Lanning For Tartup: Startup Planning Model
Lanning For Tartup: Startup Planning Model
Industry
Institute
includes
Startup
Planning
Model
• Front-End Engineering
• Detailed Design
• Procurement
• Construction
• Initial Operations
Implementation
Resource
121-2
Planning for Startup
Prepared by
April 1998
CII members may reproduce and distribute this work internally in any medium at no cost to internal recipients.
CII members are permitted to revise and adapt this work for the internal use provided an informational copy is
furnished to CII.
Available to non-members by purchase; however, no copies may be made or distributed and no modifications
made without prior written permission from CII. Contact CII at http://construction-institute.org/catalog.htm to
purchase copies. Volume discounts may be available.
All CII members, current students, and faculty at a college or university are eligible to purchase CII products at
member prices. Faculty and students at a college or university may reproduce and distribute this work without
modification for educational use.
Chapter Page
Introduction ........................................................................................................... 1
Definition of Startup
1
Introduction
No. of Startup
Project Phase Planning Activities
2
Phase 1 - Requirements Definition & Technology Transfer
Establish
Startup Objectives
[3-A]
Make Startup Refine Startup
Team Assignments Budget & Schedule
[3-C] [3-I]
Identify Startup
Identify
Procurement
Startup Systems
Requirements To Phase 4
[3-D]
[3-H]
Introduction
Q = Quality Gate
3
Introduction
4
Address Assess & Communicate Plan for Include Startup in Plan for
Startup Issues in Startup Effects Supplier Field Support Project CPM Schedule Startup QA/QC
Team-Building Sessions from Changes of Startup [4-D] [4-E]
[4-A] [4-B] [4-C]
Refine Startup Team Acquire Additional Indicate Startup System Refine Startup
Organization & Operations & Numbers on Engineering Risk Assessment
Responsibility Maintenance Input Deliverables [4-I]
Assignments [4-G] [4-H]
[4-F]
Refine Startup
Budget & Schedule
[4-N]
Phase 5 - Procurement
Phase 6 - Construction
To Phase 7
Refine Conduct Implement Field Conduct Construction
Startup Integrated Operator/Maintenance QA/QC Plan Startup Team Building
CPM Schedule Training [6-E] [6-B]
[6-C] [6-D]
Transition to
Startup System Based
Execution
[6-G]
Q = Quality Gate
To Phase 7
Introduction
5
Introduction
6
Finalize
Operations/Maintenance Checkout Systems Commission Systems
Organization & [7-B] [7-C]
Q Q
Management System
Q [7-A]
Q = Quality Gate
Introduction
Title
7
Introduction
• The manager of the business unit must take the lead in defining
startup objectives.
8
Introduction
Startup planning is not easy and has many barriers. Overall, 140
barriers to the 45 activities have been identified. These barriers can be
grouped by common themes:
• Ineffective communication
• Schedule pressures
Overview of Tools
9
Introduction
While all 26 tools (listed in Table 1.4) are important and can facilitate
startup planning in some beneficial way, arguably, two tools standout as
most important and can be used to substantially improve the quality of
startup planning. These two tools are the SuPER tool (Tool 1-A-2) for
evaluating the degree of startup planning, and the Startup Execution Plan
(Tool 3-B-2), a mechanism for integrating all startup planning
developments.
10
Introduction
11
Introduction
Tool 3-B-2: Sample Table of Contents for the Startup Execution Plan:
guidance on the types of information that should be
addressed in the execution plan.
12
Introduction
13
Phase 1: Requirements Definition and Technology Transfer
B. Key Concepts: Business unit management and key project leaders must be equally
committed to the development of a startup plan as a key element of an integrated
overall Project Execution Plan. Operations management must be convinced to
provide startup resources throughout the project planning process.
C. Deliverables: A document that clearly identifies project goals, major risks, and key
responsibilities. Key startup expertise should be identified, especially experienced
operations personnel, to interface early-on and throughout critical project phases.
G. Basic Steps: Understand the project business plan and the technology transfer aspect;
identify all key owner manufacturing representatives; understand the criticality of the
project schedule; and understand the order-of-magnitude of planning efforts required
for a successful startup.
H. Tools Needed/Provided:
Provided: graphical plot of project success vs. startup success; SuPER tool for periodic
evaluation of startup planning efforts
Needed: tools for assessing and ensuring management commitment to needed startup
resources
15
Tool
1.0
R2 = 0.56
0.8
0.7
0.6
0.5
0.4
0.3
0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
Tool
Tool
Project:
Evaluator: Date:
No Minimal With With Minor Thoroughly
Act. No. Planning Activity Execution Effort Deficiencies Deficiencies Executed Score
4-A Address startup issues in team building sessions 0 0 1 1 1 _____
4-B Assess & communicate startup effects from changes 0 0 1 1 1 _____
4-C Plan for supplier field support of startup 0 0 1 1 2 _____
4-D Include startup in the project CPM schedule 0 1 2 3 4 _____
4-E Plan for startup QA/QC 0 0 1 1 1 _____
4-F Refine startup team organiz’n & respons’b’ty assignm’ts 0 1 1 3 4 _____
4-G Acquire additional O&M input 0 1 1 2 3 _____
4-H Indicate startup system numbers on engr. deliverables 0 1 1 2 3 _____
4-I 6-F Refine/update startup risk assessment 0 1 1 1 2 _____
4-J Plan operator/maintenance training 0 1 2 3 4 _____
4-K Develop startup spare parts plan 0 0 1 1 1 _____
4-L Develop system turnover plan 0 1 1 3 4 _____
4-M Develop & communicate startup procedures & PSM 0 1 1 3 4 _____
5-A Qualify suppliers for startup services 0 0 1 1 1 _____
5-B Refine/update startup spare parts plan & expedite 0 0 1 1 1 _____
5-C Implement procurement QA/QC plan 0 0 1 1 1 _____
Detailed Design & Procurement Phase Total 0 8 18 28 37 _____
6-B Conduct Construction-Startup team building 0 0 1 1 1 _____
6-C Refine/update startup integrated CPM schedule 0 1 2 3 4 _____
6-D Conduct operator/maintenance training 0 1 1 3 4 _____
6-E Implement field QA/QC plan 0 0 1 1 1 _____
6-G Transition to startup systems-based execution 0 1 2 4 5 _____
Construction Phase Total 0 3 7 12 15 _____
Maximum Total: All Phases 0 21 50 79 100 _____
Total This Sheet: _____
Total Sheet 1: _____
GRAND TOTAL:
Tool 1-A-2. SuPER Score Target Profile
Thorough Planning 100
90
80
70
60
SuPER
50
Score
30
20
10
No Planning 0
Definition, Front-End Detailed Construction Checkout,
Concept & Engineering Design Commissioning,
Feasibility & Initial
Operations
Project Phases
19
Tool
Phase 2: Conceptual Development and Feasibility
21
Phase 2: Conceptual Development and Feasibility
22
Phase 2: Conceptual Development and Feasibility
H. Tools Needed/Provided:
Provided: financial risk assessment checklist
Needed: video: “Trip to Abilene”
I. Challenges to Successful Implementation:
• Such “reality checks” are usually politically sensitive and difficult to accept.
23
Tool
1 Req. Def.
& Tech. Trans.
