DXB-BW003-MOS-016 - Method Statement For Concrete Work

Download as pdf or txt
Download as pdf or txt
You are on page 1of 31

Insert here Insert here

Contractor Logo Contractor Logo

DOCUMENT SUBMITTAL
Project Name: Phase no. Project No.: Submittal Date: Submittal Reference. No. Rev.No.
Enhancement of Jebeli Ali & Al Quoz Bus Depots, CASS/BFD/1133-2 Enhancement 0
Dubai UAE 07-May-24 DXB-BW003-MOS-016
of Jebel Ali & al Quoz Bus Depots
Issued For: Discipline: Submittal Type: Approval Status:
For Approval Others Manuals Calculations Others A-Approved
Civil / Structural Interior Design B- Approved With Comments
For Coordination Architectural Maufacturer's Data QSHE
Electrical C-Revise & Resubmit
For Information Others Certificates NOCs D- Rejected
Landscaping Mechanical

s/n Document Ref.No. Document Title/Details Qty Status

1 DXB-BW003-MOS-016 Method Statement for Concrete Work 1


2
3
4
5
6
7
8
9
10
FOR CONTRACTOR's USE

Submitted by: Eng. Mahmoud Samy Signature: Date : 07-05-24

FOR CONSULTANT's USE


Engineer's Comments:
All the comments mention in every pages near by corrections should be follow
QA/QC should monitor all the entire activities and ensure all these steps/instructions complied
Final approval subject to RTA approval

Approved with
Status: A Approved B C
Revise and Resubmit D Rejected Name/Signature / Date 09/05/2024
Comments

FOR RTA USE


Engineer's Comments:

Other RTA Stakeholder Comments (if Required):

A B Approved with C D
Status: Approved Revise and Resubmit Rejected Name/Signature / Date
Comments

This approval does not relieve the contractor or supplier of his responsibilities to ensure compliance with the design, detail analysis, calculations, test methods or material developed or selected and compliance with the QA/QC and QSHE requirements or standards.

RTA_CASS_BUILDING AND FACILITIES DEPARTMENT


DOCUMENT SUBMITTAL FORM.01_REV.0
CHECK LIST
TRANSFER
SL NO NAME OF DOCUMENT REMARKS
CHECK LIST
1 Document Submittal Form ✔
2 Method Statement ✔
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRTE WORK

METHOD STATEMENT AND RISK ASSESSMENT

PROJECT NAME CASS/BFD/113-2 ENHANCEMENT OF JEBEL ALI & AL QOUZ BUS DEPOTS

CLIENT/EMPLOYER ROAD AND TRANSPORT AUTHORITY

CONSULTANT AL TURATH ENGINEERING CONSULTANT LLC

MAIN CONTRACTOR BUILT WAY CONSTRUCTION LLC


PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRTE WORK

MAIN CONTRACTOR: BUILTWAY CONSTRUCTION LLC.

NAME: DESIGNATION: PHONE.NO:

MAHMOUD AMARA PROJECT MANAGER 0527430590

JITHIN JOHN HSE ENGINEER 0524746016

CONSULTANT: ALTURATH ENGINEERING CONSULTANTS.

FAIZAL ENGINEER 0555322745

AYMAN BAROUDI SITE INSPECTOR 0502711760

CLIENT: R T A (ROADS & TRANSPORT AUTHORITY)

AHMED SHAWKY ENGINEER 0552685357


PROJECT NAME: DATE: 07-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: CONCRTE BW/02/AN/25
WORK

REVISION STATUS

REV DATE PREPARED BY PREPARED BY REVIEWED BY CHECKED BY APPROVED BY


QA/QC HSE BY PROJECT MANAGER PROJECT DIRECTOR
ENGINEER ENGINEER TECHNICAL
MANAGER
7-05-24 MOSHIN JITHIN HARIESH MAHMUD ABEER
RV01

SUPERVISION CONSULTANT

REW DATE REVIEWED & APPROVED BY SIGNATURE STAMP


PROJECT NAME: DATE: 7-5-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRETE WORK

REVISIONS STATUS

REV: NO DATE ORIGINATOR REVIEWED BY APPROVED BY DESCRIPTION OF


SUBMITTAL

METHOD STATEMENT FOR

PREPARED BY

PREPARED BY

PREPARED BY
PROJECT NAME: DATE:07-05-24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRTE WORK

• INTRODUCTION
o Purpose
o scope
• REFERENCES
o Project/Contract requirements
o International standards/Codes
o Regulatory/Authority requirements
• ROLES & RESPONSIBILITY

PROJECT ORGANIZATION FOR HEALTH AND SAFETY


• METHODOLOGY-SEQUENCE OF WORKS AND PROCEDURES
• RESOURCES TO BE USED

o Manpower/Personnel
o Material
o Tools/Equipment
• QA/QC
• HSE
• Waste management
• Emergency procedures
• APPENDICES
Risk Assessment
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRETE WORK

INTRODUCTION

Scope

The scope of this method statement covers the general requirements for concrete works. The
purpose of the documentation emanating from this statement is to ensure that quality control
objectives are maintained and accurate records are established for all related activities. The
objective is to ensure that the construction plan is executed, controlled and documented in
compliance with the contract drawings and specifications.

