern.
Free Board = 1 m
Allow Storage =
Discharge Q = 6.38
We know Q = 1.7*L*H1.5 =
Where L is length of Crest in
m. =
Applying above equation
Length of Crest L = 10.6 m
Therefore Provide Sharp
Crested spill over of Length = 10.6 m
Keeping in view the above parameters an Escape bowl of internal size 5.2x2.5
metre is proposed with height as per actual depending up built up section at
its location adjacent to Forebay, however the overall height shall not be less
than 4.0 metres. The above provided section is found to be safe for delivering
the free-fall flow over crest into MS Escape pipe.
Since the pipe alignment has been chosen along near Forebay to direct flow into Nallah as
such the grade of pipe has been taken into account to work out the diameter of this free flow
pipe. The gradient is found to be varying along the length of pipe line as such at this stage the
mildest grade has been considered in determining the pipe diameter. The pipe line shall be
rested on saddle blocks and shall be kept buried.
With circular section properties from Manning’s formula velocity V will be 13. m/Sec at peak
load rejection. Depth of flow has been fixed at 80% full criteria having most efficient flow.
Depth of water in free flow pipe shall be around 500 mm.
6.7 Tailrace
A very short Tailrace channel has been adopted in this project. This shall be in form of
rectangular RCC channel beyond Common RCC Pool. The Bed width of channel adopted is
5.5m with a freeboard of 0.6m as per requirement, the channel shall meet to source Nallah
above the HFL at its end. The design discharge for Tailrace has adopted as 6.38 Cumec which
includes 20% additional overload discharge as well. The Full supply depth in channel will be
0.7 metres which shall produce a maximum tailrace water level of EL 3126m. The bed grade in
= 0.002000
Area = =BD+0.5d2
Area = 3.85 sm
= 1.68 m/sec
Where,
R2/3 = =0.678m
S1/2= =0.045
=6.48cumec
Which is ok
6.8 Penstock
6.8.1 General
Penstock — a pipe used for the conveyance of water under pressure from forebay tank
to the turbine – is proposed to be of MS Grade B. IS 2062, is proposed to be adopted
for Lashpathri - Imini hydropower project. The penstock installation proposed is
embedded with backfill of suitable earth got from excavation with well-
designedconcrete support at bed to suit the buried penstock and on the bends anchor
blocks have been proposed.
The penstock will have a smooth entry of flow at forebay by providing well
designed bell mouth.
The parameter used to indicate the circumstances under which the water hammer
should be considered is called the critical time.
P= Rated HP.
P= 13211.2 HP
H= 599.02 Feet
P/H = 22.05
P/H = 0.05
Therefore D = 1.79 m
h= steady head =
Gate closure
aT/2L = 3.08
Hence Ok
Safe
The penstock thickness is provided as 28mm and 8 mm thickness in two equal divisions for
entire length from start of Power house to Forebay.
Therefore hf = KsxV1.9/D1.1x(1/1000)
0.34 286.85 x 1
D2xD1.1 1000
4.9
15.89 ÷ D
(Per Rft.)
Penstock Length = 6004.23 rft
Total hf = 95383.61 ÷ D4.9
Entrance Loss
0.2xve2
Entrance Loss = 2g
Bend Loss
hb = KV2/2g
1610 ÷ D4
..= 101327.3 x HL
4 4 4.9
D D D
Hence the economical diameter is provided in accordance with the requirements as per
economical diameter worked out above which is 2.8 metres as the penstock length is quiet
long.
Bifurcation of Penstock
The foundation of the Anchor blocks shall be designed so that the maximum pressure on
the foundation shall not exceed the allowable bearing capacity of the soil determined as
specified in IS 1904-1978. The permissible bearing capacity shall be increased in
accordance with IS: 1893-1975 for seismic condition.
Since the support pier is not designed to resist significant longitudinal forces and remains
therefore unaffected by the component of this weight parallel to the pipe. IS 11639 Part-I
have been followed for the design of saddle supports.
For Lashpathri - Iproject the spacing between any two saddles, structural stability and
safety against sliding and overturning have been found in order in respect of the fact that
maximum pipe line shall be laid underground by way of back filling .
