PROJECT

STATUS
REPORT
MARCH 2024

Great Roads,
Great User Experience
UPGRADING PROJECTS
COMPLETED ROAD UPGRADING PROJECTS
FY Road Project Length (KM) Source of Funding Region
Kampala Northern Bypass Phase I 20 EU/EIB Buganda
2010/11 Dokolo-Lira 60 World Bank Lango
Soroti – Dokolo 64 World Bank Teso-Lango

Matugga – Semuto – Kapeeka 41.4 DANIDA Buganda


Kampala-Gayaza-Zirobwe Road 44.3 World Bank Buganda
2011/12 Mbuya/SilverSprings-Kireka 5 GOU Kampala
Kabale-Kisoro-Bunagana/Kyanika 101 AfDB Kigezi

Nyakahita-Kazo 68 AfDB Ankole


2012/13
Kazo-Ibanda-Kamwenge 75 AfDB Ankole

Fort Portal-Bundibigyo - Lamia 103 AfDB Rwenzori


Kabale-Town Roads 13 GOU Kigezi
Nyakabande-Mutolore 5 GOU Kigezi
2013/14
Nyakabande-Muganzi 7 GOU Kigezi
Mbarara-Kikagati - Murungo Bridge 74 GoU Ankole

Hoima-Kaiso-Tonya 92 GOU Bunyoro


Gulu-Atiak 74 World Bank Acholi
2014/15
Vurra-Arua-Oraba-Koboko and Town
92 World Bank West Nile
Roads

Atiak-Nimule 35 JICA West Nile


2015/16 Ishaka – Kagamba Road 35.4 GoU Ankole
Moroto-Nakapiririt 93 GoU Karamoja
Ntungamo – Mirama Hills 37 TMEA Ankole
2016/17
Fortportal- Kamwenge 65 WB/GoU Tooro

Mbarara-bypass 28 EU Ankole
Kampala-Ebb Express way 57 China EXIM Bank Kampala
Munyoyo Spur 28 China EXIM Bank Kampala
2017/18 Rushere-Nshwerenkye 11 GoU Ankole
Gulu-Acholibur 78 GoU Acholi
Acholibur-Musingo 86 GoU Acholi
Mpigi-Kanoni 65 GoU Buganda

Mukono – Kyetume - Katosi/Nyenga-


74 GoU Buganda
Njeru
Musita - Lumino - Busia/Majanji Road 104 GoU Busoga/Bugisu
2018/19 Akisim-Moroto 50.3 GoU karamoja
Olwiyo - Gulu 70.3 GoU Acholi
Kashenyi-Mitooma 11.5 GoU Ankole
Kanoni-Ssembabule-Villa Maria 110 GoU Buganda

Soroti- Katakwi - Akisim 100 GoU Teso


Mbale - Bubulo - Lwakhakha Road 45 AfDB Bugisu
Mubende-Kakumiro-Kagadi Rd 107 GoU Buganda/Bunyoro
2019/20
Bulima-Kabwoya 66 AfDB Bunyoro
Kyenjojo-Kabwoya 100 WB Bunyoro
Nyenga-Njeru 10 GOU Buganda

Kigumba-Bulima 69 ADF, DFID and GOU Bunyoro


Tirinyi – Pallisa - Kumi 67 ADB & GOU Busoga-Bukede
2020/21 Pallisa - Kamonkoli 44 ADB & GOU Busoga-Bugisu
Masaka - Bukakata 41 BADEA, OFID & GOU Buganda

Kampala Northern Bypass 17.5 EU/EIB/ GOU Buganda


GOU/EXIM Bank of
2021/22 Package 2: Hoima Butiaba - Wanseko 111 Bunyoro
China
Upgrading Of Selected Town Roads in 20.2 GOU Ankole
Mbarara Municipality
Mpigi Town Roads 20 GOU Buganda
Entebbe Paediatric Hospital Access
4.2 GOU Buganda
Road
Masaka town roads 7.3 GOU Buganda
Package 3: Buhimba – Nalweyo –
2022/23 Bulamagi & Bulamagi – Igayaza – 93 Exim Bank/GOU Bunyoro
Kakumiro
2022/23 Gulu Logistic Hub Access Road 2.2 GOU Acholi
Selected Access Roads in Rushere
2023/24 Town(3.0KM) and Kyamate Access 5.6 GOU Ankole
Roads(2.6KM)