Objective

• The objective of this method statement is to ensure that the best industrial
practices & project specifications are strictly followed in the construction to
achieve the minimum set standards & acceptance levels of quality for the tile
work.
• It is also to ensure that all related activities are executed in accordance with the
Contract and safety requirements, related hazards and concerns on
environmental impact are analyzed and safety precautions are implemented
throughout the progress of the work.
REFERENCES

Project/Contract requirements
PROJECT NAME:

ENHANCEMENT OF JEBEL CASS/BFD/1133-2& AL QOUZ BUS DEPOTS.

Regulatory/Authority requirement

As per DM requirement.
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRETE WORK

ROLES & RESPONSIBILITY

PROJECT ORGANIZATION FOR HEALTH AND SAFETY

PROJECT MANAGER

• The Project Manager is overall responsible for the implementation of this method
statement.
• The progressing works are carried out according to the planned program and all the
equipment required to execute the works are available as per the project planning and
are in good condition.

Construction Manager
• The Construction Manager is responsible for overall execution of this work; Construction
Manager shall coordinate with Project Manager, Site Engineer, Surveyor and
Subcontractor site representative to ensure that the necessary resources and
equipment’s are provided to implement the works in an acceptable manner as per the
approved documents, MS, and also to ensure all construction staffs comply with Quality,
Health, Safety and Environmental Management System requirements.
• He shall ensure that all works are executed as per approved shop drawings. He shall
involve in toolbox talks given by the QC Engineer for the site staff prior to start works at
site. He is also responsible for indenting and using only the approved materials for
construction purpose and shall also inform the QC Engineer at site prior to the
commencement of any new activities at site.
Isolated footing support shoulod be proceed with tie rod system.

Site Engineer
• The Site Engineer shall have overall responsibility for ensuring HSE requirements and
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRETE WORK

site preparations.
• Site Engineer shall ensure and monitor the work progress in accordance with the required
schedule and report the same to the Construction Manager.
• Site Engineer shall coordinate with the HSE Officer to ensure that the works are carried
out in a safe working method and all HSE procedures being followed. Site Engineer shall
ensure that the works carried out are in line with quality requirements. Site Engineer shall
ensure that latest shop drawings are available and works are carried out as per latest
drawings.
• Site Engineer shall communicate with his subordinates and ensure that all project
communications being transferred to his work force effectively.
• Site Engineer shall be responsible for conducting and coordinating to implement the
sequence of works.

HSE Engineer / Officer

• The HSE Engineer / Officer is responsible for ensuring that the activities are carried out as
per the project-specific safety rules and regulations and strict compliance of the
approved HSE plan, the personnel shall have safety induction in possession to work at
site locations.
• All permits/passes shall be issued before thestart of any related work (if required).
Operators / Drivers shall have relevant experience and valid UAE license, lifting
equipment operators shall possess 3rd Party Competency Training and be certified.
Equipment Inspection / Certification and color coding qualified operators to be used at
the site.
• All Personnel shall have attended safety induction and awareness training conducted in-
house. Risk assessment shall be done to ensure that all the Hazards involved are
identified, risk assessed, and control measures are put in place.

QAQC Engineer
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-
2ENHANCEMENT OF
JEBEL ALI & AL QOUZ BUS
DEPOTS

DOCUMENT NO:
METHOD STATEMENT AND BW/02/AN/25
RISK ASSESSMENT:
CONCRETE WORK

• Significant work shall be ensured by the Project Engineer/Site Engineer and the QC
Engineer to conform to the drawing and specification.
• QA/QC Engineer shall be responsible for the implementation and control of the quality
procedures as per the approved ITP, approved project specification and drawings. He
shall ensure that all required inspections and tests are performed and are in compliance
with approved specifications.
• He shall review and ensure that all shop drawings and material submittals are presented
to the Consultant with adequate supporting documents. He shall control non‐conforming
products, and workmanship and implement the required timely corrective actions.
• Ensure that the required testing is undertaken by approved independent laboratories,
and all test results are reviewed. Ensuring that materials are inspected when delivered to
site and it is complying with the approved specifications and maintaining all relevant
records of QA/QC activities related to concrete works.

