DFCC Project, Contract CT P-12 ON SITE INSPECTION PLAN FOR RESOURCES PROCUREMENT
Inspection by and Type of
Sr. Inspection, measuring and Records to be Remarks
Material / Activity Frequency of Testing Reference Standard Specification limit for acceptance Responsibility Inspection
No. test equipment maintained
Consortium Engineer
2 Slump Test Random IS:456-2000 IS:7320-1974 As per Mix Design Slump apparatus Site In charge Site Records W W
1-5 m³ = 1 sample,
6-15 m³ = 2 sample, 28 days Compressive Strength should be
Cube Mould 150X150X150
3 Concrete Samples (Cubes) 16-30 m³ = 3 sample, IS: 456 - 2000 as per Acceptance Criteria as per IS:456- Site In charge Cube Register W W/R
mm
31-50 m³ = 4 sample 2000.
51M³ & onward = 1sample/50m³
4 Air Content Random Max. as per 10262 2% for Concrete & 3% Shot Crete Air Entrant meter. Site In charge Site Records W W
1 Density of each Cube For each cube before testing IS:7325-1974 Mix Design Balance & Scale Site In charge Lab test result W -
For each (extra cast) concrete Indicative for Initial knowledge and
2 7 Days Comp. Strength IS:456-2000, IS:516-1970 CTM Site In charge Lab test result W -
sample Action, if required
28 days Compressive Strength should be
3 28 Days Comp. Strength For each concrete sample IS:456-2000, IS:516-1970 as per Acceptance Criteria as per IS:456- CTM Site In charge Lab test result W W/R
2000.
IX Batching Plant
2 Adjustment of Blade gap in Mixer Once / week, Plant Manual Gap for Blade 10 mm Measuring Tape and Vernier Site In charge Site Measurement W W
X Bentonite
1 Liquid Limit of Bentonite Once for Source IS: 6186 - 1986, IS: 2720 Part 5 300 - 450% As per IS: 6186 Site In charge Auth Lab result W W
2 Sand Content of Bentonite Powder Once for Source IS: 6186 - 1986, IS: 2720 Part 5 7% Max. As per IS: 6186 Site In charge Auth Lab result W W
3 Differential Free Swell Once for Source IS: 6186 - 1986, IS: 2720 Part 40 540% Min. As per IS: 6186 Site In charge Auth Lab result W W
DFCC Project, Contract CT P-12 ON SITE INSPECTION PLAN FOR RESOURCES PROCUREMENT
Inspection by and Type of
Sr. Inspection, measuring and Records to be Remarks
Material / Activity Frequency of Testing Reference Standard Specification limit for acceptance Responsibility Inspection
No. test equipment maintained
Consortium Engineer
4 pH value of Bentonite Suspension Every Pile IS: 6186 - 1986 9 - 11.5 pH Meter / pH papers Site In charge Site Test Results W R
5 Viscosity Every Pile IS: 6186 - 1986 30 - 60 Sec. Marsh Cone and Stop Watch Site In charge Site Test Results W R
XI Bridge Bearings
A Cast Steel
B Mild Steel
C Forged Steel
C Stainless Steel
1 Hardness From each batch at random IS: 3400 (Part – 2) - 2003 50 ± 5 IRHD At Manufacturer's Lab Site In charge MTC & Lab Results W W
2 Min. Tensile Strength From each batch at random IS: 3400 (Part – 1) - 1987 15.5 MPa At Manufacturer's Lab Site In charge MTC & Lab Results W W
3 Minimum elongation at break From each batch at random IS: 3400 (Part – 1) - 1987 Ref. Table 1 of IRC:83 (Part II)-1987 At Manufacturer's Lab Site In charge MTC & Lab Results W W
4 Maximum compression set From each batch at random IS: 3400 (Part – 10) - 1977 Ref. Table 1 of IRC:83 (Part II)-1987 At Manufacturer's Lab Site In charge MTC & Lab Results W W
5 Accelerated ageing From each batch at random IS: 3400 (Part – 4) - 1987 Ref. Table 1 of IRC:83 (Part II)-1987 At Manufacturer's Lab Site In charge MTC & Lab Results W W
DFCC Project, Contract CT P-12 ON SITE INSPECTION PLAN FOR RESOURCES PROCUREMENT
Inspection by and Type of
Sr. Inspection, measuring and Records to be Remarks
Material / Activity Frequency of Testing Reference Standard Specification limit for acceptance Responsibility Inspection
No. test equipment maintained
Consortium Engineer
1 Physical and chemical tests 1 for total lot MTC of Manufacturer Site In charge MTC W W
A-2 Inspection and testing of finished bearings.
At Manufacturer's
1 Test of welds Every Bearing IS: 822 - 1970, No crack in welds Visual and DPT Site In charge W W
Premises
3 Ultrasonic Test All metal parts IS: 9565 - 1995 Level 3 of IS: 9565 - 1995
2 Tightening of fastenings For every bearing As per Standard Practices Tight all fastenings uniformly Spanners and Torque wrench Site In charge Site Measurements W W
DFCC Project, Contract CT P-12 ON SITE INSPECTION PLAN FOR RESOURCES PROCUREMENT
Inspection by and Type of
Sr. Inspection, measuring and Records to be Remarks
Material / Activity Frequency of Testing Reference Standard Specification limit for acceptance Responsibility Inspection
No. test equipment maintained
Consortium Engineer
Centreline within ± 3 mm of theoretical,
Level of a bearing or the mean levels of
more than one bearing at any support
within a tolerance of ± 0.0001 times the
3 Bearing Position Tolerances For every bearing IRC: 83 (Part - III) - 2002 sum of the adjacent spans of a Surveying Equipment Site In charge Site Measurements W R
continuous girder (not exceeding ± 5mm.
In a horizontal plane within a tolerance of
1 in 200 in any direction
1 Length and Width of Bearing Sheet Every Bearing UIC: 772 - 2R -0mm, +5mm Vernier Site In charge MTC and Test Results W R
2 Thickness Every Bearing UIC: 772 - 2R Vernier Site In charge MTC and Test Results W R
DFCC Project, Contract CT P-12 ON SITE INSPECTION PLAN FOR RESOURCES PROCUREMENT
Inspection by and Type of
Sr. Inspection, measuring and Records to be Remarks
Material / Activity Frequency of Testing Reference Standard Specification limit for acceptance Responsibility Inspection
No. test equipment maintained
Consortium Engineer
2.1 Single Layer Nominal value ± 10% Vernier Site In charge MTC and Test Results W R
4 Water Tightness Every Duct IRC: 112 - 2011 Must be water tight Pressure Gauges Site In charge Site Measurements W R
1 Physical Test One test for every brand proposed IS 8944 - 2005 IS 8944 - 2005 From Authorised Lab Site In charge Authorised lab result W W
2 Chemical Test One test for every brand proposed IS 8944 - 2005 IS 8944 - 2005 From Authorised Lab Site In charge Authorised lab result W W