ON-GOING UPGRADING PROJECTS AS OF MARCH 2024


Length Source of Progress
No. Road Project Surface Contractor / Consultant Contract Amount
(KM) Funding (%)
Contractor: Works Contract:
China Henan International UGX; 207,834,646,967
Rukungiri – Kihihi Double
Construction Company
1. – Ishasha/ 78.5 Surface ADB/GOU Substantially Complete
Supervision Contract:
Kanungu Treatment
Supervision Consultant: USD 4,712,121.76 + UGX
SMEC International Pty 12,478,542
Contractor:
DOTT Services Ltd Works Contract:
UGX 93,846,360,134
Luwero – Asphalt BADA/OFID Supervision Consultant:
2. 29.6 2.83
Butalangu Road Concrete and GOU BEZA Consulting Engineers
PLC in association with Supervision Contract:
SEREFACO Consults Ltd USD 1,272,000

Revised Contract Sum:


Package 1: Contractor:
USD 217,916.518.4
Masindi Park CCCC
Asphalt (Design and Build
3. Junction and 159 Exim Bank/GoU 99.82
Concrete Contract)
Tangi Junction- Supervision Consultant:
Supervision Contract:
Para-Bulisa PROME
N/A
ON-GOING UPGRADING PROJECTS AS OF MARCH 2024
Length Source of Progress
No. Road Project Surface Contractor / Consultant Contract Amount
(KM) Funding (%)
Contractor:
Package 5: China Railway Seventh
Masindi-Biiso, Group Co. Ltd (CRSG)
Works Contract:
Hohwa –
UGX 504,861,701,727
Nyairongo – Asphalt Supervision Consultant:
4. 97 Exim Bank/GoU 84.36
Kyarusheesha – Concrete Net Consult Consulting
Supervision Contract:
Butoole, And Engineers in JV With Stadia
UGX 12,641,454,625
Kabaale – Engineering Works
Kiziranfumbi Consultant Plc and KKATT
Consult Ltd.
Contractor: Works Contract:
In-house construction team UGX 2,000,000,000
Asphalt
5. Kitala – Gerenge 10 GOU Substantially Complete
Concrete
Supervision Consultant: Supervision Contract:
In-house supervision team UGX 450,000,000
Contractor:
China State Construction
Works Contract:
Engineering Corporation
UGX
Limited
268,461,095,349
Kapchorwa – Asphalt ADB/ ADF/ Supervision Consultant:
6. 73 Supervision Contract: 98.8
Suam Concrete GOU LEA International Ltd., in
USD 1,620,650 and UGX
Joint Venture with
4,526,631,000 excluding
LEA Associates South Asia
taxes of USD 305,310 and
Pvt. Ltd., and in
UGX 440,385,300
Association with KOM
Consult Ltd.
Contractor:
STRABAG International Works Contract:
GmbH UGX 226,342,581,192
Asphalt
7. Atiak – Laropi 66 EU/ GOU 89
Concrete
Supervision Consultant: Supervision Contract:
Eptisa Servicios de UGX 15,794,667,252
Ingenieria, S.L
ON-GOING UPGRADING PROJECTS AS OF MARCH 2024
Length Source of Progress
No. Road Project Surface Contractor / Consultant Contract Amount
(KM) Funding (%)
Contractor:
China Civil Engineering
Construction Corporation in
Joint Venture with China Works Contract:
Railway 19th Bureau Group UGX 547,543,072,124.18
(U) Ltd
Busega – Mpigi Asphalt
8. 23.7 AFDB Supervision Contract: 36.22
Expressway Concrete
Supervision Consultant: US$3,180,900 +
Dohwa Engineering Co. UGX3,899,460,000
Ltd., in Joint Venture with (excluding taxes)
IDCG Engineering Group
and in association with
Tamp Blessed 3 Ms JV Ltd
Contractor:
M/S Polat Yol Yapi San. Ve
Works Contract:
Tic. A.S of Turkey
UGX 399,958,528,511
Muyembe – Asphalt
9. 92 IsDB/ GOU 54.15
Nakapiripirit Concrete Supervision Consultant:
Supervision Contract:
SCET Tunnisie in Joint
UGX 12,864,250,009
Venture with MBW
Consulting LTD

Contractor:
Works Contract:
China State Construction
Najjanakumbi – UGX 258,823,694,110
Engineering Corporation Ltd
10. Busabala and 28 Asphalt GOU 36.8
Service Roads Supervision Contract:
Supervision Consultant:
TBD
Under Procurement
ON-GOING UPGRADING PROJECTS AS OF MARCH 2024
Length Source of Progress
No. Road Project Surface Contractor / Consultant Contract Amount
(KM) Funding (%)
Contractor:
Chongqing International Works Contract
Kira-Matugga
Construction Corporation UGX 200,398,059,014
Road and
11. 21 Asphalt GOU (CICO) 43.85
improvement of 5
Supervision Contract:
No. junctions
Supervision Consultant: TBD
Under Procurement