Surveyor
The Surveyor is responsible for Control bench mark shifting, setting out, levelling and marking for
which are going to provide with block works / setting layout. He is responsible for taking of as‐
built level of architectural works.

Site Supervisor or foreman

• To follow the procedure and risk analysis and ensure that all recommended PPE are
available
• and used by worker, Staff and Visitors, He shall ensure that all risk control measures are
well disseminated to theworkers through daily toolbox talks.
Mason worker
• Builds walls, fences, walkways, roads, and other structures using bricks, stone, concrete
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRETE WORK

blocks, or marble.
• Carves out and builds structures and surfaces with bricks or concrete blocks. Places
brick or concrete blocks on mortar bed. Cuts or saws bricks to fit around windows and
doors.

Material Handling and storage:

• After delivery, the tiles shall be stored on pallet placed on the ground or over the concrete
surface.
• Store adhesive and grout material on elevated platforms, under cover, and in a dry
location.Do not use cementitious materials that have become damp.
• Store tile accessories, including corner beads, to prevent from damage and accumulation
ofdirt and oil.

METHODOLOGY-SEQUENCE OF WORKS AND PROCEDURES


Shuttering:
Approved plywood should be use at site
▪ Marine Plywood (18 mm thick) shall be used for all face shuttering works.
mention in latest approved drawings
▪ Plywood shall be cut to the required size as indicated in the drawings.
3 times
▪ Each side of the marine plywood shutter shall be used for a minimum of ----------
4 times.
▪ White wood 1”x 4” and 3” x 3” shall be used appropriately to strengthen the plywood
from outside.
▪ Propping of shuttering:

Footings:

dia
▪ The sides of isolated footings shall be propped with 12mm -------
thick steel bar props at every

Type text here


PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRETE WORK

45cm from all sides for footing depth of up to 40cm.


▪ White wood 3” x 3” shall be used along the periphery of the shuttering at top and bottom
-------------------
as stiffeners.
tie rod
▪ Additional steel propping at centre along with 3” x 3” white wood stiffeners shall be
provided for any isolated footing with depth greater than 40cm and less than 80cm.
footing coordinates ,alignment and size should be ensure prior to consultant inspection.Clear cover should be follow.Diagonal support required
▪ Tie Beams:
tie rod system support
▪ Steel bar propping shall be done at bottom and top level of tie beam sides using 3” x 3”
--------------------------------

white wood (horizontally as stiffeners) on each side.


▪ For sizes up to 45cm in depth tie rods shall be provided at every 45 cm c/c along the
length of the beam.
▪ For sizes greater than 80cm in depth an additional row of tie rods and props shall be
provided.for every 20 cms in c/c
Clear cover should be maintain. beam coordinates should be ensure by surveyor. sizea as per latest approval drawing.
column coordinates should be ensure by surveyor | column mould should be erect at the coorintaes and ensure | All support
should be done for every 30 cms from the bottom upto 1 m and remaining should be follow 45 cms inj sequence interval|
Columns: colomn top coordinates shoud be ensure after the shutter get done|
▪ Columns shall be cast up to a maximum height of 3m at a time.
▪ Steel props supports shall be provided at bottom, middle and top levels of column
shuttering.
▪ Bottom support shall be 40cm from floor level and top support shall be 10cm from
column top level.
▪ For column widths of up to 40cm 2 steel supports at each level shall be provided.
▪ For column widths of greater than 40cm tie rods shall be provided in addition to
the props as per the requirement
Slab Beams:
▪ Steel propping shall be fixed at soffits of beams and 3” x 3” white wood (installed
horizontally and perpendicularly to the beams) at every 45 c/c on each side.
▪ All steel propping at bottom of beams shall be sufficiently braced for any horizontal
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRETE WORK

movement during concreting.


▪ For beam depths greater than 30cm and less than 45cm, tie rods shall be provided at
every 45 cm c/c along the length of the beam
▪ For sizes greater than 45cm in depth, an additional row of tie rods shall be provided.

-------------
Slabs:

• -----------------------------------------------------------------------------------------------------------------------------------------------------------------
Shop drawings for slab scaffolding shuttering system shall be provided and approved
by the consultant and a certificate of approval shall be obtained from the scaffolding
----------------------------------------------------------------------------------------------------------------------------------------------------------

-------------------------------------------------------------------
agency prior to casting of concrete.

