PROJMAN Documentation FINAL
PROJMAN Documentation FINAL
Recyclable Waste
Presented By:
Jeric Mangrobang
Weynard Ramilo
John Samuel Sañada
John James Tabulao
Submitted to:
Mr. Bernardino R. Roda
Mr. Christopher T. Carpio
Mr. Jun Kevin S. Pedrosa
PROJECT DEFINITION & PLANNING
Project Charter
Title of the Project: SMRT: Waste Segregation System for Recyclable and Non-recyclable
Waste
Project Description:
Project Goal/Purpose:
Our project's goal is to create affordable and easily accessible waste segregation
technologies by utilizing Arduino equipment to develop Internet of Things solutions for waste
management. We aim to encourage sustainable waste segregation at the source by utilizing
IoT sensors and machine learning algorithms. Our project aims to reduce landfill waste,
optimize waste management processes, and lessen environmental pollution by integrating
IoT technologies.
Project Sponsor(s):
• Celso Natividad (Homeowner of Classica Northgate Brgy. Sto Cristo, San Jose Del
Monte Bulacan)
• Jeric Mangrobang
• Weynard Ramilo
• John Samuel Sañada
• John James Tabulao
Project Statement of the Problem
Project Objectives:
By the end of 2024, the project team will successfully implement a Waste
Segregation System for Recyclable and Non-Recyclable Waste in Classica Northgate
community, Brgy. Sto Cristo, San Jose Del Monte Bulacan, with the following targets:
Project Scope:
The Project Team is a collection of experts that collaborate to achieve project goals
by using their various talents and knowledge. Their responsibilities include planning,
executing, and monitoring project tasks to ensure they are completed on schedule and
within budget.
The Project Duration is the overall time allotted to complete the project, from the
beginning planning phase to the final delivery and closure, which is commonly measured in
weeks or months.
Project Schedule:
Estimated Budget:
This budget overview is crucial for managing the project effectively, giving
stakeholders a clear picture of the project's finances. It covers everything we will spend on,
like salaries, buying things, tools, extra costs, and anything else we need to pay for.
Materials Price
Software Cost PHP 2,000.00
Hardware Cost PHP 15,000.00
Frame Cost PHP 3,000.00
Labor/Professional Fee PHP 600,000.00
Training PHP 25,000.00
Support PHP 1,000
Booth PHP 3,000
Deployment PHP 1,000
Total PHP 650,000.00
Contingency = 10% of Total PHP 65,000.00
Estimated Total: PHP 715,000.00
Homeowners: Homeowners are individuals or families residing in the communities where the
system will be developed. The efficacy and effectiveness of waste management systems have
a direct effect on them. Proper waste segregation and collection results in an improved
environment with less smells, and better public health outcomes for homeowners.
Resident Communities: More categories of people residing in the project area, such as
homeowners, renters, and other people, are included in resident communities. They share
services, infrastructure, and common areas that are impacted by waste management systems.
Since they are the system's main consumers, resident communities are crucial stakeholders
in the waste segregation process.
Future Researchers: Future researchers are academics, professionals, and students who are
interested in learning about sustainability practices, machine learning applications, and waste
segregation systems.
Project Manager: The Project Coordinator oversees the project, ensuring it stays on track, on
budget, and meets its goals. They are responsible for planning, executing, and closing the
project, managing the team, and communicating with stakeholders to ensure project
alignment with organizational objectives.
Development Team: Developers are responsible for building the system. They design,
develop, and implement the waste management system, utilizing their technical expertise to
integrate machine learning models and IoT technologies effectively.
Quality Assurance: QA Analysts and Testers ensure the system meets quality standards. They
perform testing to identify bugs, verify that the system works as intended, and ensure it meets
the project requirements. Their role is crucial in delivering a reliable and effective system,
making sure it is ready for deployment to end-users.
Project Client Approval
Project approval is the official process by which stakeholders examine and approve
the project plan, ensuring that it is consistent with company goals and satisfies all relevant
requirements. This permission signals the formal beginning of project implementation.