Contractor:
Sadeem Al Kuwait General
Works Contract:
Trading & Contracting
UGX 337,526,153,350
Company
Rwenkunye –
12. 90.9 Asphalt IsDB/ GOU 40.02
Apac (Lot 1) Supervision Contract:
Supervision Consultant:
USD 3,637,650 (combined
Dar Al Handasah
for Lot 1 and Lot 2)
Consultants (Shair and
Partners)

Contractor:
Works Contract:
Gulsan Insaat Sanayi
UGX 416,337,936,348.42
Apac – Lira –
13. 100.1 Asphalt IsDB/ GOU Supervision Consultant:
Puranga (Lot 2) Supervision Contract: 53.05
Dar Al Handasah
USD 3,637,650 (combined
Consultants (Shair and
for Lot 1 and Lot 2)
Partners)

Contractor:
Works Contract:
M/s China Railway No.3
UGX 206,050,702,521
Moroto- Engineering Group Co., Ltd
14. 42 Asphalt GOU 80.04
Lokitanyala
Supervision Contract:
Supervision Consultant:
N/A
In-house supervision team
Tororo-Busia Asphalt Contractor:
Works Contract:
15. Road and Mayuge 44 Concrete/ GOU M/s China Railway 18th 52.58
UGX 136,857,027,680
and Busia Town Surface Bureau Group Co., LTD
ON-GOING UPGRADING PROJECTS AS OF MARCH 2024
Length Source of Progress
No. Road Project Surface Contractor / Consultant Contract Amount
(KM) Funding (%)
Roads dressing
Supervision Consultant:
In-house supervision team

Contractor:
Emergency M/s Arab Contractors
Reconstruction of (Osman Ahmed Osman &
Saka Crossing Asphalt Co.) Works Contract:
16. - GOU 98.10
under Design and Concrete UGX 76,500,755,047
Build Supervision Consultant:
Scheme In-house supervision team

Contractor: China
Kawuku- Communications
Bwerenga Road Construction Company Ltd
(6.6km) & Asphalt (CCCC) Works Contract:
17. 8.2 GOU 83.21
Namugonde- Concrete UGX: 38,170,421,651
Bugiri (Fuel Tank Supervision Consultant:
Reservoir 1.6km) In-house supervision team

Contractor:
M/s Arab Contractors
Selected Town (Osman Ahmed Osman &
Roads (7.5 Km) in Asphalt Co.) Works Contract:
18. 20 GOU 42.22
Pallisa and Kumi Concrete UGX 146,193,637,549.61
(12.2 Km) Consultant:
In-house supervision team

Contractor:
M/s China Railway Seventh
Asphalt
Remedial Works Group Co.Ltd
Concrete/ Works Contract:
19. on Ntungamo - 65 GOU Mobilisation Ongoing
Surface UGX 53,589,419,290
Kabale -Katuna Consultant:
dressing
In-house supervision team
ON-GOING UPGRADING PROJECTS AS OF MARCH 2024
Length Source of Progress
No. Road Project Surface Contractor / Consultant Contract Amount
(KM) Funding (%)
Water Relocation
The project for the
Contractor:
improvement of
M/s Bunyonyi Technical
national roads in
Services Ltd
the refugee Water Relocation
Supervisor:
hosting areas of Contractor:
NWSC
West Nile Sub Water Relocation Works 78%
Relocation of
20. region. GOU Contract:
Utility Works Power Relocation
Implementation of UGX 53,589,419,290 Power Relocation
Contractor:
Yumbe – Manibe Contractor:
Mal Kat Terminal Services
(Ure bridge road) 85%
Ltd
(23.6km)
Supervisor:
upgrading project
WENRECO