Reinforcement Bars:

• Reinforcing steel shall be as shown on the approved workshop drawings. All reinforcing
steel shall be free from loose mill scale, rust, oil, grease and other harmful substances
and shall be within the limits of the relevant BS or ASTM standards. mention standards
• Amana shall obtain and submit the relevant test certificates for the Mill producing the
reinforcing steel for the approval of the Engineer before placing orders. ???????

• Tests shall be carried out on samples of reinforcing steel from stock reserved for the
project and from bars delivered to the site as request by the Consultant.
• Reinforcement bars shall be stored at least 6 inches above ground level on wooden
battens. Type text here

• Reinforcement bars shall be covered with appropriate plastic tarpaulin sheets while in
storage to avoid any rusting.
• Rusted reinforcement bars shall be treated with rust remover with approval of Consultant
prior to fixing at site.
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRETE WORK

• Amana shall submit workshop drawings and bar bending schedules of the steel bars
reinforcement for the approval of the Consultant.
latest approve shop drawing
• Reinforcement bars shall be cut and bent as per municipality-approved drawings taking
into consideration the cover to the reinforcement as specified by the consultant and
shown in the municipality approved drawings.
• Reinforcing steel, ties, links, stirrups and couplers etc shall be positioned as shown in
latest approved shop drawing
the approved workshop drawings. Amana shall ensure that bars in columns and beams
are cranked for the entire length of the lap so that the minimum cover requirements are
achieved and the true alignment of the reinforcing steel is maintained.
minimium 20 gauge
• Binding wire shall be of specified gauge of galvanized steel and shall be tied at every
alternative joint for slabs and all joints for beams.
• The concrete cover to the reinforcing steel shall be as specified. Purpose made and
approved plastic, steel and concrete chairs of suitable sizes to hold the reinforcing steel
in position shall be used.
• All reinforcing steel shall be securely held in position. If required, additional bars, stirrups
and chairs to provide support for the reinforcing steel. as per required height .
mention steel mesh with code
• Mesh reinforcing steel shall be of an approved type complying with the requirements of
BS 4483 and the weights and dimension shown on the Construction drawings and will
be supplied in flat sheets.
• Where necessary, mesh reinforcing steel shall be bent accurately to the required shapes
before it is laid in position and all bending and cutting shall be done cold.
depends the dia of the steel
• All mesh reinforcing steel shall be lapped for a minimum length of 200 mm unless
otherwise stated on the drawings and tied together with the approved soft steel tying
wire on both the longitudinal and transverse wires and all lapping shall be sufficient for
the steel to develop its full strength.
• After the steel fixing has been completed, it will be subject to inspection by the Site
Engineer.
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
CONCRETE WORK

• The inspection insofar as reinforcing steel is concerned will include but will not be
limited to: evidence of compliance with the latest issue of the approved workshop
drawings and bar bending schedules, reinforcing steel type, size, spacing, cover, tying,
couplers, splices, laps, cleanliness and dowel/starter bars, etc.
Clear cover should be follow.
Concrete:
latest approve dshop drawing
• Approved grade of concrete shall be used as per approved drawings and to the approval
of Consultant. and trail mix required
• Slump shall be checked for each batch of concrete arriving at the site (slump = 100 ±
25). as per approved mix design mentioned
• Concrete shall be placed within a maximum of 2 hrs after dispatch from the batching
plant. Any concrete arriving at site beyond 2 hrs shall be rejected.
• Concrete shall be mechanically vibrator compacted using needles of appropriate size.
• Compressive test cubes shall be taken from each and every pour of concrete.
A minimum of 3 cubes for small pours and a maximum of 6 cubes for large pours
and as per consultant approval.
• Curing shall be done for 7 days using Hessian cloth wetted with water.
Temperature more them 30 degree will be rejected.

Checking Schedule:

• Footings, Stub Columns & Tie Beams:


• After complete shuttering and reinforcement bars work.
Columns :
• After the layout of columns.
• After fixing of reinforcement bars, cover block separators and 3 sides of the shuttering.
• Final checking of plumb and line after shuttering is completed.
PROJECT NAME: DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/25
BLOCK WORK

Slab :

• After shuttering and reinforcement bars works are completed.