Startup Planning
Commitment
2 Concept. Devp.
& Feasibility
Startup Planning
Realistic Scope
3 Front End
Engineering
Startup Planning
Objective
Exec. Plan
ID Systems
4 Detailed Design
Startup Planning & Implementation
Detailed Plans
5 Procurement
Startup Planning & Implementation
Supplier Integration
6 Construction
Startup Planning & Implementation
Transitions to Systems
Implementation
Planning effort
Material Cost
Contract Cost
(Work -ours)
(Work -urs)
Services
Item #
effort
Item
Requirements Definition & Technology Transfer
1 Engineering efforts
Phase Subtotal
Front-End Engineering
6 Engineering efforts
7 Manufacturing/Operations efforts
8 Maintenance efforts
9 Outside services: labs, consultants, certifications
Phase Subtotal
25
Tool
Tool
Implementation
Planning effort
(Work-Hours)
(Work-Hours)
Material Cost
Contract Cost
Services
Item #
effort
Detailed Design Item
11 Manufacturing/Operations efforts
12 Maintenance efforts
13 Outside services: labs, consultants, certifications
14 Training program development
Phase Subtotal
Procurement
15 Engineering efforts
16 Construction efforts
17 Manufacturing/Operations efforts
18 Maintenance efforts
19 Outside services: suppiers, labs, consultants, certifications
20 Training program development
21 Materials & equipment expense
22 Utilities
23 Feedstock, catalyst, raw material, product handling
Phase Subtotal
Tool 2-B: Example of Startup Cost Breakdown Structure (page 3 of 4)
Implementation
Planning effort
(Work-Hours)
(Work-Hours)
Material Cost
Contract Cost
Services
Item #
effort
Construction Item
24 Engineering efforts
25 Construction efforts
26 Manufacturing/Operations efforts
27 Maintenance efforts
28 Outside services: suppiers, labs, consultants, certifications
29 Training program development and implementation
Tool
Tool
Implementation
Planning effort
(Work-Hours)
(Work-Hours)
Material Cost
Contract Cost
Services
Item #
effort
Item
Check-out & Commissioning (continued)
38 Material & equipment expense
39 Utilities
40 Feedstock, catalyst, raw material, product handling
Phase Subtotal
Initial Operations
41 Engineering efforts
42 Construction efforts
43 Manufacturing/Operations efforts
44 Maintenance efforts
45 Outside services: suppiers, labs, consultants, certifications
46 Material & equipment expense
47 Utilities
48 Feedstock, catalyst, raw material, product handling
Phase Subtotal
Tool 2-C: Startup Financial Risk Assessment Checklist (page 1 of 2)
Risk Assessment Not
# Risk Issues Low Med. High Uncertain Applicable Comments
A Organizational Experience
Owner/Contractor Startup Mgr.
Owner/Contractor Startup Team
Owner/Licensor Pilot Plant Team
Key Supplier(s)
Other:
B Process Technology
Degree of Definition
New or Proven
Complexity
Pilot Plant Experience
Automation & Controls Experience
Equipment/System Redundancies
Note: This checklist is not all-inclusive, but is intended primarily to stimulate discussion.
29
Tool
Tool
Note: This checklist is not all-inclusive, but is intended primarily to stimulate discussion.
Phase 3: Front-End Engineering
31
Phase 3: Front-End Engineering
32
Phase 3: Front-End Engineering
33
Phase 3: Front-End Engineering
34
Phase 3: Front-End Engineering
36
Phase 3: Front-End Engineering
37
Phase 3: Front-End Engineering
38
Phase 3: Front-End Engineering
39
Phase 3: Front-End Engineering
40
Phase 3: Front-End Engineering
Tool
to commercial operations.
8. Level of Effort Required by the Startup Team: Actual startup work hours and resources
are at or below planned level of effort.
41
Phase 3: Front-End Engineering
As shown above, research indicates that a successful startup requires successful performance
in eight different areas:
• Product quality
• Product quantity
• Schedule performance
• Safety performance
• Environmental compliance
• Operations team performance
• Impact to ongoing operations
• Level of stress experienced by startup team
With the use of criteria performance scores and criteria importance weightings, these eight
Tool
criteria can be integrated into a single startup success index score. Such a score allows for ready
comparisons between startups, company-wide benchmarking, and even industry-wide
benchmarking.
42
Phase 3: Front-End Engineering
By weighting the least important criteria with a value of one, criteria of below average
importance with a value of two, etc., normalized criterion importance weightings can be derived
by determing the relative contribution of each criteria to the sum total of importance weightings
for all eight criteria. This is best illustrated with an example, as presented in Table 3-A.4.
Tool
In this way, importance weightings can be determined for each startup success criterion and
these will be consistent on a relative basis (e.g., the same weight-ings for all criteria will result
if all are assigned the same level of importance).
Fig. 3-A.1 graphically depicts the average importance weightings for the eight criteria based
on 23 actual startups analyzed. The weightings of all eight criteria fall into a relatively tight
range: between 0.10 and 0.14. Thus, at least for the startups analyzed, on average, all eight
criteria are nearly equally meaningful to startup success.
Now, given the availability of both criteria performance scores and criteria importance
weightings, a single startup success index score can be computed by simply multiplying one by
the other and summing up for all eight criteria. (Criteria performance scores should be divided
by 5 in order to achieve a 0 to 1 scale.)
43
Tool
Product Quantity Production rates Production rates met Production rates Plant did not meet Production rates were
consistently project goals. were marginally less production rates set at significantly lower
Performance
exceeded project than planned but project authorization. than planned and
goals. customers were not required significant
affected. construction rework.
Schedule The startup duration The startup duration The startup duration The startup duration The startup duration
was significantly less was as planned. was as planned but exceeded plan and far exceeded the
Performance
than estimated. The meeting the schedule meeting the schedule original plan.
process was on-line required extra levels required heroic efforts
sooner than of labor and/or on the part of the
expected. materials. startup team.
Tool 3-A: Listing of Typical Startup Objectives (page 5 of 8)
Tool
Tool
Level of Effort Startup work-hours Startup work-hours Startup work-hours Startup work-hours Startup work-hours
were well below were on budget. Level were on budget. were slightly above were significantly
Required by the
budget. Level of of stress was less than Level of stress was budget. The level of over budget. The
Startup Team stress was much less anticipated. typical. stress was greater than level of stress was
than anticipated. anticipated. significantly greater
than anticipated.
Phase 3: Front-End Engineering
Tool
Those who want to simplify the process can use industry average criteria importance
weightings with the following computation:
47
Phase 3: Front-End Engineering
Safety
Product Quality
Schedule
Environmental
Product Quantity
Level of Effort
Operations Team
Tool
Impact on Operations
48
Phase 3: Front-End Engineering
Early in the project and periodically thereafter, the project manager should do a “reality
check” to ensure that the project schedule effectively meets the demands of the project. In doing
so, project managers need to recognize that, at a very fundamental level, the project schedule
is driven by different factors during the various phases of the project:
• Conceptual design, process engineering, and basic engineering activities are driven by
the systems to be included in the plant. Chemical, mechanical, and process control
designs are examples of such systems-driven project elements.
• Detailed design is driven by site geographical area. The plot plan is divided into areas
and the design of foundations, structures, piping, electrical, and instrumentation
proceeds around the different areas of the site.
• When it comes time to requisition equipment and material, the driving force changes
from area to the procurement train, in which like items are grouped, regardless of their
system or area, so that they can be readily and efficiently handled in the requisitioning,
bidding, ordering, manufacturing, expediting, inspection, delivery, and materials
management activities.
• The driving force during the initial construction efforts reverts to the area, which is
Tool
supported with area-based drawings. As construction nears completion, work must be
completed and tested on a systems basis.
• The startup activities of check-out, commissioning, and initial operations continue to be
executed on a systems basis.
The graphic below illustrates these driving forces and the various transitions that must be
effectively planned and managed. It is important that planners have a clear understanding of
these driving forces in order to develop the most effective schedules.
Sequence-Driver
Phase System Area Procurement
Train
Basic Engineering •
Detailed Design • •
Procurement •
Construction • •
Startup •
49
Phase 3: Front-End Engineering
Tool 3-B-2: Sample Table of Contents for the Startup Execution Plan
3 Startup Objectives
4 Startup Organization
Startup Team
O&M Resources
6 Startup Schedule
7 Startup Budget
9 Procurement Issues
10 Appendices
Startup Procedures
50
Phase 3: Front-End Engineering
Startup quality gates should be implemented together with the project quality gates,
although there are exceptions. Only critical issues pertaining to startup will be delineated here.
All previous basic steps in the corresponding activity profiles should have been completed
in order to clear a quality gate. Business unit and project management must set up a formal
procedure and mechanism to assure compliance. The quality gate represents the completion of
the particular activity. Quality gate activities can be added or deleted as company preferences
dictate.