Contractor:
Works Contract:
China Railway Seventh
UGX 42,586,137,111
Group Co. Ltd (CRSG)
Access Road to
Kabaale Supervision Contract:
Asphalt Consultant:
21. International 3.5 GOU UGX 2,797,933,998 0.03
Concrete Net Consult Consulting
Airport from
Engineers in JV With Stadia
Kabaale
Engineering Works
Consultant Plc and KKATT
Consult Ltd.
REHABILITATION PROJECTS
COMPLETED ROAD REHABILITATION PROJECTS
No. Road Project Length (KM) Source of Funding Region
1 Kawempe-Luwero road 66 WB/ GoU Buganda
2 Luwero-Kafu road 50 WB/ GoU Buganda
3 Fort Portal – Hima road 55.2 WB/ GoU Tooro
4 Hima – Kasese – Kikorongo and Kasese – Kilembe road 53 WB/ GoU Rwenzori
5 Kikorongo – Katungru/ Equator roads 54 WB/ GoU Rwenzori
6 Busega-Mityana road 57.2 WB/ GoU Buganda
7 Jinja-Bugiri road 72.8 EDF/ GoU Busoga
8 Masaka-Mbarara and Masaka-Kyotera 254 EDF/ GoU Buganda/Ankole
9 Tororo-Mbale 49 GOU Bugisu
10 Mbale-Soroti 102 GOU Bugisu/Teso
11 Jinja-Kamuli 57 GOU Busoga
12 Mukono-Jinja 52 GOU Buganda-Busoga
13 Kiryandongo-Karuma-Kamdin 59 GOU Bunyoro-Acholi
14 Kamdin-Gulu 62 GOU Acholi
15 Ishaka – Katunguru 58.00 GOU Ankole
16 Hima-Katunguru (Phase I) 28.00 GOU Rwenzori
17 Kyenjojo – Fort Portal 50.00 GOU Tooro
18 Nansana – Busunju road 48.10 GOU Buganda
19 Jinja-Kamuli 22.00 GOU Busoga
20 Mukono-Kalagi-Kayunga-Bukolooto-Njeru 92.00 GOU Buganda
21 Namunsi – Sironko – Muyembe - Kaselem (PHASE I) 40.00 GOU Sebei
22 Pakwach-Nebbi (54 Km) 54 GOU West Nile
23 Kafu-Kiryandongo-Kamdini 43 GOU Bunyoro-Acholi
24 Iganga-Kaliro 32 GOU Busoga
25 Kasalem - Kapchorwa (PHASE II) 29 GOU Sebei
26 Nakalama -Tirinyi - Mbale 102 GOU Busoga
29 Namunsi - Sironko - Muyembe - Kapchorwa Phase II 29 GOU Sebei
30 Hima – Katunguru (29 km) Phase II and 4.5Km Kasese GOU Rwenzori
35
Town Roads, 1.5Km Hima service roads.
31 Buddo and Nabbingo Access Roads 6 GOU Buganda
32 Masaka Town Roads 9.3 GOU Buganda

PROGRESS OF ONGOING ROAD REHABILITATION PROJECTS AS OF MARCH 2024


Length
No. Road Project Finder Contractor / Consultant Contract Amount Progress (%)
(KM)

Contractor:
Works Contract:
Mityana - Mubende M/s Energoprojekt-Niskogrannja
UGX 395,248,484,289
1 (86km) & Mityana Town 100 GOU A.D 26.45
Roads (14km) Consultant:
Prome Consult Ltd

Contractor:
M/s Energoprojekt Niskogradnja
A.D Works Contract:
2 Kampala - Jinja Road 72 GOU UGX 82,023,283,416 50.25
Consultant:
In-House Supervision Team

Contractor:
M/S Mota-Engil Engeharia E
Construcao Africa, SA Works Contract:
Routine
World UGX 290,976,512,298.25
3 Tororo – Mbale – Soroti 150.8 Maintenance
Bank/ GOU Consultant: USD 9,463,248 and UGX
Ongoing
TNM Limited of Israel in association 2,370,533,211
with KAGGA and Partners Uganda

Contractor:
M/S Mota-Engil Engeharia E
Construcao Africa, SA
Rehabilitation and
Soroti – Dokolo – Lira- World Works Contract:
4 189.4 improvement Works
Kamdini Road Bank/ GOU Consultant: UGX 331,623,758,818.88
ongoing
TNM Limited of Israel in association
with KAGGA and Partners Uganda
Contractor:
China Railway 18th Bureau Group
Alwii – Nebbi (33Km) and
Works Contract:
5 Upgrading of Packwach 33 GOU 48.66
Consultant: UGX 104,554,875,495
and Nebbi Town Roads
In-House Supervision Team

Contractor:
M/s NEC and CRSG Joint Venture
Works Contract:
6 Olwiyo – Pakwach Road 62.5 GOU 23
Consultant: UGX 177,443,228,975
In-House Supervision Team

Contractor:
Chongqing International
construction corporation (CICO) Works Contract:
Additional Masaka Town
7. 9.3 GOU UGX 53,336,684,835 99
Roads
Consultant:
In-House Supervision Team