Introduction
The Scope Management Approach for Waste Segregation System of Solid Materials
project:
1. Scope Definition:
• Clearly define the boundaries of the project, including what is included and what is
excluded.
• Identify the key deliverables, such as the machine learning model, software interface,
and documentation.
2. Stakeholder Identification:
3. Scope Planning:
• Develop a detailed project scope statement outlining the objectives, scopes, and
limitations.
• Create a Work Breakdown Structure (WBS) to break down the project into
manageable tasks and activities.
• Utilize project management software for tracking scope, tasks, and milestones.
• Use communication tools or software to facilitate collaboration among team
members and stakeholders.
5. Risk Management:
• Identify potential risks that could impact the project scope, such as technical
challenges, data quality issues, or regulatory changes.
• Regularly review and update throughout the project lifecycle.
6. Quality Management:
• Establish quality standards and metrics to measure the performance and effectiveness
of the waste segregation system.
• Conduct regular quality assurance activities, such as code reviews, testing, and
validation, to ensure compliance with the defined standards.
• Implement continuous improvement processes to address any quality issues and
enhance the system's capabilities over time.
7. Resource Management:
• Allocate resources, including personnel, equipment, and budget, based on the project
scope and requirements.
• Monitor resource utilization and availability to ensure optimal allocation and avoid
resource constraints.
• Develop contingency plans for addressing resource shortages or unexpected changes
in resource requirements.
Scope Definition
The Scope Definition for the Waste Segregation System of Solid Materials project
includes a detailed description of the project and its deliverables, including references to
papers created throughout the requirements definition process. The main documents for this
process are the requirements documentation, requirements traceability matrix, and
requirements management plan.
This project description and deliverables were developed based on the requirements
collection on the process and input from subject matter experts in software development,
machine learning, and waste management. The features and functionalities that need to be
included in the scope can be determined through research on comparable waste segregation
systems and machine learning applications. Developing the scope by identifying the most
feasible and effective solutions involves taking into consideration other methods for waste
segregation and machine learning algorithms.
The project aims to develop a Waste Segregation System of Solid Materials, leveraging
technology to automate waste sorting. Deliverables include software, trained models, and a
user interface. Exclusions involve physical infrastructure and policy issues. Assumptions
include data access and regulatory compliance. Stakeholders include waste authorities and
communities. The approach entails agile methods and stakeholder collaboration.
Work Breakdown Structure
A Work Breakdown Structure (WBS) is a fundamental tool that breaks down a project
hierarchically into more manageable tasks, deliverables, or smaller components. It serves as
a roadmap for both project Documentation and System Development, facilitating their
planning, execution, and monitoring. By organizing the work required to achieve the project's
objectives in a logical and structured manner, the WBS ensures clarity and efficiency
throughout the project lifecycle. Whether it is delineating the phases of project
documentation or outlining the stages of System Development, the WBS provides a
framework for effective resource allocation, scheduling, and cost estimation.
Project Documentation
System Development
Scope Verification
As this project progresses, the project team verifies that all requirements and
specifications have been fulfilled by comparing the completed deliverables to the original
scope as stated in the Scope Management Plan. The client or other important stakeholders
engage in regular reviews and demonstrations of project deliverables to provide feedback
and ensure that expectations are being accomplished. Instead of delaying until the end of the
project, deliverables are formally accepted and approved by the client or other specified
stakeholders as they are finished. This encourages communication and reduces the possibility
of miscommunications or disagreements on the standard of the deliverables. In a project,
scope verification is a continuous process that involves regular checkpoints to evaluate
progress and ensure submission with the goals and scope of the project.
Scope Control
Purpose
Scope Description
- The scope of this project includes developing and implementing a complete waste
segregation system for our client. The system's primary goal will be to properly
categorize and segregate solid waste items according to their material makeup.