Tool
4-O Update the Startup Execution Plan
51
Phase 3: Front-End Engineering
At this point all basic steps called for in Phase 1 (Requirements Definitions and Technology
Transfer) and Phase 2 (Concept Development and Feasibility) should have been completed.
At this quality gate, all startup activities to be accomplished during Phase 3 (Front-End
Engineering) are subject for review. This is the most important quality gate because as the
project enters the detailed design phase, changes become increasingly more expensive and
detrimental to schedule adherence.
Tool
52
Phase 3: Front-End Engineering
All startup activities during Phase 4 (Detailed Design) need to be reviewed. Documented
proof of the following critical items is required:
1. Startup team has been formed and team building is taking place around startup issues.
2. Supplier pre-shipment testing requirements and field support have been delineated and
submitted to procurement.
3. Startup execution plan is reflected in project CPM.
4. Operator training plan is in place.
5. System turnover plan is in place.
6. Startup system numbers are indicated on engineering deliverables.
This startup quality gate may not coincide with the overall project quality gate because it
Tool
focuses on procurement requirements and startup team building and training. The major
interface with construction is the field QA/QC program. This startup quality gate review should
take place early in the construction phase.
The following critical activities must be going on or must have been completed:
1. The supplier technical performance criteria and QA/QC requirements are going out with
each bid package.
2. Construction/startup team building has been implemented.
3. O/M (operations & maintenance) training is being implemented.
4. Field QA/QC plan has been implemented based on startup systems.
5. Startup risk assessment has been finalized and is understood by startup leadership team.
6. For pharmaceutical plants all validation protocols have been completed.
7. System completion forecasting is correctly reflected on appropriated schedules.
53
Phase 3: Front-End Engineering
This is a critical startup quality gate because it should give assurance to management that
a knowledgable startup team has been assembled and trained and is ready to commission the
plant according to a detailed startup plan.
At this point management must have assurance that all checkouts have been completed and
are thoroughly documented with appropriate sign-offs. In the pharmaceutical industry these are
called IQs (installation qualifications) and must be documented according to regulation.
Tool
At this step the plant (system by system) must have been verified to be capable of safe
operation. Rigorous documentation is needed for regulatory compliance and safety. For
pharmaceutical plants, OQs (operational qualifications) and PQs (process qualifications) for
the building and OQs for the process should have been completed and documented according
to regulations. The owner formally must take custody and control of the plant prior to
introduction of feed stock. PQs must be conducted with actual production according to
regulation in order to obtain product release.
54
Tool 3-C-1: Sample Organizational Chart (page 1 of 2)
Owner’s
Business Unit Project Manager
Manager
Contractor
Plant Manager Project Manager
Training Rep.
Supplier Rep.
Tool
Tool
Manufacturing/Operations Rep.
Construction Manager
Procurement Manager
Maintenance Rep.
Planner/Scheduler
QA/QC Manager
Startup Manager
Plant Manager
Supplier Rep.
Estimator
Num. Activity Title
1-A Ensure Sr. Mgmt. Commitment R/A C C I
Tool
Tool
Owner Project
Manufacturing/Operations Rep.
Construction Manager
Procurement Manager
Maintenance Rep.
Planner/Scheduler
QA/QC Manager
Startup Manager
Plant Manager
Supplier Rep.
Estimator
Num. Activity Title
4-A SU Issues in Team-Building A R R C
4-B Assess SU Effects from Changes A C R C C
4-C Supplier Field Support of SU I A R C C
4-D Include SU in CPM Schedule I C A C R
4-E Plan for Startup QA/QC I A C C C R
4-F Refine Team Org. Plan & Resp. A C R C
4-G Additional O&M Input A R R R I
4-H SU Sys. Numbers on Eng. Deliv. I A C R
4-I Refine SU Risk Assessment I C A R C C
4-J Plan & Start Operator Training A R R R C I
4-K Develop SU Spare Parts Plan I C C A C R R
4-L Develop System Turnover Plan I I A C R
4-M SU Procedures, Process Safety I C A R I
4-N Refine SU Budget and Schedule A C R C C R R
4-O Update SU Execution Plan I I C A R C I
Manufacturing/Operations Rep.
Construction Manager
Procurement Manager
Maintenance Rep.
Planner/Scheduler
QA/QC Manager
Startup Manager
Plant Manager
Supplier Rep.
Estimator
Num. Activity Title
6-A Finalize SU Execution Plan I C R I A C R C C
6-B Conduct Const.-SU Team Building A I C R R C I
6-C Refine SU Integrated CPM C C A C C R
6-D Continue Operator Training I I C C A R
6-E Implement Field QA/QC Plan I C A C C R I
6-F Finalize SU Risk Assessment C C I R A C R C C
6-G Transition to Systems-Based Ex. A C R R R I
A - Accountability 2 19 0 1 0 21 0 0 0 0 0 0 0 0
C - Consult 1 8 4 18 8 5 7 15 1 2 5 8 3 2
I - Inform 5 13 13 5 1 0 0 0 0 1 1 16 0 1
Tool
Phase 3: Front-End Engineering
A system is a composite assembly of piping, vessels, equipment, and instruments which can
be defined as having a singular purpose. Systems need to be identified in order to facilitate the
precommissioning, commissioning, and initial startup of the facility. Systems are commissioned
in a specific sequence, as required, by the process and unit operations.
It is suggested that operations personnel, under the direction of the Project Engineer, use
“Approved for Design” P&IDs to identify systems and the sequence in which they will be
commissioned. Systems are defined and can be shown on P&IDs and assigned a unique system
number. When defining systems, attention should be given to the ability to isolate the system
from other parts of the process so that interdependence of the systems is minimized.
This information is from CII Education Module EM-7, Construction Planning for Startup,
1993.
60
Tool 3-E-1: Integrated Flowchart for P&ID Development Process (page 1 of 2)
Legend
O D D = P&ID Development = P&ID Information
Prepare Scope Receive Owner Develop AFO Stage Input
S Interm.
of Work AFP P&ID to Draft AFD
Supplier = P&ID Development = P&ID-Related
Input Milestone Activity
O D X
Process = P&ID Development O = Owner S = Supplier
Flow Develop P&ID Develop Draft O D = Designer C = Constructor
O/D Activity &
Diagram Schedule Reqt. AFM P&ID D
O S Multi-Disc. Reponsible Team O/D = Owner/Designer
Modify AFM Hazard/Safety Input
O Prelim. D to Draft AFO Revw • Piping/
• Control O
O Supplier O Mech.
Concept Collect Prelim. Conduct C
Input • Elect/ Issue AFD
• Interlock P&ID Input Owner Review
D D Receive Owner
Owner Instrum. P&ID for
Req’ts Collect AFC P&ID
Proj. Issue Draft • Struct. Detailed Design D
• Std. Dwgs. O Hazard/Safety
D Team AFO for • Geotech.
& Symbols Comments
Collect Prelim. Input Owner Review D Detailed Disc.
Issue AFM P&ID
• Piping/Mech.
D
P&ID Internally Receive AFD
• Eqpt. List O • Equipment Engrg. D • Elect. & Modify AFC
• Piping Spec. Multi-Discip. O for Detailed
• Piping & Ducts Check- Instrum. to AFS
• Vendor Review Modify Draft Design
• Instrument. lists Conduct • Struct.
Packages • Owner AFD to Satisfy • Geotech.
C
• Elec. Req’ts (Optional) Owner Review
• Eng’g Stds. D O Hazard/Safety D * Field
• Special Req’ts • Dgn Team
- Piping Review Changes
• Eqpt. & Mech. D Expert, Review Owner Modify AFD
- HVAC Supports D Draft to D O/D
- Elect. • Prelim. Safety or
P&ID
& Environ. P&ID Collect Owner O/D Match Detailed Material Pre-Startup
- Instrum. Check- Design Results
O • Construct. Revw Comments Pre-Detailed Quantity Revw
- Insul’n lists
Issue Draft • Plant Op/Main Check- Design Review Takeoff
- Fire Prot.
