Method Statement - ROAD CUTTING
Method Statement - ROAD CUTTING
Method Statement - ROAD CUTTING
FOR
ROAD CUTTING
PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGANG,
DAERAH KUALA LANGAT, PAKEJ A – KERJA-KERJA PENGUKUHAN
PEMBINAAN TETAP TEGUH SDN. BHD. DAN PEMULIHARAAN KOLAM PRA-RAWATAN DAN KOLAM UTAMA Rev. No:
TERMASUK MEMBINA MUKASAUK DI SG. LANGAT SERTA KERJA-
KERJA BERKAITAN DI LABOHAN DAGANG, SELANGOR.
Contract No. : Document Reference Number:
00
1.0 Introduction The main purpose of this method statement is to describe the methods and steps,
which shall be used in general to carry out the road cutting works for
1.1 Sequence of works 1. The contractor shall prepare sufficient sand, crusher run, safety measures
and other necessary equipments before commencement of works.
2. To minimise the traffic flow problem, cutting works shall be carried out by
cutting the first half
side first then
followed by the
other side.
Marking of cutting
alignment
5. After pipe laying, backfilling and compaction of crusher run shall then
follow. The contractor shall ensure the thickness of crusher run is
appropriate after fully compacted.
PROJEK PEMBANGUNAN LOJI RAWATAN AIR LABOHAN DAGANG,
DAERAH KUALA LANGAT, PAKEJ A – KERJA-KERJA PENGUKUHAN
PEMBINAAN TETAP TEGUH SDN. BHD. DAN PEMULIHARAAN KOLAM PRA-RAWATAN DAN KOLAM UTAMA Rev. No:
TERMASUK MEMBINA MUKASAUK DI SG. LANGAT SERTA KERJA-
KERJA BERKAITAN DI LABOHAN DAGANG, SELANGOR.
Contract No. : Document Reference Number:
00
Sand compaction
Reinstatement of premix