Limitations
- Waste streams may contain a variety of components, including mixes and composite
goods. Machine learning techniques may fail to distinguish between similar materials
and complicated waste products.
- Environmental elements such as illumination, camera angles, and background clutter
can all influence machine learning algorithms' success in garbage sorting tasks.
- The success of machine learning models in trash segregation is strongly dependent on
the quality and amount of training data provided. Limited or biased datasets may
result in classification errors.
Exclusions
- The scope excludes integration with external waste management systems, such as
inventory management or transportation systems. The system will concentrate
entirely on garbage classification and segregation within its specified domain.
PROJECT DEFINITION & PLANNING
TIME MANAGEMENT
The table presents a thorough project plan for creating and implementing a "Smart
Waste Bin System for Solid Materials." Each row in the table denotes a particular task or
component of the project, and the corresponding columns list the people in charge of carrying
it out.
The project team uses this organized plan as a road map to help them navigate each
phase of the project lifecycle. It includes major areas like quality control, stakeholder
engagement, procurement management, and project documentation, proposal, scope, time,
cost, and risk management.
The plan makes it clear who oversees each task and guarantees accountability by
giving tasks to the group as a whole or to individual members. This encourages cooperation
and teamwork among team members, which results in the project being completed
effectively.
The Activity List in Time Management is a thorough inventory of all project tasks or
activities necessary to meet project goals. It is an essential tool for organizing, prioritizing, and
sequencing project tasks, allowing for more effective project scheduling and resource
allocation.
Sequence Activities:
Project Documentation:
Project Proposal:
Project Charter:
Scope Management:
Time Management:
Cost Management:
Quality Management:
Stakeholder Management:
• Initiated following Project Charter approval and runs parallel with project
execution.
Research:
• Conducted prior to Waste Bin Designing and Machine Learning & Application
to inform decisions.
• Follows research and planning phases to design waste bins based on project
requirements.
Finalizing Project:
• Concludes all project execution activities and ensures all deliverables meet
quality standards.
• Follows Finalizing Project to deploy the project and present it to the client.
Develop Schedule:
- The Plan Cost Management method entails developing an accurate cost management
plan that outlines how project costs will be managed, monitored, and controlled throughout the
SMRT project. To ensure accuracy, use ±10% tolerance, cost estimating methodologies, and tools
such as Microsoft Excel and project management software. The cost baseline will be set using a
time-phased budget with contingency and management savings (5-10%). Earned Value
Management (EVM) will be used to assess cost performance, with important measures including
Cost Variance (CV) and Cost Performance Index (CPI). Weekly updates and monthly reports will
guarantee accurate expense tracking. Documentation shall consist of the cost management
strategy, cost estimates, budget records, and modification requests. Roles are specified with the
project manager in charge of cost control, assisted by a Financial Analyst and project team
members. Regular evaluations at project milestones will ensure that the plan remains in line with
the project's objectives.
Estimate Costs:
- In this process, the project team approximates the monetary resources needed to
complete project work. Various estimating techniques are used to predict the costs of the
project’s activities.
Description
• Category: This column lists the different budget categories for the project, including project
management, hardware, software, training, support, booth, and contingency.
• Estimated Cost: The projected amount allocated for each category before the project begins.
It represents the budgeted figures for each aspect of the project.
• Actual Cost: The actual amount spent on each category. As of now, no expenses have been
incurred, so all actual costs are ₱ 0.
• Variance: The difference between the estimated cost and the actual cost. It is calculated as
“Variance = Estimated Cost - Actual Cost”. Since no money has been spent yet, the variance
equals the estimated cost for all categories.
Summary
• The Total Project Cost combines the estimated, actual, and variance amounts for all categories,
providing an overview of the project's financial status.
• As actual costs are recorded, the variance will help monitor spending, indicating areas where
costs are either under or over the budget.
This table is essential for project managers to track and control project expenses, ensuring that the
project stays within the allocated budget and identifying any financial discrepancies early on.