RESOURCES T BE USED

• Manpower/Personnel
• Manpower employed will be as per the program requirement and the site progress
situation.
Material:
• Formwork
• Steel Reinforcement Bars
• Spacers and supports for concrete
• Binding wire
• Polythene sheets
• Ready-mix Concrete
• Form releasing agent
• Absorptive mat fabric (Hessian cloth) for curing

Tools/Equipment
General:
Appropriate plants and equipment shall be used for the execution of the activity. The tools and
equipment shall be checked visually prior to use.
No defective plant and equipment shall be allowed to be used on-site
• Only authorized applicators approved and trained by the manufacturer to install the
manufacturer's products.
• All Operators shall be trained and certified by the 3rd party where required.
• No defective plant and equipment shall be allowed to be used on-site.
• All power tools shall undergo a monthly inspection and will be tagged - different
PROJECT NAME:
DATE: 7/05/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT:
BW/02/AN/25
CONCRETE WORK
• color every month ‐ to indicate suitability for use

• Sling and (or) Shackles


• Pellets
• Trolley
• Wheelbarrow
• Cutting, drilling Machine
• Grinder
• mixer mortar
• Aluminumam scaffolding( 1.5 m
• Concrete transit mixers
• Vibrators
• Masonry tools
• Carpenter tools
• Light projectors
• Water tank and pumps
• Stand-by generator

Personal Protective Equipment:


▪ All operatives involved in the activity shall be provided with Job specific Personal
Protectiveequipment which is and but not limited as mentioned below:
▪ Polycarbonate Safety Helmet
▪ Safety boots with steel toe
▪ Coverall with high visibility strips
• Safety Induction
• Start Program
• Toolbox Talk Meeting
PROJECT NAME: DATE: 5/04/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/24
BLOCK WORK

• Job Training
• Supervisors/Foreman
• Notices/Memos

Emergency Procedure
The site emergency arrangements are detailed in the Project HSE Plan
The construction manager/safety manager shall be familiarized with the Emergency Response
Plan & Contact Numbers. Emergency contact numbers to be posted on site.

General

• The project HSE department shall be responsible to arrange and coordinate with
construction team to arranging the emergency procedure
• First aid room should be established to carry on first aid on site in case of any minor
injuries in case of any emergency the safety officer should be informed about the
emergency.
• Emergency assembly point shall be allocated and communicated to all the operatives
involved in the works.
• Ensure clear access to the emergency assembly area with signages in place. No
construction activity shall modern combo roofing system the access leading to the
• emergency assembly point. In case of any deviation the access has to divert the same
shall be communicated to all the operatives on site.
PROJECT NAME: DATE: 5/04/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/24
BLOCK WORK

Fire Precaution

• Fire extinguishers shall be put in place at each working zone and clear access shall be
provided to the location.
• All the operatives should be trained for fire precautions on site.
• A fire warden should be appointed and trained from each team operatives.

Name Designation Contact #

Mahmud Project Manager 0566968622

Jithin HSE Officer 0524746016

Imran First Aider 0555633746

CONSULTANT: ALTURATH ENGINEERING CONSULTANTS.

FAIZAL ENGINEER 0555322745

AYMAN BAROUDI SITE INSPECTOR 0502711760

CLIENT: R T A (ROADS & TRANSPORT AUTHORITY)


PROJECT NAME: DATE: 5/04/24
CASS/BFD/1133-2
ENHANCEMENT OF JEBEL
ALI & AL QOUZ BUS
DEPOTS

METHOD STATEMENT AND DOCUMENT NO:


RISK ASSESSMENT: BW/02/AN/24
BLOCK WORK

Waste Management

Environmental Goals: To implement all reasonable measures to prevent leakage,


spillage or inappropriate disposal of hazardous waste.
• To ensure that a sound approach to waste management is adopted which would include;
waste minimization, re-use, recover, recycling, treatment and proper disposal. Builtway
sites / departments will coordinate with central store in accordance to the disposing of
wastes e.g. batteries, tyres, steel, scrap vehicles and sold vehicles. Central store to
ensure appropriate measures in disposing the wastes documented & maintained.
• To maintain a clean and tidy site.
Environmental Specifications for Waste Management:
• The HSE officer will ensure the implementation of the following waste management
procedures:
• No waste will be burned on construction sites.

