HOW TO USE THIS COMPETENCY-BASED
LEARNING MATERIAL
WELCOME to the unit of competency, “FABRICATE, INSTALL AND
REMOVE WOODEN FORMWORKS”, is one of the competencies of Core
Competency, CARPENTRY NCII, a course which comprises the knowledge,
skills and attitude required for a TVET training possesses.
Remember to:
Read information sheets and complete self-checks. Suggested
references are including supplementing the materials provided
in this module.
Perform the Task Sheets and Job Sheets until you are confident
that your output conforms to the Performance Criteria checklist
that follows the sheets.
Submit your Task Sheets and Job Sheets to your facilitator for
evaluation and recording in the Accomplishment Chart.
Outputs shall serve as your portfolio during the Institutional
Competency Evaluation. When you feel confident that you have
had sufficient practice, ask your trainer to evaluate you. The
results of your assessment will record in your Progress Chart
and Accomplishment Chart.
You may already have some or most of the knowledge and skill covered in
this module because you have;
Inside this module you will find the activities for you to complete followed
by relevant information sheet each learning outcome. Each learning
outcome may have more than learning activity.
CARPENTRY NC II
COMPETENCY-BASED LEARNING MATERIALS
List of Competencies
MODULE CONTENT
QUALIFICATION: CARPENTRY NC II
LEARNING OUTCOMES:
At the end of this module you MUST be able to:
LO1 Prepare materials, tools and equipment
LO2 Lay out and cut dimension of form sheathing and stiffeners
LO3 Assemble and erect form panels and components
LO4 Erect wooden scaffolds
LO5 Strip form panels and dismantle scaffold.
LO6 Clean and restore reusable form panels and components.
ASSESSMENT CRITERIA:
1. Use personal protective equipment (PPE) in accordance with rule
1080 of OSH standard
2. Secure and follow list of material, hand tools and equipment
according to job requirements
3. Select, inspect and prepare materials, tools and equipment
consistent with job requirements
Republic of the Philippines
DRC Technical and Vocational School
Sta.Cruz, Bontoc, Southern Leyte
4. Clean work area according to safety and environmental regulations
(e.g. PD 1152 SECTION 6,8& 42
5. Complete required output as specified by the immediate supervise
base on schedule
6. Use personal protective equipment (PPE) in accordance with
rule 1080 0f OSH standards.
7. Measure and mark form sheathing and stiffeners according to
job requirements
8. Lay and cut form sheathing and stiffeners according to job
requirements
9. Clean work area according to safety and environmental
regulations (e.g. PD 1152 Section 6,8 & 42)
10. Complete required output as specified by the immediate
supervisor based on work schedule
11. Use personal protective equipment (PPE) in accordance with rule
1080 0f OSH standards.
12. Position and fix sheathing to stiffeners
13. Check assemble form panels for squareness, levelness, plumbness
and alignment
14. Positon and fix primary and secondary support to hold assemble
form panels as per drawing
15. Check assemble form panel for compliance with job requirements
16. Clean work area according to safety and environmental
regulations (e.g. PD 1152 Section 6, 8 & 42)
17. Complete required output as specified by the immediate
supervisor based on work schedule
18. Use personal protective equipment (PPE) in accordance with rule
1080 0f OSH standards.
19. Prepare, place, space soleplates/timber planks accordingly
considering ground surface condition based on design requirement
20. Erect, plumb and level wooden scaffold components based on
design requirements
21. Check wooden scaffolds system based on design requirements
22. Install lifeline for fall protection devices (harness) in accordance
with specification and OSHS requirements
23. Clean work area according to safety and environmental
regulations (e.g. PD 1152 Section 6, 8 & 42)
24. Use personal protective equipment (PPE) in accordance with rule
1080 0f OSH standards.
25. Prepare tools, equipment and staging
Republic of the Philippines
DRC Technical and Vocational School
Sta.Cruz, Bontoc, Southern Leyte
26. Remove bracing, support and form panels as schedule accordingly
27. Remove shores and scaffolds according to schedule
28. Sort, clean and store panels and other components for the next
reuse
29. Clean work area according to safety and environmental
regulations (e.g. PD 1152 Section 6, 8 & 42)
30. Use personal protective equipment (PPE) in accordance with rule
1080 0f OSH standards.
31.Recover and stockpile materials such as scaffolding and formworks
according to company rules and procedures
32. Clean work area according to safety and environmental
regulations (e.g. PD 1152 Section 6, 8 & 42)
33. Clean tools, equipment and others materials after use
Complete required output as specified by the immediate supervisor