6.10.1 General
The layout of the power house has been prepared as per relevant IS Codes including IS
12800 (Part 3); 1991.
The consultants propose to have a surface power house on a relatively plain terrain and are
large enough to accommodate the electrical and mechanical equipment. The site for the
power house is geologically stable on the right bank of the river. The power house is indoor
type so that all erection and maintenance of the machines is done within the power house
itself.
The size of the power house has been arrived at after the detailed layout plan of the units,
control panels and service space and other requirements. The size and location of the power
house also takes into consideration the surface drainage, ventilation, lighting etc. The location
of the gantry columns has been based on the economy and the machine layout.
The location of power house site and the fixing of the machine hall floor level and the
setting level of turbines is also determined by the HFL and minimum tail water level in the
stream with the machine floor having been kept above the HFL ensuring that the power
house is not flooded.
a. Superstructure
i. Roof
ii. Roof support system
iii. Gantry Girder
iv. Gantry Columns
v. Cross Beams or Braces
vi. Panel Walls
vii. Floor
Dead Loads: This includes the self load of the structure and permanent superimposed
loads
Crane loads: Weight of the fully loaded crane and longitudinal and lateral impact
forces.
The permissible stresses for rivets, bolts, etc are increased by 25% only in all the cases
from serial 2 to 6.
In view of the site conditions, location, power house size and the economy in the
construction truss of structural steel with CGI sheeting has been proposed. The
thickness of the sheets has been determined on the spacing of the purlins. The CGI
sheets shall conform to IS: 277. It is laid on purlins and is secured by hook bolts 8 to 10
mm diameter spaced at 400 mm Centre to centre. Joints along the length have an
overlap of 150 mm and joints along the sides of the sheet overlap two corrugations
and rivets /screws have been proposed at 300 mm c/c. The holes will be provided
through the ridge and curved washers have been provided to prevent leakages.
6.10.6 Columns
From the economy of construction and the speed of construction RCC columns are
ideally suited to the site. Columns are subject to moments in longitudinal and
transverse directions and direct thrusts and are designed for biaxial bending and direct
thrust using the design procedure of IS: 4247-Part II and the reinforcement as per
6.10.8 Substructure
This is the part of the structure below the machine hall floor and is proposed to be
rigid gravity structure. The stability analysis therefore considers the following:
c. Floatation
The analysis is done in both longitudinal and transverse directions and the loads for
d. Live loads
g. Weight of water acting on the substructure i.e. in scroll case, draft tube etc.
h. Back-fill pressure
j. Uplift pressure
The generator floor is designed to carry the load of machines, live load and any other thrust
transferred through turbines, generators or any other machine. It has been designed as
RCC raft with openings/pits as required for equipment and the cable trenches.
Out flow from two numbers draft tube openings shall be flown into a common tailrace
pool which shall finally be led to the stream through a tail channel. The channel shall be
RCC structure or random rubble masonry structure. The channel is designed to have a
discharging capacity of 40%% of one unit discharge under minimum tail water level
condition and 120% of full design discharge of both the turbines under normal and
maximum tail water level
conditions. The discharging capacity in each case is determined by Manning's formula
which shall be rectangular in shape with RCC bed raft laid in reverse slope in pool, to
form the crest at its end. The crest level has been provided in conjunction to the flow
depth in Tailrace Channel to maintain minimum tailrace water level during lowest
power generation from the plant during lean flow condition to avoid cavitations’ of
turbines. Tail race channel shall be directly connected to the converged pool. This
structure is used for sending the tailrace waters from power house to Source stream.
The tail race channel has been designed as RCC structure with for required discharge
capacities with free board of 0.6 m. The channel has been designed as a rectangular
RCC structure up to the bank of the stream and thereafter on crate construction in the
stream bed making it flexible and repairable after flood seasons. The size of the tail race
is 3.6m wide with the full length made of RCC with Tailrace pool size as shown in
Drawing. The FSD in the channel shall be 0.7 metres at a bed grade of 1 in 800.