Cost Control:
This project focuses on controlling costs at every stage, from planning to deployment. It
carefully manages resources to save money and stick to the budget.
This table provides a current snapshot of the project's cost performance as of March 25, 2024.
Please note that these figures are subject to change as the project progresses. The project emphasizes
cost control at every stage, ensuring resources are managed efficiently to stay within budget.
This table presents project performance metrics related to cost control. It includes columns
for Planned Value (PV), Earned Value (EV), Actual Cost (AC), Cost Variance (CV), and Cost Performance
Index (CPI) for each month. PV represents the budgeted cost for the planned work, EV represents the
value of completed work, AC represents the actual costs incurred, CV shows the variance between EV
and AC, and CPI indicates the cost efficiency of the project.
This table provides a current snapshot of the project's cost performance as of March 18, 2024.
Please note that these figures are subject to change as the project progresses. The project emphasizes
cost control at every stage, ensuring resources are managed efficiently to stay within budget.
Planned Value (PV): The Planned Value (PV), also known as the Budgeted Cost of Work Scheduled
(BCWS), represents the authorized budget assigned to scheduled work. It shows the value of the work
that was planned to be completed up to a certain point in time.
Earned Value (EV): The Earned Value (EV) represents the value of the work that has been completed
and verified up to a certain point in time. It is typically calculated based on the budgeted cost of work
performed (BCWP).
Cost Variance (CV): The Cost Variance (CV) measures the variance between the earned value (EV) and
the actual cost (AC). It indicates whether the project is under or over budget.
Actual Cost (AC): The Actual Cost (AC) represents the actual expenditure incurred for the work
performed up to a certain point in time. It is also known as the Actual Cost of Work Performed (ACWP).
Cost Performance Index (CPI): The Cost Performance Index (CPI) measures the cost efficiency of the
project, indicating how much value is being earned for every unit of actual cost spent. A CPI greater
than 1 indicates favorable cost performance, while a CPI less than 1 indicates unfavorable
performance.
Control Cost (WBS):
WBS Control Cost involves tracking and managing project expenses according to the Work
Breakdown Structure (WBS). It ensures that costs are monitored and controlled at every level of the
project's hierarchy, allowing for effective budget management and resource allocation.
Project Documentation
Project documentation in cost management involves carefully recording and organizing all
financial data and related papers throughout the project's duration. It offers accessibility, accuracy,
and accountability when tracking project costs, allowing for more efficient budgeting and financial
control.
System Development
System Development in Cost Management refers to the costs involved with planning, creating,
and implementing software or technology solutions for a project. It focuses on maximizing resources
and reducing costs throughout the development process to achieve timely delivery within budget.
Fig. 11 System Development
PROJECT DEFINITION & PLANNING
HUMAN RESOURCE MANAGEMENT
Introduction
• Ensure the project has the right people with the necessary skills.
• Monitor and enhance the performance of project team members.
• Develop team members' skills and knowledge to improve project outcomes.
• Keep team members motivated and engaged throughout the project.
• Manage and resolve conflicts within the project team.
Roles and Responsibilities
Staffing management is essential for the timely and successful completion of the
project. This plan identifies the required skill sets, defines roles and responsibilities, and
establishes processes for performance monitoring and risk management. By ensuring that the
right people are in the right roles at the right times, the project can achieve its objectives,
meet deadlines, and maintain high standards of quality.
This table outlines the roles of the project team and the specific tasks each member is
responsible for. A checklist is used in each column to indicate the involvement of team
members in their respective tasks.
Organizational Chart
Introduction
Communication Objectives
1. Team Meetings
• Daily Stand-ups
i. Purpose: Provide quick, daily updates to keep the team aligned and
identify any blockers.
ii. Participants: Entire team (developers, Scrum Master, Product Owner).
iii. Structure:
1. What did you do yesterday?
2. What will you do today?
3. Are there any impediments in your way?
iv. Duration: 15 minutes.
v. Tools: Video conferencing (for remote teams), Trello or Jira for task
tracking.