APPENDICES

• Risk Assessment
ACTIVITY TITLE: Risk Assessment Concrete Works

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓ Closed ✓ Control
monitoring by measure/risk
assigned assessment shall
foreman. be communicated
✓ Test certificate to the operatives
of machinery prior to the job
✓ Incompetent shall be commencement
operatives produced as ✓ Provide
and work when required. awareness
equipment ✓ All operatives training and
Mechanical
✓ Lack of are competent, toolbox talk
Transporting of Failure
awareness for trained in the regarding the safe
concrete the site activity. movement
cement& Poor perception
✓ All operatives around the truck

High
emergency

Low
1. 3C 2C - 3C 1C 1C - 1C
Materials by of work
preparedness. shall safety mount vehicle
machines to ✓ Personnel Injury /
work location. ✓ Collision with Property damage induction and during the
Inexperienced/ ✓ Crush Injuries,
the fixed trained as per offloading activity
Untrained
objects, project ✓ Site speed limits
✓ Collision with requirement shall be abided by
the moving ✓ Operator and the plant
objects Machine shall be operator
3rd party certified ✓ Flag man shall be
and operator assigned with the
should possess machine to guide
valid UAE driving the plant
license to operator.
operate the ✓ Overcrowding in
vehicle the area in the
ACTIVITY TITLE: Risk Assessment Concrete Works

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

vicinity to be
avoided.

✓ Supervision for the


work.
✓ Permit to work
system in place
✓ Manual handling
training
✓ Provision of easy
access to facilities
Mechanical ✓ Job Specific PPEs.
Back injuries
Failure ✓ Tool box talks the
workers prior the
Muscular
Poor perception task.
problems,
Manual ✓ Should ensure
of work Close monitoring of
2. Handling of ✓ Physical injuries 3C 2C - 3C equipment utilizing 1C 1C - 1C
Cuts, activity by a

L
Materials ✓ Property damage in the
Slips and Trips competent supervisor
Inexperienced/ lifting/handling or a
Ergonomics Untrained person is fit for the
Sprains and
Not wearing purpose.
strains
suitable PPE ✓ MSRA should be
Dehydration
communicated to
all workforce
engaged in the
activity and ensure
that all are well
aware of the
hazards and its
control measures.
ACTIVITY TITLE: Risk Assessment Concrete Works

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓ Job rotation and ✓ Appropriate PPEs


competent like Hand Gloves,
supervision to be Eye protection
provided. shall be provided
✓ Permit to work to the employees
system. for personnel
✓ Incompetent ✓ Selection of correct protection.
operatives power tools or hand ✓ Right tools for the
and work tools for the job. right job shall be
equipment ✓ Work involving the used.
✓ Lack of use of power tools ✓ All tools and
shall be equipment shall
awareness for
appropriately be color coded by
the site planned, organized competent
✓ Falling objects, ✓ Cuts and abrasions,
emergency and appropriately person.
3. Concrete work ✓ Use of ✓ Physical injury 3C 3C - 3C 1C 1C - 1C
preparedness supervised. ✓ The area to be
Defective hand
✓ Falling ✓ Ensure that persons kept clean and tidy
tools involved in the use to prevent any
objects,
of power tools are Slips, Trips and
✓ Defective
trained and falls.
hand tools,

High

Low
competent. ✓ Ensure that the
✓ Flying objects ✓ Eye wash station or effective
✓ Slips, Trips & first-aid facilities procedures and
Falls should be provided control measures
in the site. are in place which
✓ Do not use any are implemented
altered hand tools in order to
for the job. manage the safe
✓ Area to be use of power
restricted only for tools.
ACTIVITY TITLE: Risk Assessment Concrete Works

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

authorized person’s
entry.
✓ Scaffolding ✓ There should be a
inspection system. means of access
✓ Competent scaffold (for example
inspector for temporary stairs
inspection. or a ladder) to the
✓ Scaffolding tagging level the
system. scaffolding has
✓ Falls from ✓ Tool Box talk. With reached
height the work force. ✓ Scaffold to be
✓ Falling of ✓ Working at height design, erected,
training. alter and
objects
✓ Supervision for the dismantle, by
✓ Collapse of ✓ Lack of
Personal Injury or work. competent
Scaffold awareness ✓ Tools, equipment’s person.

Low
Scaffold for Property
4. ✓ High wind ✓ Failure to 3C 3C - 3C and lanyard ✓ Scaffold shall be 1C 1C - 1C
work at height
condition follow work at inspection and color on firm and stable
Damage.
✓ Lack of height coding by ground and braced
scaffold procedure competent person. and stabilized.
✓ Ensure that ✓ Scaffold platform
inspection
employees erect shall be fully
✓ Incomplete and inspect boarded and no
platform scaffolding are gaps to be lifted.
✓ qualified and ✓ Safe means of
competent access to be
✓ All employees shall provided to
be trained for work scaffold.
at height work. ✓ Appropriate
✓ No one shall be protective
allowed to work in measures shall be
high wind condition installed
ACTIVITY TITLE: Risk Assessment Concrete Works