Contractor:
Abubaker Technical Services &
GOU General
Busunju- Kiboga-Hoima Works Contract:
8. 145 Supplies Ltd. 1.31
Road UGX 309,073,180,813
Consultant:
In-House Supervision Team
Contractor:
National Enterprise Corporation
and China Railway Seventh Group
Works Contract:
Co.,Ltd Joint Venture
9. Karuma-Olwiyo 43.5 GOU UGX; 48,617,881,569 0.03
(NEC&CRSG)

Consultant:
In-House Supervision Team
Contractor:
Matugga-Semuto- Abubaker Technical Services &
Kapeeka Road (41Km) General Supplies Ltd. Works Contract:
10. 46 GOU 3.60
and Upgrading of Town UGX 216,116,086,606
Roads (5Km) Consultant:
UNRA In-house Supervision Team

PROJECTS UNDER PROCUREMENT AS OF MARCH 2024


NO. SUBJECT

1. Emergency Repair Works at landslide affected sections along Fort portal-Bundibugyo-Lamia Road(0.35Km)

2. Supply and delivery of Lubricants for Ferries under Framework contract for three years.
Civil works for the Upgrading of Katine-Ochero Road (69.3km) including the construction of 2.9kms of Town Roads in Kaberamaido and
3.
Kalaki Towns to Bituminous Standard.
Consultancy Services for Monitoring and Evaluation, Technical Audit and Road Safety Audit under the Namagumba-Budadiri-Nalugugu Road
4.
Project (37km)
Consultancy Services for Design Review & Construction Supervision for upgrading Masaka-Kyotera-Mutukula Road
5.
Procurement of a Frame Work Contract for the Supply and Delivery of Critical Spare Parts and Onboard Equipment for UNRA Ferries for
6.
Three (03) years.
7. Addendum for Consultancy Services for Design Review and Construction Supervision for Busega-Mpigi Expressway (23.7 Km)

8. Consultancy Services for the Design Review and Construction Supervision of Lira-Abim Road (125Km) from gravel to paved (Bit) standard.
Consultancy Services for Independent Engineer for Kampala- Jinja Expressway PPP Project
9.
Provision of Consultancy Services for Awareness Creation on Dangers of Female Genital Mutilation (FGM) and Gender-based Violence
10.
(GBV) on Kapchorwa -Suam road section (73km)
Additional Construction Supervision Services for Upgrading of Muyembe - Nakapiripirit Road Project (92Km) from Gravel to Paved (Bitumen0
11.
Standard
Consultancy Services for the Preparation of Sironko District Physical Development Plan and Urban Physical Development Plans for Seven
12.
Selected Urban Centres within the district
Consultancy Services for Design Review and Construction Supervision of Works for the Upgrading of Kihura - Kahunge Road and Mpara-
13.
Bwizi Road (105Km) to Bitumen
Consultancy Services for Design Review and Construction Supervision of Works for the Upgrading of Katine-Ochero Road to Bitumen
14.
Consultancy Services for undertaking Studies Mobility patterns and Transport Barriers for women in the Refugee Hosting Districts and the
15.
Design of Potential Pilots for Refugees to Benefit from Road Upgrading
Consultancy Services for Design Review and Construction Supervision of Katuna-Muko-Kamuganguzi Road (104Km)-Lot II from Gravel to
16.
Paved (Bituminous) Standard.
Consultancy Services for Monitoring and Evaluation, Technical audit and Road Safety Audit and Sensitization of Kabale-Lake Bunyonyi and
17.
Kisoro-Mgahinga Road Upgrading Project (34km)
18.
Supply, Delivery, installation and Commissioning of ICT Equipment for UNRA Weighbridge Stations –Servers
Supply and installation of Reinforced Concrete Marker Posts to Demarcate Right of Way for the Kampala Jinja EExpressway PPP Project
19.
under FWC
Addendum for Consultancy Services for Design Review and Construction Supervision for Busega-Mpigi Expressway (23.7 Km)
20.
Provision of Consultancy Services for Feasibility Study and Detailed Engineering Design of Corner Kilak-Adilang-Abim-Kotido Road (162km)
21.
Consultancy Services for Procurement of Operation and Maintenance Equipment for the Source of the Nile Bridge under Direct Procurement
22.
Consultancy Services for Design Review and Construction Supervision for the Upgrading of Namagumba-Budadiri-Nalugugu Road Project
23.
(39km) from Gravel to Paved (Bitumen) Standard.
Consultancy Services for the Design Review and Construction Supervision of Luku-Kalangala-Mulabana Road (65.6km), 7 No Town Roads
24.
(10.6km) from gravel to Paved (Bituminous) Standard and 2No Ferry Landing Sites
Consultancy Services for Managing Risks associated with Gender Based Violence (GBV)/Sexual Exploitation and Abuse (SEA) on Koboko-
25.
Yumbe-Moyo Road under Upgrading Project (KYM)-Retender
Additional Inputs for Consultancy Services for Construction Supervision for the Upgrading of Kapchorwa-Suam Road (73km).
26.