• Weekly Team Meetings
i. Purpose: Review weekly progress, plan for the upcoming week, and
discuss any challenges.
ii. Participants: Entire team.
iii. Structure:
1. Review of completed tasks.
2. Planning for the upcoming week.
3. Discussion of any challenges or blockers.
iv. Duration: 1 hour to 3 hours.
v. Tools: Video conferencing, Trello or similar tools for visual task
management
2. Project Adviser Reports
• Weekly Status Reports
i. Purpose: Provide regular updates on project progress and any issues.
ii. Structure:
1. Summary of activities and progress.
2. Achievements and milestones.
3. Challenges and issues faced.
4. Plans for the next period.
iii. Frequency: Weekly.
iv. Format: Written report, email, or shared document.
• Milestone Reports
i. Purpose: Report on the completion of key project milestones.
ii. Structure:
1. Overview of the milestone achieved.
2. Deliverables completed.
3. Issues encountered and how they were resolved.
4. Next steps and upcoming milestones.
iii. Frequency: As milestones are reached.
iv. Format: Written report, presentation, or meeting.
3. Client Report
• Progress Reports
i. Purpose: Update the client on project status and ensure alignment.
ii. Structure:
1. Summary of work completed.
2. Progress against the project plan.
3. Upcoming tasks and milestones.
4. Issues and risks, with mitigation plans.
iii. Frequency: Monthly.
iv. Format: Written report, email, or presentation.
PROJECT DEFINITION & PLANNING
RISK MANAGEMENT PLAN
Introduction
Risk management is an important aspect of every successful project, especially
in the developing field of waste management systems. Our project, "SMRT: Waste
Segregation System for Recyclable and Non-Recyclable Waste," intends to transform
how trash is sorted and processed, making a substantial contribution to
environmental sustainability and resource efficiency. Effective risk management is
recognizing, analyzing, and prioritizing risks, followed by coordinated actions to
reduce, monitor, and control the likelihood and severity of unplanned occasions.
Risk Management Processes
• Identify Risks:
• Prioritize Risks:
• Communication:
Risk Review
A Risk Management Plan includes an ongoing review of recognized risks and the
efficacy of risk actions implemented.
Risk Mitigation
Technical Failure such as the machine is Train users and staff to troubleshoot the
not working. system.
Train the machine learning to recognize the
Difficulty in identifying the material.
material.
Harsh environmental conditions such as
Select materials and components resistant to
extreme temperatures, humidity, or
environmental factors and implement
exposure to corrosive substances can
protective measures like enclosures or
impact the performance and lifespan of
climate control systems.
system components.
Develop an offline mode feature for the
Unstable Internet connection may affect waste segregation machine, allowing it to
the functionality of the machine. continue basic operations and perform critical
tasks even without internet connectivity.
Include a backup power supply such as
Power Supply Interruptions.
another battery
Table 7 Project Risk Response Strategy
PROJECT EXECUTION AND PROJECT PERFORMANCE & CONTROL
QUALITY MANAGEMENT
Introduction
Quality management is essential for delivering successful projects because it
ensures that the project meets required standards and satisfies stakeholder
expectations. When a project delivers on its promises in terms of features,
performance, and reliability, customers are more likely to be satisfied. Satisfied
customers are more likely to return for future projects and recommend your services,
which helps build a positive reputation.
Focusing on quality also builds stakeholder confidence. Delivering a project
that meets or exceeds expectations builds trust among customers, investors, and
team members. This trust encourages stakeholders to support current and future
projects. Moreover, high-quality standards and clear expectations boost team morale.
When team members take pride in their work and know their contributions are valued,
their productivity and job satisfaction increase.
Roles and responsibilities
Roles Responsibilities
Project Manager • Develop and implement the project's quality
management plan, outlining quality standards,
practices, resources, and documentation.
Developer • Write safe, effective, and maintainable code that
complies with guidelines and standards.