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

or adverse weather guardrails, Mid


condition. rails and toe
✓ 100 % tie off policy boards to prevent
to be adopted by all employees and
the workers while tools from falling
working at height ✓ Ensure that the
by using double scaffolding
lanyard with shock foundation shall
absorber attached be able to carry
to appropriate and distribute all
anchorage point the weight of the
above the waist scaffold, including
level all the times. any extra loads
✓ placed on the
scaffold which
may also include
perimeter
containment
screens

✓ Personnel ✓ Hot work permit for ✓ Pre use inspection


Use of Power injuries the task. of the tool and
✓ Lack of Personal Injury or
tools ✓ Cut injuries ✓ Power tools training electric cables
awareness Property
(concrete ✓ Flying for the employees shall be carried
5. mixer, cutter, objects ✓ Failure to 3C 3C - 3C involved. out by the 1C 1C - 1C
Damage.
driller,vibration ✓ Electric follow work at ✓ PPEs for the operative.
machine shock height workers. ✓ Double insulated
✓ Slips and procedure ✓ Supervision. tools shall be used
trips ✓ Fire extinguisher at to prevent electric

Low
✓ Fire work place. shock.
ACTIVITY TITLE: Risk Assessment Concrete Works

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓ Provision of ELCB ✓ Power supply to


for the Use of be taken through
Power Tools ELCB only.
✓ Face Shield for ✓ Cable
workers using management shall
portable grinders be carried out to
and drills. prevent slips, trips
✓ Tool Box talks for and falls.
the workers ✓ Power supply to
involved. be cut off while
✓ If it’s necessary to repairs or
use 240v tools, then changing drill bits.
it should be ✓ Adequate PPEs
protected with a like face shields
30mA RCD/ELCB. and eye protection
shall be worn by
the workers for
the task
✓ Permit to work
system shall be
followed and
strictly enforced.
✓ Use of 110v tools
to be encouraged.

✓ Daily clean-up is to
✓ Lack of be performed
✓ Housekeeping Injuries
awareness ✓ Walkways will be ✓ Personnel will
6. Waste & waste Cut 3C 2C 3C 3C 1C 1C - 1C
✓ Slips and Trips kept clear at all wear suitable PPE
Management disposal Broken bone
✓ Sharp-edge times at all times
✓ Dust ✓ Proper disposal of
cuttings
High

Low
wastes as per
ACTIVITY TITLE: Risk Assessment Concrete Works

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓ Accumulation Land Contamination/ contractor Waste


of waste Environment impact Management Plan.
✓ Waste management
training
✓Especially under or
behind any plant or
parked vehicle.
✓Rest Area
✓Cool Drinking water
✓Lack of ✓Mid-Day Break Rule
supervision. implemented
✓Heat stroke. Ensure all
✓Confusion. operatives are
✓Heat Stress acclimatized of the
✓Nausea working
✓Stroke environment.
✓TBTs working in

High
✓Dehydration. ✓Exhaustion ✓Heat Stroke ✓Drinking water
Working in hot high temperature
7 ✓Burns. ✓ Collapse 3C 2C - 3C availability and 1C 1C - 1C L
weather ✓Fatality ✓ Medical assistance
✓Falling ✓Rapid weak operatives to drink
Heat related illness ORS to be utilized
✓Fall of person pulse water as frequently

✓ ✓Head ache. as possible.
✓Weakness ✓Take regular breaks
✓Mussels in hot weather.
Cramps ✓When feel unwell,
✓Vomiting inform to
supervisor.
✓ Unconscious ✓Appropriate
training shall be
given to all
employees working
in high
temperature.
ACTIVITY TITLE: Risk Assessment Concrete Works

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓ Medical assistance
ORS to be utilized
✓ Weather condition
must be monitored
daily, work ban
timings
implemented
strictly during
✓Poor visibility
summertime from
✓Working in ✓Slippery floor ✓Provide heat
June 15-September
adverse ✓Heat stress ✓Fatality stress training and
15 of the year
weather illness ✓Heat related illness emergency
12:30-3:00PM for
condition e.g., ✓Dust struck by Injury
response training
Adverse all external works,
8 sand storm, lightning 3C - 4C 3C to workers, TWL 1C 1C - 1C

Low
High
weather ✓Work Delay, ✓ heat stress
high wind, ✓fall from level monitored
✓Property damage prevention program
extreme heights & every 2 hours and
implemented, stop
temperature, falling object communicated to
all lifting operation
rain, due to high workers
during
thunderstorm wind
thunderstorm, all

work at heights
activity not limited
to roof work and
scaffolding works
are not allowed
during heavy rain.
✓Delay in notification / ✓First aid shall be In case of any
✓Movement of
response provided if emergency workers
heavy
Emergency Unsafe Act and ✓Lack of common necessary shall report
9 equipment 4C 2C - 4D 1C 1C - 1C
High

