Spectrum Report: 1 Cover Page
Spectrum Report: 1 Cover Page
1 Cover Page
SPECTRUM REPORT
(GPS)
The CE mark as shown below can be used, under the responsibility of the manufacturer, after completion of an EC Declaration of
Conformity and compliance with all relevant EC Directives. The protection requirements with respect to electromagnetic compatibility
contained in Directive 2014/53/EU are considered.
Bruce Zhang
Laboratory Manager
This report details the results of the testing carried out on one sample. The results contained in this test report do not relate to other
samples of the same product and does not permit the use of theCCISproduct certification mark. The manufacturer should ensure that all
products in series production are in conformity with the product sample detailed in this report.
This report may only be reproduced and distributed in full. If the product in this report is used in any configuration other than that detailed in
the report, the manufacturer must ensure the new system complies with all relevant standards.
This document cannot be reproduced except in full, without prior written approval of the Company. Any unauthorized alteration, forgery
orfalsification of the content or appearance of this document is unlawful and offenders may be prosecuted to the fullest extent of the law.
Unless otherwise stated the results shown in this test report refer only to the sample(s) tested and such sample(s) are retained for 90 days
only.
Report No: CCISE170603406
2 Version
Test Engineer
Project Engineer
3 Contents
Page
1 COVER PAGE ....................................................................................................................................................... 1
2 VERSION ............................................................................................................................................................... 2
3 CONTENTS ........................................................................................................................................................... 3
4 TEST SUMMARY .................................................................................................................................................. 4
5 GENERAL INFORMATION .................................................................................................................................. 5
5.1 CLIENT INFORMATION ........................................................................................................................................... 5
5.2 GENERAL DESCRIPTION OF E.U.T. ...................................................................................................................... 5
5.3 TEST MODE ............................................................................................................................................................ 5
5.4 DESCRIPTION OF SUPPORT UNITS ........................................................................................................................ 5
5.5 LABORATORY FACILITY ........................................................................................................................................ 6
5.6 LABORATORY LOCATION ...................................................................................................................................... 6
5.7 TEST INSTRUMENTS LIST....................................................................................................................................... 7
6 RADIO TECHNICAL REQUIREMENTS SPECIFICATION IN ETSI EN 301 413............................................ 8
6.1 TEST ENVIRONMENT .............................................................................................................................................. 8
6.1.1 GUE adjacent frequency band selectivity performance ........................................................................... 9
6.1.2 Receiver spurious emissions ...................................................................................................................... 11
7 TEST SETUP PHOTO ........................................................................................................................................ 14
8 EUT CONSTRUCTIONAL DETAILS ................................................................................................................ 15
4 Test Summary
Radio Spectrum Matter (RSM) Part ofTransmitter
5 General Information
5.1 Client Information
Applicant: Shanghai Sunmi Technology Co.,Ltd.
Room 505, KIC Plaza, No.388 Song Hu Road, Yang Pu District,
Address of Applicant: Shanghai, China
Manufacturer: Shanghai Sunmi Technology Co.,Ltd.
Address of Manufacturer: Room 505, KIC Plaza, No.388 Song Hu Road, Yang Pu District,
Shanghai, China
Factory: Shenzhen Starworks Technology Co.,LTD.
Address of Factory: Basicom lndustry Park, Baolong Avenue 3rd Road, Longgang District,
Shenzhen City, Guangdong Province, P.R.China
Test procedure: 1. Configure the GNSS signal generator to simulate those GNSS and
GNSS signals from table 4-1 declared as supported by the GUE, with
power levels and other details as specified in clause B.2.
2. With the adjacent frequency signal switched off, the EUT shall be
given sufficient time to acquire all simulated satellites from the
declared GNSS system(s).
3. Record the baseline C/N0 value(s) reported by the EUT. Sufficient
filtering shall be used to obtain a stable value. C/N0 may be averaged
across all the satellites in view for each GNSS constellation.
However, C/N0 shall not be averaged across satellite signals in
different GNSS constellations. For a multi-GNSS EUT, there shall be
a separate C/N0 value recorded for each GNSS constellation and
each GNSS signal supported.
4. The adjacent frequency signal generator shall be configured to
generate the signal defined in table 4-4, at the first test point centre
frequency and signal power level as specified in table 4-2.
5. The adjacent frequency signal shall be switched on, and the EUT's
C/N0 value(s) recorded as in step 3) to measure the degradation with
respect to the baseline value(s) recorded in step 3).
6. 6) Test point Pass/Fail Criteria: If the C/N0 degradation from step 5)
does not exceed the value in equation 4-1, then this test point is set
to "pass". If the C/N0 degradation exceeds the value in equation 4-1,
then this test point is set to "fail." For a multi-GNSS and multi-signal
EUT, there shall be a separate pass/fail determination for each
Shenzhen Zhongjian Nanfang Testing Co., Ltd. Project No.: CCISE1706034
No.B-C, 1/F., Building 2, Laodong No.2 Industrial Park, Xixiang Road,
Bao’an District, Shenzhen, Guangdong, China
Telephone: +86 (0) 755 23118282 Fax: +86 (0) 755 23116366 Page 9 of 15
Report No: CCISE170603406
GNSS and for each GNSS signal supported. If the C/N0 degradation
exceeds the value in equation 4-1 for any supported GNSS or
supported GNSS signal, then this test point is set to "fail".
7. 7) Step 1) through step 6) shall be repeated for all test point centre
frequencies (and associated signal power level) specified in table 4-2.
Test Instruments: See the section 5.7
Test mode: Kept Rx in receive mode.
Measurement Data:
Test point Adjacent GPS Measured C/N0 (dB)
Frequency band centre frequency
(MHz) frequency signal power No interfering With interfering Decrease Δ C/N0
(MHz) level (dBm) signal signal of C/N0 ≤1
1 518 to 1 525 1524 -65 48.82 48.93 0.11 Pass
1 525 to 1 549 1548 -95 49.06 49.59 0.53 Pass
1 549 to 1 559 1554 -105 49.33 49.81 0.48 Pass
1 559 to 1 610 GUE RNSS band under test
1 610 to 1 626 1615 -105 48.28 48.89 0.61 Pass
1 626 to 1 640 1627 -85 49.05 49.72 0.67 Pass
Above 1GHz
Test procedure: Substitution method was performed to determine the actual ERP
emission levels of the EUT.
The following test procedure as below:
Measurement Data:
Spurious Emission
Frequency (MHz) Limit (dBm) Test Result
polarization Level(dBm)
39.854 Vertical -63.98
2nW/ -57dBm below
63.313 V -66.18
1GHz,
3150.84 V -62.34
39.299 Horizontal -67.35 Pass