27.
Supply and Delivery of Weighbridge Spare Parts under a Framework Contract for three years -Re tender
28. Civil Works for the Upgrading of Corner Bobi-Aboke-Corner Ayer Road (54.27Km) from Gravel to Paved Standard.

29. Works for Installation of Battery Backup Power for Traffic Lights in Entebbe.
Consultancy Services for Framework Contract to undertake Environmental and Social Impact Assessment (ESIA) and Resettlement Action
30.
Plan (RAP) preparation for a period of three years (Retender)
Consultancy Services for the Design Review and Construction Supervision for the Upgrading of Corner Bobi-Aboke-Corner Ayer Road
31.
Project (54.27Km)
32. Procurement of Frame Work Contract for the Supply and Delivery of Life Saving Appliances to Ferries for three years

33. Construction of the Kamengo High Speed Weigh-In- Motion Lanes Station and Parking Yard

34. Design and Build of Kira-Matugga and Improvement of 5 No. Junctions: Addendum No. 1 to Contract:
Construction of Munyonyo - Kajjansi Spur Street Lighting along Entebbe Expressway (14Km) and Zana to Mpala (19km)
35.
Lot 1: Zana – Mpala section (19km)
Construction of Lugogo-Kasozi (1Km) and Lugogo-Ngoma (6.6Km) Approach Roads to Augment the Construction of Swamp Crossing along
36.
Kyamukonda-Kasozi-Ngoma Road
Design and Build of Kinyara Sugar Factory Access Road (8km) Under Contract for Design and Build of Lot 3: Masindi-Biiso,Kabale-
37.
Kiziranfumbi, Hohwa-Nyairongo, Kyarushesha-Butole Road Upgrading Project (97km)- Package 5
Consultancy Services for the Design Review and Construction Supervision for the Upgrading of Bubulo-Bududa Circular Road (28km) and
38.
Mbale- Nkokonjeru Road (21km) from Gravel to Paved (Bituminous) Standard
Additional Inputs for Consultancy Services for Design Review and Construction Supervision for the Upgrading of Rukungiri-Ishasha Road
39.
(78.5km)
Consultancy Services for the Construction Supervision of the Emergency Reconstruction of Selected Sections along Kampala – Masaka
40.
Road damaged by floods under Design and Build for Katonga Bridge (2.7 Km), Lwera Swamp (11.6 Km) and Kalandazi Swamp (1.5 Km)
Consultancy Services for the Construction Supervision of the Emergency Reconstruction of Ssezibwa Bridge (1.6 Km) along Kalagi-Kayunga
41.
Road under Design and Build.
42. Supply and delivery and installation of Mobile Accommodation Units for BKK Ferry Project
Supply and Delivery of Hydromaster Ferry Propulsion Units and Components under Framework Contract for three years
43.

44. Design and Build of Kotido-Kaabong Road (69.6Km)


Design and Build of Kotido-Moroto Road from gravel to paved (bituminous) standard (96.4Km).
45.
Addendum No. 1 to the Contract for Emergency procurement of Design and Build contractor to develop an alternative landing site at
46.
Wanseko
47. Emergency supply and installation of solar street lighting on Kajjansi - Munyonyo spur (14 km)
Emergency Ramp Repair Works of MV Nakiwogo – II Ferry
48.
Civil Works for the Upgrading of Kabwohe-Bwizibwera/Nyakambu-Nsiika Road (46.4km) from Gravel to Paved (Bituminous) Standard
49.
Consultancy Services for the Design Review and Construction Supervision for the Upgrading of Karenga-Kapedo-Kaabong Road Project
50.
(67.5Km)
51. Consultancy Services for Road Asset Management and Investment Planning Support for UNRA.
Emergency Reconstruction of Ssezibwa Bridge (1.6Km) along Kalagi-Kayunga Road under Design and Build
52.
Reconstruction of Masaka-Kyotera-Mutukula Road (89.5Km) and Rehabilitation of Nyendo-Villa Maria Road (11Km) and Access Roads (7Km)
53. to paved standards

54. Civil Works for Upgrading of Bubulo-Bududa Circular Road (25km) and Mbale -Nkokonjeru (21Km) Roads from Gravel to Paved (Bituminous)
Emergency Reconstruction of Katonga River Swamp crossing along Kabulasoke-Villamaria road under Design and Build.
55.
Individual Consultant under framework Contract for Survey/CADD expert on selected Road Projects under UNRA.
56.