P&ID Internal • Research lists • Plant Op/Main O/D D
D
Review • Construct. Pre-Construct. S Modify P&IDs
Modify Draft Final
D Review to Incorporate
AFO to Supplier
O Comments
Collect Multi- Incorporate D Input
Collect Internal Discipline Owner D
Modify Draft D
Comments Comments Comments Complete
AFD to AFD Issue AFS
AFC P&ID
to Owner
O D
O D O O O O
Approval for Approval of Approval of Approval of Approval of Start
AFP P&ID AFM P&ID AFO P&ID AFD P&ID AFC P&ID Operation
Approval for Approval for Approval for Approval for Approval for Approval for
Preliminary Multi-Discipline Owner Detailed Design Construction Startup &
Review Stage Review Stage Review Stage Stage Stage Operation Stage
61
Tool
Phase 3: Front-End Engineering
The flowchart on page 1 of this tool is presented as a startup planning tool supportive of
planning activity 3-E: Acquire Operations & Maintenance Input. As discussed in activity profile
3-E, this activity is very important to startup planning. Use of the flow chart, along with the
checklist provided in tool 3-E-2, can significantly increase the efficiency and thoroughness of
input and reviews by operations and maintenance personnel.
The P&ID flowchart is taken from work from a previous CII research team and two of its
publications (CII Research Summary 47-1, Piping: Improving P&IDs, Supplier Data, and
Packaged Units; and Implementation Resource 47-2, Tools for Enhancing the Piping Engineering
Process). Use these documents for additional background on the development and detailed use
of the flowchart.
The three-letter acronyms associated with each milestone on the P&ID flowchart are
derived from the milestones themselves (e.g., AFD: Approved for Detailed Design). These
abbreviations are also listed in the glossary of this document.
Tool
62
Tool 3-E-2: P&ID Checklist of Information Elements (page 1 of 6)
P&ID Development Technical Review P&ID Dwg. No.: CADD File No.:
Checklist Acceptance Status (Circle One): Yes, No If No, Total No. of Deviations: ___
P&ID Title: Originator: Auditor: Check Date:
Project Name: P&ID Type (Circle One): Process, Utility, Auxiliary Rev. Date:
P&ID Development Stage (Circle One) P&ID Technical Information Elements Acceptance Status:
(1) (2) (3) (4) (5) (6) Yes/ No. of
AFP AFM AFO AFD AFC AFS No Deviations:___
• : Recommended time to freeze an element A. Equipment
• 1. Symbol representing each type of item on the equipment list
• 2. Equipment names are shown and match the equipment list
• 3. Equipment numbers are shown and match the equipment list
• 4. Drivers as required
• 5. Installed spares
Tool
Tool
P&ID Development Technical Review P&ID Dwg. No.: CADD File No.:
Checklist Acceptance Status (Circle One): Yes, No If No, Total No. of Deviations: ___
P&ID Title: Originator: Auditor: Check Date:
Project Name: P&ID Type (Circle One): Process, Utility, Auxiliary Rev. Date:
P&ID Development Stage (Circle One) P&ID Technical Information Elements Acceptance Status:
(1) (2) (3) (4) (5) (6) Yes/ No. of
AFP AFM AFO AFD AFC AFS No Deviations:___
• : Recommended time to freeze an element A. Equipment (continued)
• 9. Number of sections/elements for equipment such as air cooled
exchangers, cooling towers, etc.
• 10. Number and relative location of flow connections external to
the equipment, such as lube oil, seal flush, side draws, cooling
water for inter-coolers and lube oil coolers, bypass, drains, etc.
• 11. Vendor package designations
• 12. Vendor details as required
• 13. Pump seal flush schematics
• 14. Bearing lube systems
Tool 3-E-2: P&ID Checklist of Information Elements (page 3 of 6)
P&ID Development Technical Review P&ID Dwg. No.: CADD File No.:
Checklist Acceptance Status (Circle One): Yes, No If No, Total No. of Deviations: ___
P&ID Title: Originator: Auditor: Check Date:
Project Name: P&ID Type (Circle One): Process, Utility, Auxiliary Rev. Date:
P&ID Development Stage (Circle One) P&ID Technical Information Elements Acceptance Status:
(1) (2) (3) (4) (5) (6) Yes/ No. of
AFP AFM AFO AFD AFC AFS No Deviations:___
• : Recommended time to freeze an element B. Pipe Lines
• 1. Line sizes
• 2. Line specification
• 3. Line numbers
• 4. Tie-in designations
• 5. Paint specification
Tool
Tool
P&ID Development Technical Review P&ID Dwg. No.: CADD File No.:
Checklist Acceptance Status (Circle One): Yes, No If No, Total No. of Deviations: ___
P&ID Title: Originator: Auditor: Check Date:
Project Name: P&ID Type (Circle One): Process, Utility, Auxiliary Rev. Date:
P&ID Development Stage (Circle One) P&ID Technical Information Elements Acceptance Status:
(1) (2) (3) (4) (5) (6) Yes/ No. of
AFP AFM AFO AFD AFC AFS No Deviations:___
• : Recommended time to freeze an element D. Instrumentation
• 1. Primary control function
• 2. Panel, local, PLC or DCS designations
• 3. Alarm and shutdown requirement
• 4. Instrumentation and control hardware
• 5. Instrument numbers
• 6. Failure positions, where applicable
• 7. Bridles/manifolds
• 8. Control valve bypasses designated
• 9. Instrument isolation valve locations
Tool 3-E-2: P&ID Checklist of Information Elements (page 5 of 6)
P&ID Development Technical Review P&ID Dwg. No.: CADD File No.:
Checklist Acceptance Status (Circle One): Yes, No If No, Total No. of Deviations: ___
P&ID Title: Originator: Auditor: Check Date:
Project Name: P&ID Type (Circle One): Process, Utility, Auxiliary Rev. Date:
P&ID Development Stage (Circle One) P&ID Technical Information Elements Acceptance Status:
(1) (2) (3) (4) (5) (6) Yes/ No. of
AFP AFM AFO AFD AFC AFS No Deviations:___
• : Recommended time to freeze an element E. Safety Systems
• 1. Pressure controlled vents and safety relief valves; rupture discs
• 2. Discharge designation of relief devices, e.g., atmosphere, high
pressure flare header, etc.
• 3. Back flow preventors, flame arrestors, safety showers
• 4. Emergency interlocks
• 4. Sample systems
Tool
Tool
P&ID Development Technical Review P&ID Dwg. No.: CADD File No.:
Checklist Acceptance Status (Circle One): Yes, No If No, Total No. of Deviations: ___
P&ID Title: Originator: Auditor: Check Date:
Project Name: P&ID Type (Circle One): Process, Utility, Auxiliary Rev. Date:
P&ID Development Stage (Circle One) P&ID Technical Information Elements Acceptance Status:
(1) (2) (3) (4) (5) (6) Yes/ No. of
AFP AFM AFO AFD AFC AFS No Deviations:___
• : Recommended time to freeze an element H. Special Notations
• 1. Discharge designations for drains and vents, e.g., open drain,
closed drain, process drain, storm drain, atmosphere, etc.
• 2. Miscellaneous notes, such as normally open / closed, car seal
open/closed, free drainage line, low point drain, high point vent,
drop out spool piece, minimum distance, construction strainers
• 3. Seal leg requirements
• 4. Critical elevations, e.g. vessel elevation relative to pump centerline
• 5. Discipline design details as required
B Process Technology
1 degree of definition
Note: This checklist is not all-inclusive, but is intended primarily to stimulate discussion.
Tool
Tool
D Hazardous Materials/Processes
1 hazardous chemicals
2 explosive reactions
3 inherent safety hazards
4 likelihood of spills, emmisions
5 plant preparedness
6 community preparedness
7 RMP/PSM system adequacy & confidence
8 health risk monitoring
9 separation between processes
10 emergency response plan
11 other:
Note: This checklist is not all-inclusive, but is intended primarily to stimulate discussion.