Quality Assurance • Share quality-related comments and
modifications with stakeholders and the
development team.
Documentation Lead • Examine and confirm that all project
documentation (requirements, design
specifications, test plans, and user manuals)
meets quality standards.
Table 8 Roles and Responsibilities (Quality Management)
The UAT plan for SMRT Waste Segregation System comprises six key test cases,
including user registration and login, dashboard functionality, waste segregation
process, reporting and analytics, admin controls, and integration testing. Each test
case is accompanied by a description of the specific functionality being tested, the
expected result, and the actual result observed during testing. Additionally, the
Pass/Fail column indicates whether each test case met the expected result or not.
• Quality Improvement
Quality Improvement in Quality Management is concerned with the ongoing
improvement of processes, goods, and services through systematic efforts to identify
and correct problems. This increases productivity, effectiveness, and customer
happiness by cultivating a continual culture of excellence.
2. Stakeholder Identification
• Project Sponsor: Homeowners President (High Power, High Interest, High
Impact)
• Project Manager: Project Coordinator (High Power, High Interest, High
Impact)
• Development Team: Engineers, Developers (Medium Power, High Interest,
High Impact)
• End-Users: Homeowners, Residents (Medium Power, High Interest, High
Impact)
• Quality Assurance: QA Analysts, Testers (Medium Power, Medium Interest,
Medium Impact)
• Future Developers: Academics, Students (Low Power, High Interest, Medium
Impact)
3. Stakeholder Analysis
Stakeholder analysis is the systematic process of identifying, evaluating, and
prioritizing stakeholders in a project. It seeks to understand their interests,
influence, and possible impact on the project's success, allowing for more effective
communication, engagement, and stakeholder relationship management
throughout the project lifetime.
STAKEHOLDER POWER INTEREST IMPACT
Project Sponsor:
• Regular meetings, project updates, key decision involvement.
Project Manager
• Daily stand-ups, weekly project reviews, risk management sessions.
End-Users:
• Training sessions, user manuals, feedback surveys.
Future Developers:
• Workshops, research collaborations, access to project data.
Development Team:
• Technical workshops, code reviews, progress demos.
Quality Assurance:
• Regular testing cycles, bug tracking meetings, quality reviews.
Fig. 24 Item(s)
Fig. 25 Labor
Vendor Information
Procurement Schedule
The Procurement Schedule defines the timeframe for purchasing goods and services,
including major milestones and deadlines for procurement operations.
• Activities Involved:
o Defining the procurement requirements.
o Developing a procurement strategy.
o Setting timelines and responsibilities.
o Preparing the procurement documentation.
Vendor Selection
• Importance: Selecting the right vendor(s) is crucial for ensuring that the procured
goods or services meet quality standards and are delivered on time.
• Activities Involved:
o Issuing requests for quotations (RFQs). (Refer to Fig. 26 Request for Quote
Template)
o Negotiating terms and conditions with the shortlisted vendors.
o Finalizing the vendor selection and notifying the selected vendor(s).
Contract Awarded
• Importance: Formalizing the contract ensures that both parties have a clear
understanding of their responsibilities, the scope of work, delivery timelines, and
payment terms. It provides a legal basis for the transaction and serves as a reference
point in case of disputes. (Refer to Figure 27, 28, & 29 Contract Page 1, 2, & 3)
• Activities Involved:
o Reviewing and finalizing the contract details.
o Signing the contract by authorized representatives of both parties.
o Communicating the contract details to relevant stakeholders.
Pick Up Goods/Services
• Importance: Ensuring that all picked-up items or services meet the required
standards before making the final payment helps in maintaining quality control and
protecting the project from substandard deliveries.
• Activities Involved:
o Inspecting the picked-up goods or services.
o Testing and verifying that they meet the project's specifications and quality
standards.
o Documenting any discrepancies or defects.
o Formally accepting the goods or services if they meet the requirements or
rejecting and requesting replacements/adjustments if they do not.
o Updating inventory or project documentation to reflect the acceptance.