Low
Response Condition resources ✓All work will be immediately to HSE
✓Collision of
✓Lack of or inadequate stopped and staff / department,
mobile
emergency workers assembled
equipment
equipment
ACTIVITY TITLE: Risk Assessment Concrete Works

* Risk Assessment Additional Risk Residual Risk


No. Hazard Title Hazard Detail Causes Consequences Existing Controls Controls Planned/
P A E R RI Required P A E R RI

✓Language barrier in nearest assembly Manager,


✓Fatality point emergency contact
✓Personal Injury no 999,998

Implement the additional risk controls identified

Risk control-1 TBT should be conducted prior to the star of the activity Date Implemented by PM/HSE

Risk control-2 Competent and trained operators to be deployed at site. Date Implemented by PM/HSE

All Scaffolding structures shall be erected by 3rd party certified scaffolding


Risk control-3 Date Implemented by PM/HSE
erectors and shall be inspected by 3rd party certified scaffolding inspector
implemented strictly during summertime from June 15-September 15 of the year
Risk control-4 Date Implemented by PM/HSE
12:30-3:00PM for all external works.

Risk control-5 Ensure to Illumination level as per requirements Date Implemented by PM/HSE

It is important to monitor risk controls and review risk assessments regularly. Review is required when there is a change in the process, relevant legal changes, and where a cause for concern has arisen.
Reviews could be scheduled on an annual basis. If the risk assessment has substantially changed a new risk assessment is warranted.

Review date 02.04.2024 Reviewed by Mohmud Authorized by Abeer

Notes: Include legal and advisory documentation that supports this risk assessment be listed. Such documentation includes Acts, Regulations, Standards, where applicable. If the risk assessment for an identified hazard is ranked ’Low’
but the regulatory requirements have not been complied to while establishing and/or implementing controls, the ranking for the assesses risk shall be considered ‘Very High’
Risk Assessment Steps:
Step 1: Identify Hazards Title (e.g. Physical Hazard, Fire Hazard, and Electrical Hazards).
Step 2: List Hazards Details identified (e.g. Tripping Hazard, Flammable Materials stored, Working in Electrical Cabinets).
Step 3: List Causes of Hazard (e.g. Untidy workplace, Hot work, un-isolated electrical supply).
Step 4: List Consequences of Hazard (e.g. Personnel Injury, Fire, electric shock).
Step 5: Determine Likelihood and Consequences to People, Assets, Environment, and Reputation from attached Risk
Assessment Matrix (Page 2) (this should be the most probable outcome without controls and should be listed as 2A, 3D
etc.).
Step 6. Calculate the Risk Index using the Qualitative or Semi-Quantitative Risk Assessment Matrix as deemed appropriate.
This is a product of Likelihood and Consequence and should be stated Low, Medium, High or Very High). Likelihood Descriptor to assist in Qualitative Assessment of Likelihood/ Frequency of Occurrence.
Step 7. List Existing Controls. (e.g. Tidy Site Policy, Hot Work Permit, Isolation of Electrical Supply).
Step 8. List Safety Critical Activities and Additional Controls that may be deemed necessary to reduce risk level to ALARP. A
Step 9: Recalculate Likelihood and Consequences to People, Assets, Environment, and Reputation from attached Risk Has occurred within port industry worldwide.
Assessment Matrix. B
Step 10. Recalculate the Risk Index. Has occurred regionally within port industry or judged likely to have occurred.
Step 11. If residual risk deemed to be High or Very High then risk must be reduced further before proceeding, if risk is C
medium then note that risk reduction must be planned, monitored and documented, if risk is low then risk is acceptable Has occurred in port industry within UAE or judged likely to have occurred.
without required further action. D Has occurred in port industry within UAE on an annual basis or judged likely to have occurred.
E May occur in UAE port industry multiple times annually.

* Risk Assessment Matrix – Qualitative LIKELIHOOD

Consequences P= People A= Assets E= Environment R= Reputation A B C D E


VERY
5- Catastrophic Multiple fatalities Extensive damage Massive effect International impact
HIGH
Single fatality or
4 - Severe Major damage Major effect National impact HIGH
permanent disability
Major injury or health
3 – Critical Localized effect Localized effect Considerable impact MEDIUM
effects
Minor injury or health
2 – Marginal Minor effect Minor effect Minor impact
effects
Slight injury or health
1 - Negligible Slight effect Slight effect Slight impact LOW
effects