Tool 3-F: Startup Risk Assessment Checklist (page 3 of 3)
Risk Assessment Not
# Risk Issues Low Med. High Uncertain Applicable Comments
E Quality of Startup Planning
1 application of quality gates
2 quality of Startup Execution Plan
3 availability of startup spares
4 training challenges and needs
5 other:
F Project Schedule
1 realistic schedule durations
2 long lead procurement
3 past performance of contractor
4 permitting delays
5 environmental compliance delays
6 effect of incentives
7 labor prob./coll. bargaining agreemt
8 other:
G Existing Plant/Site
1 adequacy of utilities
2 interfaces with existing systems
Note: This checklist is not all-inclusive, but is intended primarily to stimulate discussion.
Tool
Tool
Note: This checklist is not all-inclusive, but is intended primarily to stimulate discussion.
Tool 3-I: Checklist of Typical Startup Activities (page 1 of 7)
Description A B C D E
1.0 Towers, Drums, and Heat Exchangers
1.1 Cure and dry out cement linings
1.2 Install all tower and drum internals
1.3 Clean out all vessels and open manholes and other openings for final inspection by Owner’s startup crew.
1.4 Inspect towers and drums after final cleaning
1.5 Head up vessels after inspections, etc., when such activities must be completed:
1.5.1 Prior to startup
1.5.2 After startup
1.6 Perform cold hydrostatic or pneumatic test as directed by Owner.
3.0 Pumps
3.1 Set and align pumps and driver for cold operation. Furnish record of alignment.
Responsibility Codes:
Mechanical Completion: A = Subcontractor Responsibility, B = Subcontractor/Owner Responsibility
73
Tool
Tool
Description A B C D E
3.4 Remove all rust preventatives, oil, grease, etc. used to preserve the equipment during construction.
3.5 Install proper lubrications after review with the Owner. Lubricants to be supplied by the Owner.
3.6 Install temporary packing (if permanent packing is not suitable for flushing).
3.7 Make final check of cold alignment after flushing.
3.8 Make piping correction prior to run-ins (as required to obtain proper alignment and couple pumps).
3.9 Check and run-in all the pumps; maintain them after turnover. and do any required doweling of the pumps and
drivers.
3.10 Make final hot alignment check.
Responsibility Codes:
Mechanical Completion: A = Subcontractor Responsibility, B = Subcontractor/Owner Responsibility
Startup Operations by Owner: C = Subcontractor Responsibility, D = Subcontractor/Owner Responsibility, E = Not Applicable
Tool 3-I: Checklist of Typical Startup Activities (page 3 of 7)
Description A B C D E
5.0 Compressors, Expanders, and Generators
5.1 Install all equipment and make piping corrections (as required to obtain proper alignment). Assist Owner as
required to obtain proper alignment.
5.2 Maintain the equipment up to the time the unit or section is turned over to the Owner.
5.3 Turn over compressor, suction piping, interstage piping, lube and seal oil piping, in clean condition (free of mill
scale, weld spatter, and all loose and foreign material).
5.4 Install necessary lubricants (furnished by Owner).
5.5 Check and run-in the compressors on air; maintain them after turnover; and do any required doweling of the
compressors and drivers.
5.6 Make hot alignment of compressors.
5.7 Correct any piping alignment or deficiency which may be necessary after the run-in of the compressors.
5.8 Make comprehensive vibration check of rotating elements and ancillary equipment.
Responsibility Codes:
Mechanical Completion: A = Subcontractor Responsibility, B = Subcontractor/Owner Responsibility
Startup Operations by Owner: C = Subcontractor Responsibility, D = Subcontractor/Owner Responsibility, E = Not Applicable
75
Tool
Tool
Responsibility Codes:
Mechanical Completion: A = Subcontractor Responsibility, B = Subcontractor/Owner Responsibility
Startup Operations by Owner: C = Subcontractor Responsibility, D = Subcontractor/Owner Responsibility, E = Not Applicable
Tool 3-I: Checklist of Typical Startup Activities (page 5 of 7)
Description A B C D E
9.0 Piping
9.1 Hydrostatically or pneumatically test and clean all piping as required by drawings, specifications, and good
practices.
9.2 Provided and install all strainers (both temporary and permanent), figure-eight blanks, temporary blanks, and
spool piece called for on drawings and specifications.
9.3 Re-pack and grease valves (where necessary).
9.4 Supply supervised labor and necessary tools to break flanges, drop out control vales and spool pieces, and install
temporary blanks and piping connection for final flushing of piping and equipment.
9.5 Provide suitable temporary hose connections, blind, and dummy spools (as required) for flushing.
9.6 Supply personnel and supervision (as required) for final flushing.
9.7 Clean temporary strainers (if necessary) during the flushing operations.
9.8 Remove the strainers from the piping when no longer required.
9.9 Supply supervised labor for the hot bolting of piping and equipment during the initial plant startup.
9.10 Provide adequate marking to identify steam or heat tracing take-off valves.
9.11 Supply and install line identification tags and signs. Stencil lines fro identification.
Responsibility Codes:
Mechanical Completion: A = Subcontractor Responsibility, B = Subcontractor/Owner Responsibility
Startup Operations by Owner: C = Subcontractor Responsibility, D = Subcontractor/Owner Responsibility, E = Not Applicable
77
Tool
Tool
Description A B C D E
11.0 Electrical
11.1 Remove all rust preventatives, oil, grease, etc. used to preserve equipment during construction.
11.2 Install necessary lubricants (furnished by Owner).
11.3 Check condition of grease in grease-lubricated motor and generator bearings.
11.4 Energize substations and circuits (as mutually agreed by Contractor and Owner) after completion of field tests
of wiring and electrical equipment, in accordance with recognized standards and codes. Such tests are to
include measuring of liquid insulation dielectric strengths and equipment dielectric absorption ratios,
insulation resistance, grounding resistance, and testing and adjusting of relays.
11.5 Owner shall issue permits to Contractor for carrying out checks on electrical equipment after electrical
facilities are energized.
11.6 Calibrate and set relays on all circuit breakers. Set time delays. Check protection systems for all equipment.
11.7 Check operability of emergency and instrument power systems (as mutually agreed).
11.8 Assume all responsibility for electrical facilities which are energized.
12.0 Instrumentation
12.1 Perform required pressure tests on instrument take-off piping and air piping and tubing.
12.2 Check continuity and identification of transmission and control systems for each instrument to ensure proper
hook-up. This applies to both pneumatic and electrical systems.
Responsibility Codes:
Mechanical Completion: A = Subcontractor Responsibility, B = Subcontractor/Owner Responsibility
Startup Operations by Owner: C = Subcontractor Responsibility, D = Subcontractor/Owner Responsibility, E = Not Applicable
Tool 3-I: Checklist of Typical Startup Activities (page 7 of 7)
Description A B C D E
12.3 Calibrate all instruments (except temperature and pressure gauges) and synchronize transmitter and receiver
readings for each instrument.
12.4 Calibrate temperature and pressure gauges.
12.5 Install all pressure and temperature gauges.
12.6 Re-install all control valves after line flushing and check each valve for proper operation (i.e. travel, action with
air failure, etc.).
12.7 Install all orifice plates after flushing and/or air blowing.
12.8 Provide and install sealing fluids (where required).
13.0 General
13.1 Make inspection of plant to check conformity to flow diagrams and construction drawings.
13.2 Inspection required by governmental agencies and/or insurance companies.
13.3 Inspection of plant tie-in points to existing plant according to schedule provided by Contractor .
13.4 Arrange for visits of suppliers’ field service engineers:
13.4.1 Prior to startup
13.4.2 After startup
13.5 Removal of temporary facilities (to a mutually agreed upon degree).
13.6 Clean up of plant areas (to a mutually agreed upon degree).
Responsibility Codes:
Mechanical Completion: A = Subcontractor Responsibility, B = Subcontractor/Owner Responsibility
Startup Operations by Owner: C = Subcontractor Responsibility, D = Subcontractor/Owner Responsibility, E = Not Applicable
79
Tool
Phase 4: Front-End Engineering
81
Phase 4: Front-End Engineering
82
Phase 4: Front-End Engineering
83
Phase 4: Front-End Engineering
84
Phase 4: Front-End Engineering
85
Phase 4: Front-End Engineering
86
Phase 4: Front-End Engineering
87
Phase 4: Front-End Engineering
88
Phase 4: Front-End Engineering
92
Phase 4: Front-End Engineering
93
Phase 4: Front-End Engineering
94
Phase 4: Front-End Engineering
95
Tool
Tool
2. Demonstrated Performance at Rated Capacity (if feasible)
• Safety requirements addressed
• Quality
• Quantity
• Process stability
• Documentation complete
97
Phase 4: Front-End Engineering
5. Verification that overall dimensions and mounting surfaces are consistent with approval
drawings such that items can be brought into the building and set as intended.