Payment
A Request for Quote (RFQ) is a standardized form that requests price quotes from potential
suppliers for specified goods or services.
Service Contract Template
This Service Contract Agreement outlines the terms and conditions under which
services will be provided by the contractor to the client. It defines the scope of work, payment
terms, responsibilities, and other essential details to ensure mutual understanding and
satisfaction.
Introduction
A Change Management Plan is a strategic document that outlines the steps and processes
necessary for managing and implementing changes within an organization. Its primary goal is to
ensure that changes are carried out smoothly, effectively, and with minimal disruption to business
operations. The Change Management Plan records and monitors the essential details needed to
successfully handle project changes from the beginning to the end of the project. This plan is
developed during the project's Planning Phase. It is designed for the project manager, project team,
project sponsor, and any senior leaders whose backing is crucial for the plan's execution.
The Change Request Process Flow Requirements in a Change Management Plan describe the
methodical methods for submitting, assessing, and approving change requests within a project. It
defines the criteria, roles, and duties for managing change, ensuring that changes are fully evaluated
and executed in accordance with project objectives.
1. Submitter:
• Initiates change requests by filling out the CR Form.
2. Project Manager:
• Receives and logs CRs.
• Facilitates the evaluation and authorization processes.
• Presents change requests to the Change Control Board (CCB) for review and approval.
3. Project Team:
• Reviews and evaluates CRs.
• Develops solutions and proposes changes.
• Implements approved changes.
4. Change Control Board (CCB):
• Reviews and assesses the impact of proposed changes on project scope, schedule, and
budget.
• Makes decisions regarding the approval, rejection, or deferral of proposed changes.
• Ensures that changes align with project objectives and stakeholder requirements.
• Provides oversight and governance of the change management process.
5. Stakeholders:
• Provide input and feedback on proposed changes.
• Approve changes as needed, based on their impact on project objectives and stakeholder
interests.
A change request typically initiates the change control process. This request can come from
stakeholders seeking new features, the need to fix issues that arise during the execution phase,
upgrades, or various other reasons. Regardless of the source or nature of the change, change control
assesses its value and determines how to feasibly implement it.
Fig. 33 Change Request Form
Change Management Log
Once a change has been identified and approved, it's crucial to have a robust change
management logging system in place to track the change throughout its lifecycle.
• Change management logging provides a centralized repository for documenting all changes,
including their initiation, approval status, implementation details, and outcomes.
• It establishes accountability by recording who initiated the change, who approved it, and who
is responsible for its implementation.
• Change management logging enables project managers and stakeholders to track the progress
of each change against the planned schedule.
• It helps identify any delays or bottlenecks in the change implementation process, allowing for
timely interventions to keep the project on track.
3. Resource Allocation
• By logging changes, organizations can effectively allocate resources, such as personnel, time,
and budget, to ensure that changes are implemented efficiently and within the allocated
constraints.
4. Risk Management
The Change Control Process is a systematic technique to controlling changes to project scope,
timeline, or resources. It entails seeking, analyzing, authorizing, and implementing modifications in a
controlled way to reduce risks and ensure project alignment with objectives.
Step Description
Generate CR A submitter fills out a CR Form and submits it to the Project Manager.
Log CR Status The Project Manager records the CR in the CR Log and updates its status as
it progresses through the CR process.
Evaluate CR Project team will review the CR, estimate the level of effort required to
implement it, and develop a proposed solution for the suggested change.
Authorize Obtain approval to proceed with incorporating the suggested change into
the project.
Implement If approved, make the necessary adjustments to implement the requested
change and update the submitter and other stakeholders on the CR status.
Update Change Log Any updates regarding the change, including approvals, implementation
progress, and completion status, are recorded in the Change Log.
Introduction
The Transition Plan outlines the process and activities required to transition the
project from the implementation phase to operational status. It ensures that all aspects of
the project are effectively handed over to the operational teams, and that all stakeholders
are prepared for the project's conclusion.
