S1 ENG2001 PM Tutorial 3
S1 ENG2001 PM Tutorial 3
Project
Managers Suppliers
sponsor
project
Customers Government
manager
interest
project team Employees
groups
Step 1- What are the Characteristics
of the Stakeholders?
• The list of stakeholders in the project charter is expanded in the planning stage
and each stakeholder’s level of power, support, and interest in the project are
assessed.
Other examples?
Step 1- What are the Characteristics
of the Stakeholders?
• The assistance provided by the stakeholder to the project corresponds
to their level of support.
• For example: a project sponsor will show a significant level of support in
solving an issue.
• Government regulatory agencies maybe indifferent
• Activist group may be unsupportive (how?)
Other examples?
Step 1- What are the Characteristics
of the Stakeholders
• The template for the stakeholder register
Stakeholder Register
Project Name Project Name : ……………………………..
Name Project Role Level of Power Level of Interest Level of Support
Low High
Power
Low
Stakeholder Interest
1. Functional requirements
2. Performance requirements
3. Technical requirements
Scope Planning
The Work Breakdown
Structure
organizes the
deliverables into a
hierarchy.
Project Level 1
The project itself is at
the top of a WBS and is
known as Level 1.
Level 2
The project may be
divided into smaller 1. Deliverable 2. Deliverable 3. Deliverable
pieces (deliverables)
shown in Level 2.
1.1 Deliverable 2.1 Deliverable 3.1 Deliverable
(work package) (work package) (work package)
Level 3
1.2 Deliverable 2.2 Deliverable 3.2 Deliverable
(work package) (work package) (work package)
2.3 Deliverable
(work package)
Scope Planning
The deliverables in Level 2 may be further divided into smaller
deliverables in Level 3.
The deliverables that can no longer be divided are called Work
Packages.
Each level is equivalent to the level above.
• The duration of each activity should be moderate and not too long (e.g. 30 days
– a challenge to manage if work is complex) or too short (e.g. 10 minutes – too
many activities).
Milestone-Based Schedule
Project Name Project Name : ……………………………..
Milestone Date
Name of the [Date of the Milestone]
person
Milestone-based schedules are simple to use and understand. They can also be
easily accessed and will likely require minimal update during the project.
Since they do not contain activities, they will need to be managed outside of the
schedule.
Activity-Based Schedule
The activity based schedule contains the project’s activities and includes
information such as the duration, start date, and end date of each activity.
Activity-Based Schedule
Project Name Project Name : ……………………………..
Activity Duration Start Date End Date
[Name of the phase]
[Name of the Activity] [Duration of the activity] [Start date of the activity] [End date of the activity]
Click to assign
stakeholder responsible Click to indicate the
for the task percentage of the activity
completed
Creating Gantt Chart -
• Fill the right side of the chart – Move cursor to draw
bars that correspond to durations.
High
Activity
progress
Task dependency
High
Assigned
stakeholders