6. Verification of outstanding provisions of order:
• Release for shipment procedure understood
• Confirmation of shipping date and method
Tool
98
Phase 4: Front-End Engineering
Tool
Outside Battery Limits Process Systems
System Number System Definition Scheduled Completion Date
201 Misc. Structural Supports
202/203 Misc. Concrete & Paving
204 Lighting
209 Grounding
99
Phase 4: Front-End Engineering
100
Phase 4: Front-End Engineering
NOTE: Generic Systems marked with asterisk (*) are common to both the ISBL and OSBL Areas.
Tool
101
Phase 4: Front-End Engineering
503 Firewater
504 Electric Power
505 Instrument Air/Plant Air/Starting Air
506 DCS and Control Room
507 Cooling Water System
508 Boiler Feed Water Treatment & Supply
509 Steam System
510 Condensate System
Support Systems – 600 series: Complete 601 first and 609 last, others as available
601 Flare System & Atmospheric Vents
602 Process Hydrocarbon Drains
603 Glycol System
604 Amine System
605 Amine Drains
606 Refrigeration System
607 Hot Oil System
608 Fuel Gas System
609 Methanol System
102
Phase 4: Front-End Engineering
Main Operating Systems – 700 series: All Systems to be complete before startup
701 Feed Bypass to Produce
702 De-ethanizer Feed
703 De-ethanizer
704 Ethane Treatment & Export
705 Depropanizer
706 Debutanizer
707 De-isobutanizer
708 Storage, Rerun & Export
709 Analyzers & Meters
Instructions for commissioning and startup are normally provided by equipment manufactures
for each piece of tag number equipment. The manufacturer’s instructions should be studied and
followed carefully before the initial run-in of the equipment otherwise their warranties may be
Tool
void. Some of the equipment will be commissioned with the manufactures representative
assisting the operating crew.
The guidelines contained herein are intended to supplement the manufacturers instruction
and the owners safety and operating practices.
501. Storm Water Drains: Required to keep the plant area dry for construction and
to handle the post-hydrotest flush water. Pump-out pump can be of a
temporary nature until the permanent pumps and power supply and installed
and commissioned. The permanent pumps should be commissioned and
placed in automatic mode as soon as possible. A temporary discharge header
should be installed if the permanent piping is not available.
103
Phase 4: Front-End Engineering
Also required for a communications center during the critical startup operations.
104
Phase 4: Front-End Engineering
Tool
package. After thoroughly cleaning the BFW storage tank, the tank and system
should be flushed with city water and drained. The softening and chemical
treatment systems should be loaded with the proper resins and chemicals.
Begin to make treated water and thoroughly rinse the storage tank, de-aerator and piping
system. Circulate the water through as much of the system as possible and take water samples
to adjust the chemical recipe to the supplier’s specifications.
105
Phase 4: Front-End Engineering
steam, the condensate should be wasted to drain until samples prove that the
system is clean.
601. Flare and Vents Systems: This system includes all of the PSVs and their relief
lines. Spillback relief valves and piping are also included, but some of them
may be internal to the equipment or included in packaged equipment. Each
relief valve is tested and set before installation. There is never any reason to
change these settings for commissioning or startup.
106
Phase 4: Front-End Engineering
Tool
After construction is complete, the drains should be flushed again to remove
debris. The API separator should be checked for debris also.
603. Glycol System: Check and flush out this package system thoroughly. Rinse the
system with condensate and blow with instrument air. Flow dry air through
the system until dry. When ready, prepare the system for operation and fill
with glycol to operating levels. Circulate glycol through the system and filters
using temporary connections as required. Heat the glycol with hot oil and vent
off the moisture through the glycol regenerator overhead line. Remove any
temporary connection before start-up on feed.
107
Phase 4: Front-End Engineering
installed piping by first flushing after hydrotest, then blowing down with dry
instrument air and finally by flowing hot nitrogen until no moisture is present.
Make up the skid connections and continue the nitrogen purge until ready to
operate. When ready, introduce the propane refrigerant and sweep the piping
out to the flare. Continue the sweep purge until the nitrogen is removed.
Pressure up the system and initiate operation according to the manufactures
recommendations. Vent inert collect in the refrigerant accumulator to flare.
108
Phase 4: Front-End Engineering
Tool
should be made with full knowledge of the existing conditions and the required
safety precautions which must be taken.
Flush the fuel gas piping thoroughly and drain. Pressure with instrument air
and leak check. Blow down low point drains to eliminate as much water as
possible. Confirm that the flare system is ready to operate and that hot work
has been reduced to a controllable minimum.
Prior to operation, hold safety meetings with the construction forces and
operations personnel to inform everyone on site of necessary changes in work
procedures and increased safety awareness. With agreement of all on-site
parties as to the construction, startup and operational procedures to ensure
plant and personnel safety, the fuel gas system can now be charged.
109
Phase 4: Front-End Engineering
• All users not ready for fuel gas should be blinded with vents downstream.
All of the main process systems must be completed and turned over to Operations before feed
can be introduced into the process. By this time, all systems have been hydrotested, flushed,
Tool
flanges made up, leak tested, and blown down. All in-line instruments must be installed and
thoroughly tested and verified that the control room readouts are correct. These commissioning
procedures may proceed through the main process systems on a system by system basis. At the
end of the commissioning process, the entire plant should be leak tested and purged with
nitrogen. By this time, the exception lists should be down to a few inconsequential items which
can be safely completed while the plant is operating.
110
Phase 4: Front-End Engineering
Tool
709. Analyzers and Meters
After all systems are complete, it is appropriate to hold another series of safety meetings with
all site personnel before bringing in the feed.
111
Phase 4: Front-End Engineering
Build a liquid level in the de-ethanizer reflux drum and start a reflux pump to
flow liquid back to the de-ethanizer. Continue operating in this mode until
normal liquid levels are achieved in the de-ethanizer system. Adjust the
pressure controls to flow C2 vapor to the amine and glycol systems and on to
the ethane surge drum. Vent off any nitrogen to flare and continue flowing
ethane until a normal liquid level has been achieved. Take samples of the liquid
before operating the ethane product pumps. When pipeline quality has been
achieved, the pumps can be started and ethane can flow to the pipeline.
112
Phase 4: Front-End Engineering
Tool
the gasoline product is made in quantity, it can be circulated back to the front
end of the process and heat integration can be achieved.
4. Initial Operation: The plant is now in the initial operations phase. Confirm
that all utility systems and support systems are operating and ready to continue
feed introduction. Confirm that at least one pump or compressor of each
system is operating or on spillback. Take special precautions to ensure that the
liquid inventory in each of the towers is within normal range. Make process
control moves slowly and maintain pressures in their normal ranges. It will
take some time to achieve steady operating temperatures because of the many
process moves and the front-end heat integration.
Confirm the plant performance by taking an orderly series of gas and liquid
samples for analysis and reporting the constituents. Make adjustments to the
process to bring the product analysis into range as required.