Workforce Transition:
Workforce transition ensures that the project team and operational teams are well-prepared for their
new roles and responsibilities in managing the Waste Management System. This process helps
maintain continuity and efficiency as the project moves from development to operational phases.
• Staff Reassignment: Plan for reassigning project team members to new roles within the Waste
Management System implementation team or other relevant projects. This ensures that
experienced staff continue to contribute their expertise to the project or to other areas where
their skills are needed.
• Training and Support: Provide necessary training to operational teams on how to operate and
maintain the Waste Management System effectively, leveraging machine learning technology.
This training helps ensure that the teams are competent in using the system and can handle
any issues that arise.
• Communication: Conduct regular updates and meetings to keep the workforce informed of
the transition progress and address any concerns or questions they may have. Clear
communication helps ensure that everyone is on the same page and that any potential issues
are addressed promptly.
Knowledge Transfer:
Knowledge transfer is essential to ensure the operational teams are fully prepared to manage and
maintain the Waste Management System effectively. This involves sharing important information and
skills developed during the project with those who will be responsible for its ongoing use.
• Knowledge Sharing Sessions: Conduct sessions to transfer critical knowledge from the project
team to the operational teams, focusing on the operation and maintenance of the Waste
Management System. These sessions help ensure that the operational teams understand how
to use the system properly and can troubleshoot any issues that may arise.
• Documentation: Provide detailed documentation of the Waste Management System's
processes, decisions, and lessons learned, ensuring that operational teams have access to
valuable insights for efficient system management. This documentation serves as a reference
guide, helping teams understand the system's functionality and any important decisions made
during the project.
Intellectual Property:
In the context of our project, which introduces an innovative Waste Management System
empowered by machine learning technology, Intellectual Property (IP) refers to the unique
creations and innovations developed during the project. This includes the machine learning
algorithms that differentiate between Recyclable and Non-recyclable waste, the software and
models used to classify waste materials in real-time, and any IoT solutions designed for waste
management using Arduino equipment.
• IP Handover: Ensure all intellectual property developed during the project, such as algorithms,
software, and IoT designs, is formally transferred to the client or appropriate stakeholder. This
process includes documenting and transferring ownership rights, ensuring the client or
stakeholder can utilize, modify, and benefit from the IP without legal issues.
• Documentation: Provide comprehensive documentation of all IP elements, including detailed
descriptions of the machine learning models, software architecture, IoT configurations, and
any other technological innovations. This ensures that the client or stakeholder has all
necessary information to maintain, use, and further develop the technology.
A well-structured schedule is essential for the successful transition from project development to
operational use of the Waste Management System. It helps ensure that all necessary activities are
completed in a timely manner, maintaining project progress and minimizing disruptions.
• Transition Timeline: Develop a detailed schedule outlining all transition activities, including
training sessions, system setup, and handover of responsibilities. Each activity should have
specific deadlines aligned with the project's overall timeline. This ensures that the transition
progresses smoothly and according to plan.
• Milestones: Identify key milestones for the transition process and ensure they are met on
time. These milestones mark significant achievements or stages in the transition, such as
completion of training sessions or system setup. Meeting these milestones is crucial for
tracking progress and ensuring that the transition stays on schedule.
PROJECT CLOSE-OUT
PROJECT CLOSE-OUT ACTIVITIES
Ensuring a smooth transition and completing all project tasks is vital for consolidating
achievements, finalizing deliverable acceptance, and gathering insights for future waste
management endeavors with innovative technologies.
Confirming Work Completion
• Verification: Ensure that all project work, including the development and implementation of
the Waste Management System, has been completed in accordance with the project plan,
aligning with our goal of optimizing waste management processes.
• Inspection: Conduct thorough inspections and reviews to ensure that the Waste Management
System meets the required standards and is ready for operational use, reflecting our
commitment to delivering high-quality solutions.