57. Supply, Delivery, Training and Commissioning of a Mobile Crane Truck for Enforcement Operations

58. Supply and Delivery of Timber Pallet for Ferries under framework contract for 3 years; Go Grow Investments Ltd

59. Supply, Installation, Operation and Maintenance of Automatic Traffic Counters

60. Procurement of Community Liaison Officers on Koboko-Yumbe-Moyo Road Project (Re-tender)


Consultancy Services for Carrying out Third Party Technical Audits on Koboko-Yumbe-Moyo Road
61.
Consultancy Services for Updating Gender Mainstreaming Tools and Data for Roads and Bridges
62.
Consultancy Services for Road Safety Sensitization and awareness Campaigns on Koboko-Yumbe-Moyo Road.
63.
Consultancy Services for Review and Strengthening of Environment, Social, Health and Safety Management Systems at UNRA (ESHSMS)
64.
Consultancy Services for Feasibility Study and Detailed Engineering Design for Capacity Improvement and Signalization of Namungoona-
65.
Nansana-Wakiso-Kakiri Road (30km)
Consultancy Services for Carrying out Periodic Monitoring and Evaluation Services and User Satisfaction Surveys of the Roads and Bridges
66.
Project
Consultancy Services for Feasibility Study and Detailed Engineering Design of Kilak (Gulu)-Rhino Camp Road (100 Km)
67.
Civil Works for the Upgrading of Kyenjojo (Kihura)-Bwizi-Rwamwanja-Kahunge/MparaBwizi Road (105km) to Bituminous Standard
68.
69. Procurement of Social Development Specialist (Re-tender) for KYM.
Kampala-Jinja Expressway PPP Project Implementation Unit (PIU) Consulting Services- Individual Consultants
• Legal Expert
70.
• Environmental Specialist
• Right of Way (Surveyor)
Consultancy Services for the Feasibility Study and Detailed Engineering Design for Soroti (Arapai)-Amuria-Acan Pii (88 Km
71.

72. Civil Works for the Upgrading of Katuna-Muko-Kamuganguzi Road (104Km)- Lot 2 from Gravel to Paved (Bituminous) Standard

CONTRACTS SIGNED AWAITING IMPLEMENTATION (AS OF MARCH 2024)


NO. SUBJECT CONTRACTOR
Emergency Reconstruction of Selected Sections along Kampala-Masaka China Communications Construction Company (CCCC)
Road damaged by Floods under Design and Build for Katonga Bridge (2.7km),
1.
Lwera Swamp (11.6km) and Kalandazi Swamp (1.5km): Addendum No. 1 to
Contract:
Framework for Maintenance of Street Lighting across the Country for three Sinew Limited.
2.
years.
Framework for Maintenance of Street Lighting across the Country for three Green Power International Ltd
3.
years.
Civil Works for the Upgrading of Koboko-Yumbe-Moyo Road (103.08km) from Zhongmei Engineering Works Ltd
4.
Gravel to Paved (Bituminous) Standard
Consultancy Services for Design Review for the Upgrading of Koboko Yumbe Intercontinental Consultants and Technocrats PVT Ltd in Joint
5.
Moyo Road (103.08km venture with Gauff Consultants (U) Ltd

.
PROJECTS UNDER DESIGN AS OF MARCH 2024
Projects Under Design Review
SN Project Name Length, Km
1. Puranga-Acholibur 62
2. Kitgum-Kidepo 110
3. Lusalira-Nkonge-Ssembabule 97
4. Kibuye-Busega 10
5. Kisubi-Nakawuka-Nateete
6. Kabale - Bunyonyi/Kisoro-Mgahinga 33
7. Kisoro-Rubuguli-Muko 72
8. Karugutu-Ntoroko 50
Feasibility Studies and Detailed Design (Inhouse)
9. Matugga-Wakiso-Buloba - Nsagi - Nsagu 38.7
10. Atiak - Kitgum 128
Feasibility studies and Preliminary Design (External Consultants)
11. Bunagana-Kyanika and Lamia One Stop Border Posts
12. Kituuma-Kapeeka-Butalangu 37
13. Soroti-Serere-Pingire-Mugarama 64
14. Kamwenge-Dura-Rwimi 57
15. Nyakabirizi-Nyakashaka-Nsiika 48.3