113
Phase 4: Front-End Engineering
114
Phase 4: Front-End Engineering
3. Process Information
3.1. Process Description
3.2. Flow Diagrams
3.3. Process Chemistry
Tool
4. Equipment Information
4.1. P&IDs and Drawing Lists
4.2. Equipment Lists and Specifications
4.3. Instrumentation
4.4. Piping
5. Operating Procedures
5.1. Unit Operations
5.1.1. Commissioning
5.1.2. Initial Startup
5.1.3. Unit Ramup
5.1.4. Normal Operations
5.1.5. Emergency Shutdown
5.1.5.1. Process Shutdown
5.1.5.2. Power Outage
5.1.5.3. Loss of Containment
5.1.5.4. Loss of Signal
5.1.5.5. Fire
5.1.6. Interim Startup
5.1.7. Normal Shutdown
115
Phase 4: Front-End Engineering
6. Equipment Integrity
6.1. Equipment Listing and Spare Parts
6.2. Equipment Inspections and Testing
6.3. Maintenance Work Procedures
6.4. Non-Routine Work Procedures
6.5. Quality Control
6.6. Maintenance Training
7. Contractor Procedures
7.1. Evaluation and Approval of Contractors
7.2. Communications and Training
Tool
8. Emergency Preparedness
8.1. Process Description
8.2. Safety and Health Considerations
8.3. Leak Detection
8.4. Emergency Response
8.5. Evacuation Detailed
8.6. Incident Command
8.7. Emergency Call Out Procedures
9. Compliance Audits
9.1. Audit Responsibility
9.2. Audit Method
9.3. Audit Team
9.4. Documentation and Follow-up
116
Phase 4: Front-End Engineering
Tool
117
Phase 4: Front-End Engineering
3.0 Civil
3.1 Soils reports and Proctor analysis sheets
3.2 Soils compaction test report log, soils density test reports
3.3 Concrete test reports
3.4 Completed QC checklists
3.5 Completed punchlists
5.0 Buildings
5.1 Building inspector’s acceptance certificate
5.2 Completed punchlists
5.3 Reline as built drawings
118
Phase 4: Front-End Engineering
Tool
10. Complex loop description — if applicable
11. Motor schematic — if applicable
12. Loop acceptance form/checklist
13. Instrument installation detail
119
Phase 5: Procurement
A. Phase: Procurement
B. Key Concepts: Suppliers must be selected based on the ability to provide quality
products, deliver the products as scheduled, and support start-up activities.
C. Deliverables: A list of qualified suppliers prepared to support startup
D. Motive/Rationale: Effective suppliers and quality products will reduce field startup
problems. On-site suppliers will be able to address and remedy problems or questions
that arise during startup.
E. Responsibility: Procurement Manager
Accountability: Contractor Project Manager
Consult: Startup Manager
Inform: Planner/Scheduler, Expeditors
F. Quality Gate/Sequencing Constraints: This is not a quality gate, but must be
accomplished prior to issuance of purchase orders.
G. Basic Steps:
1. This activity should build upon the previous activities pertaining to startup
supplier support and QA/QC.
2. Visits to proposed suppliers will uncover past track records, current shop and
engineering work loads and backlogs, and capability to supply the specific items.
Critical sub-suppliers should be evaluated similarly to primary suppliers.
3. Consider the ability of suppliers to: perform partial or full pre-shipment testing
prior to delivery of equipment; stock and provide critical spare parts; train
personnel in full operation of the equipment in the field; provide complete
operating and maintenance manuals; and work effectively with sub-suppliers.
4. List all key supplier selection criteria, such as special fabrication requirements,
shipping mode capabilities, and compatibility with existing equipment.
5. Avoid negotiating a supplier into promising unachievable shipment dates. If
necessary, make sure that the project team and the supplier clearly understand
what the supplier will do differently to accomplish any early shipments and what
the project’s responsibilities are to assist the supplier in meeting these dates.
6. Consider substantial milestone payments as incentives to meet critical needs.
7. Ensure that suppliers include adequate installation and operating instructions
packed with each instrument.
H. Tools Needed/Provided: none
I. Challenges to Successful Implementation:
• Not taking the time to properly evaluate suppliers, which includes site visits.
• Low-cost bidding without thorough prequalification.
121
Phase 5: Procurement
A. Phase: Procurement
B. Key Concepts: The previously prepared startup spare parts plan should be updated
based on current information. In addition, many spare parts will require expediting
to ensure timely deliveries that support commissioning, checkout, and startup of the
project.
C. Deliverables: A spare parts procurement plan that addresses consumables, high-risk
components, and needs for expediting.
D. Motive/Rationale: Startup risks and costs will be reduced by ensuring that necessary
spare parts are available to support commissioning, checkout, and startup of the
project.
E. Responsibility: Procurement Manager
Accountability: Contractor Project Manager
Consult: Manufacturing Operations Rep., Maintenance Rep., Startup Manager
Inform: Owner Project Manager
F. Quality Gate/Sequencing Constraints: This activity is not a quality gate, but the plan
must be refined prior to the issuance of purchase orders.
G. Basic Steps:
1. Ensure that all spare parts have been ordered. Check purchase orders and spare
part summaries to determine what has actually been purchased. Review the scope
of equipment items to determine if parts may have been overlooked.
2. Work with suppliers, specialists, operations, and maintenance to identify additional
high-risk component requirements.
3. Organize an expediting report that includes individual purchase order item
numbers for tracking spare parts placed with major equipment items.
4. Ensure expediters understand the importance of expediting spare parts.
5. Prepare and issue a status report that addresses spare parts.
6. Conduct routine spare parts status meetings with the appropriate personnel.
H. Tools Needed/Provided:
Needed: a comprehensive expediting plan; expediting procedures that address spare
parts
I. Challenges to Successful Implementation:
• Not having time or experience in identifying spare parts requirements.
• Changes do not receive the same degree of attention as the base design receives.
• Spare parts are often overlooked when major equipment is shipped.
• Expediters neglect spare parts as they are perceived to be non-critical.
• Suppliers often treat spare parts as a nuisance and will not follow through without
122 expediting pressure.
Phase 5: Procurement
A. Phase: Procurement
B. Key Concepts: Implementation of the QA/QC plan developed in 4-E (Plan for Startup
QA/QC) during this phase will insure awareness and conformance to QA/QC
standards and will subsequently lead to a more successful facility startup.
C. Deliverables: Execution of QA/QC activities during procurement with the ultimate
achievement of having the correct materials on-site.
D. Motive/Rationale: Implementation of the final QA/QC plan at the procurement and
pre-shipment stage of the project will insure that the QA/QC requirements are
incorporated into procurement activities, thereby leading to a more successful startup.
E. Responsibility: QA/QC Manager
Accountability: Contractor Project Manager
Consult: Startup Manager
Inform: Procurement Manager, Suppliers
F. Quality Gate/Sequencing Constraints: This activity is not a quality gate.
G. Basic Steps:
1. Activity 4-E is the point of departure for this step. QA/QC requirements must be
included within each bid solicitation package so suppliers will know the requirements
prior to execution of a contract or purchase order.
2. Suppliers’ QA/QC procedures should be coordinated with those of the project to
identify any inconsistencies.
3. Sub-suppliers must conform to the same QA/QC requirements that suppliers do.
H. Tools Needed/Provided:
Needed: QA/QC sign off procedures, testing and inspection procedures, non-
conformance corrective plan, acceptance procedures, packaging and shipping
procedures
I. Challenges to Successful Implementation:
• Lack of well-defined technical performance criteria.
• Lack of a well-defined testing and acceptance plan.
• Allowing low initial cost to influence procurement strategies.
• Delay in procurement schedule subsequently resulting in a less than desired focus
on QA/QC requirements prior to shipment.
123
Phase 6: Construction
A. Phase: Construction
B. Key Concepts: Final modification and review of the Startup Execution Plan should
occur prior to full implementation in order to ensure startup success.
C. Deliverables: Final Startup Execution Plan, which identifies all resources, strategies,
and contingencies pertaining to the introduction of feedstocks, performance testing,
and documentation preparation. This plan should also highlight areas where definition
may be lacking and activities where resources are particularly critical to success. It
should also address outstanding punchlist items.
D. Motive/Rationale: To insure that all salient project developments that have occurred
to date are adequately addressed in the Startup Execution Plan. Without proper
planning, the risks and costs of failure beyond this point are high.