16. Puranga-Acholibur 64

17. Nebbi-Goli 17.5

18. Pajule-Pader District Headquarters 20


19. Busega Systems Interchange
20. Isingiro – Kamuli - Kyasimbi Road 71.5
21. Kamatalisi-Ngarama - Kibengo - Burama 19.6
22. Kityaza Tc-Burama-Bugango 13.7
23. Kityaza Tc-Nakivale Camp 3.8
24. Juru-Kibengo 4.8
Feasibility Study and Detailed Engineering Design (External Consultants)
25. Kabwohe-Bugongi-Kitagata-Kabira-Rukungiri/Ruhinda-Kashenshero-Mitooma Road - Lot 1 99
26. Kapeeka Roads 188

27. Kamuli-Kaliro-Pallisa - Lot 2 90


28. Gulu - Corner Kilak - Lot 3 100
Arua (Manibe)-Ure (51Km), Ure-Kulikulinga (7Km), Kulikulunga-Obongi landing site (45Km), and Obongi-Adjumani (35Km) –
29. Lot 6 138
Capacity Improvement & Expressway Projects
30. Kampala Jinja Expressway & Kampala Southern Bypass: Update and Issuance of Final RFP 95
31. Transaction Advisory Services Agreement for Uganda PPP Roads Projects 95

32. Kampala-Jinja Expressway PPP Project Implementation Unit (PIU) Consulting Services- Individual Consultants

33. Kampala Entebbe Expressway: Operation & Maintenance Contract 26


Bridge under Design
34. Diagnostic Study and Assessment of Karuma Bridge
35. Masindi Port Bridge
36. Laropi bridge
Road Rehabilitation/Periodic Maintenance Design Projects
36. Nebbi - Arua 80
37. Mbarara - Ishaka 59
38.. Kampala-Gayaza 12
39. Gayaza - Zirobwe 32
40. Gayaza - Kalagi 20
41. Hoima - Kaiso - Tonya 91
42. Namugongo - Seeta 15
43. Ntungamo-Katuna 76
44. Gulu - Atiak - Nimule 108
Low Volume Roads
45. Bukomero - Dwaniro - Kyankwanzi 68.8
46. Abayita - Ababiri 7
Road Safety
47. Carry out 20 No Road Safety Audits/ Assessments (No.) 10
48. Carry out 20No Road Safety Inspections
49. Review 10 No Traffic Impact Assessment Reports (5No.) 5
50. Prepare 5No Road Safety Designs
51. Review of Bill Board Designs (no. of submissions) 20
Bottlenecks
52. Detailed Design of 15No Bottlenecks 0.802
SN COMPLETED DESIGNS, AWAITING FUNDING KM
1. Puranga-Acholibur 62
2. Pajule – Pader District Headquarters 18
3. Lusalira - Nkonge - Lumegere - Sembabule 97
4. Karugutu-Ntoroko Road 50.3
5. Kisoro - Nkuringo - Rubugiri - Muko Road 72
6. Laropi - Moyo - Afoji 37.3
7. Kibuye - Busega 10
8. Kayunga – Bbaale – Galiraya 89
9. Nambole - Namilyango – Seeta - Mukono 14
10. Ishasha – Katunguru 87
11. Jinja-Mbulamuti-Kamuli 65
12. Kamuli – Bukungu 64
13. Dokolo – Ochero – Namasale 88
14. Mbale - Nkokonjeru 21
15. Luku – Kalangala – Mulabana 66
16. Moroto-Kotido 100
17. Kotido-Kaabong 64
18. Karenga – Bira ( Sudan Border) 42
19. Kitgum – Orom – Karenga 116
20. Abim – Aloi – Lira 187
21. Atiak – Kitgum 108
22. Kumi – Ngora – Brooks Corner – Serere – Kagwara 102
23. Bubulo – Bududa Circular Road 28
24. Kanyantorogo - Butogota - Bohoma 31.4
25. Hamurwa-Kerere-Kanungu 47
26. Butogota-Ifasha-Ruhija-Ikumba 64
27. Buzibwera- Nyakambu - Nsiika - Nyakashaka - Nyakabirizi with spur to Kabwohe 92.2
28. Kanoni - Misingi - Mityana 37
29. Iganga - Bulopa - Kamuli 57.2
30. Nabumali - Butaleja - Namutumba 90
31. Kashwa-Kashongi-Ruhumba 33