E. Responsibility: Manufacturing Operations Representative, Startup Manager
Accountability: Contractor Project Manager
Consult: Owner Project Manager, Construction Manager, Planner/Scheduler, Suppliers
Inform: Business Unit Manager, Maintenance Representative
F. Quality Gate/Sequencing Constraints: This should be treated as a quality gate,
occurring prior to the transition from discipline-based management to systems-based
management.
G. Basic Steps:
1. Review all significant project developments since the last update of the Startup
Execution Plan (Activity 4-O), particularly developments pertaining to suppliers,
spare parts, QA/QC, expediting, and construction plans and progress.
2. Expand and update the Startup Execution Plan as appropriate or needed.
3. Finalize the checkout/commissioning plan, the plan for initial operations, and the
plan for the introduction of feedstocks.
4. Finalize project-specific procedures and responsibilities for problem identification
and resolution during turnover, commissioning, and initial operations.
5. Review and discuss salient components of the revised plan with all appropriate
personnel. Revisit resource needs and allocations.
6. Make any necessary final modifications to the plan and issue as the Final Startup
Execution Plan.
H. Tools Needed/Provided:
I. Challenges to Successful Implementation:
• The updating of plans is often undervalued, and thus neglected.
125
Phase 6: Construction
A. Phase: Construction
B. Key Concepts: The construction-startup transition can be greatly improved with
team-building activities.
C. Deliverables: An execution team that fully supports startup plans and systems-based
concept during construction.
D. Motive/Rationale: Construction commitment to a successful startup can result from
team-building activities.
E. Responsibility: Contractor Project Manager, Construction Manager
Accountability: Owner Project Manager
Consult: Maintenance Representative, Startup Manager, Team-Building Facilitator
Inform: Manufacturing Operations Representative, Planner/Scheduler
F. Quality Gate/Sequencing Constraints: This is not a quality gate, but should be
initiated shortly after award of major construction contracts.
G. Basic Steps:
1. All key construction and startup personnel must be named and in place. Choose
supervisors who support the concept of teamwork.
2. Establish open communications through all levels.
3. Involve an outside facilitator.
4. Conduct team-building sessions off-site. Identify barriers to success. Seek buy-in
into the Startup Execution Plan, especially concerning the startup objectives.
5. Concentrate on resolving problems, not placing blame. Encourage all individuals
to take an active interest in making their counterparts successful.
H. Tools Needed/Provided:
I. Challenges to Successful Implementation:
• Team building is a continuous process.
• Contracts should support team building activities.
• Team building requires one or more “time outs,” however brief.
• High concurrent time demands on personnel.
126
Phase 6: Construction
A. Phase: Construction
B. Key Concepts: As the project progresses through construction, modifications to the
schedule should reflect current construction progress.
C. Deliverables: Revised Detailed Project Schedule
D. Motive/Rationale: To provide the best possible integrated plan of project activity
based on current information.
E. Responsibility: Planner/Scheduler
Accountability: Contractor Project Manager
Consult: Owner Project Manager, Manufacturing Operations Representative, Startup
Manager, Project Team
Inform:
F. Quality Gate/Sequencing Constraints: This activity is not a Quality Gate.
G. Basic Steps:
1. Review in detail the startup responsibilities of all interface organizations and all
testing activities.
2. Review testing durations using defined system parameters. Ensure that adequate
time is allowed for checkout and commissioning. Incorporate schedule time
contingencies where justifiable.
3. Review resource loading of startup activities, supplier testing/startup support, and
contractor support for startup.
4. Evaluate any special skills required for the personnel involved in executing the
startup.
H. Tools Needed/Provided:
I. Challenges to Successful Implementation:
• Not getting information in a timely fashion
• CPM schedules that are not kept current
• Underestimates of durations
127
Phase 6: Construction
A. Phase: Construction
B. Key Concepts: The training of operations and maintenance personnel should follow
the training plan in a timely manner.
C. Deliverables: Well-trained operators and maintenance personnel who are prepared
for all the challenges they may confront.
D. Motive/Rationale: Startup success is highly dependent upon operator and maintenance
proficiency, which is only achieved through experience and/or training. Effective
operating/maintenance skills can help in avoiding costly mistakes with respect to
safety performance, environmental performance, integrity of the equipment, efficiency
of operation, product quality, waste generation, and time required to achieve project
objectives.
E. Responsibility: Startup Manager, Training Manager
Accountability: Contractor Project Manager
Consult: Manufacturing Operations Representative, Maintenance Representative
Inform: Plant Manager
F. Quality Gate/Sequencing Constraints: This activity is not a quality gate, but should
occur prior to the transition to systems-based execution.
G. Basic Steps:
1. Implement the previously developed training plan, including classroom, simulation,
and on-site activities.
2. Competency testing should be used to confirm that personnel have achieved the
minimum necessary skills prior to startup.
3. Retrain where individuals fail to demonstrate minimum proficiency as defined in
the qualification.
4. Utilize startup activities to reinforce the training (system identification, marking,
punch listing, and testing).
H. Tools Needed/Provided:
Needed: collective bargaining agreement (if applicable), training plan, startup
procedures, operations and maintenance manuals and databooks
I. Challenges to Successful Implementation:
• Lack of understanding of that minimum level of proficiency needed to operate and
maintain the process, particularly in projects involving a new technology.
• Capital constraints — training costs are often underestimated and under-funded.
• Staffing constraints; it is often difficult to find personnel with both the technical
skills and training development skills to deliver an effective program.
• Restrictive collective bargaining agreements
128
Phase 6: Construction
A. Phase: Construction
B. Key Concepts: A successful startup is predicated on the implementation of a complete
and fully defined field QA/QC plan during the construction phase.
C. Deliverables: Documented construction per the specification with all deviations
identified and corrected.
D. Motive/Rationale: To insure a successful facility startup, a QA/QC plan must be
implemented at the outset of construction, installation, and testing phases in order to
minimize quality defects and maximize startup efficiency.
E. Responsibility: QA/QC Manager
Accountability: Contractor Project Manager
Consult: Manufacturing Operations Rep., Construction Manager, Startup Manager
Inform: Owner Project Manager, Project Team
F. Quality Gate/Sequencing Constraints: This activity is not a quality gate.
G. Basic Steps:
1. Activity 4-E is the point of departure for this activity. The owner and contractor
must have agreed-upon, formal QA/QC procedures prior to the beginning of
construction. These should be organized on the basis of startup systems.
2. Detailed QA/QC requirements must be included within the scope of work for
prime contracts, purchase orders, and subcontracts.
3. Ensure that the prime contractor has a QA/QC representative on site full-time.
4. Ensure subcontractors and primary equipment suppliers have on-site QA/QC
representatives concurrent with execution of their work.
5. Field QA/QC corrective action plan should be complete with procedures.
6. Testing and acceptance sign-off documentation must be complete, communicated,
and ready for implementation.
H. Tools Needed/Provided:
Needed: QA/QC standards and regulations, QA/QC field guideline book, and owner-
approved testing and acceptance procedures
I. Challenges to Successful Implementation:
• Lack of qualified QA/QC field representatives.
• Lack of follow-through with QA/QC procedures.
• Non-conformance issues not quickly addressed.
• Delay in receipt of equipment thus forcing an accelerated installation process and
subsequently overlooking QA/QC issues.
• Owner expectations for witnessing tests are not communicated and result in
rework.
129
Phase 6: Construction
A. Phase: Construction
B. Key Concepts: The risk assessment developed during detailed design must be
reviewed, updated, and communicated to the entire project team.
C. Deliverables: A final document delineating risk potential and critical risk abatement
procedures.
D. Motive/Rationale: This is the final opportunity to mitigate risk and to assure a safe
startup through planning.
E. Responsibility: Manufacturing Operations Representative, Startup Manager
Accountability: Contractor Project Manager
Consult: Business Unit Manager, Owner Project Manager, Construction Manager,
Planner/Scheduler, Estimator
Inform: Plant Manager
F. Quality Gate/Sequencing Constraints: This activity is not a quality gate, but should
be done prior to commissioning.
G. Basic Steps:
1. This activity should build on previous activity 4-I. Any recently discovered risks
should be fully reviewed and strategies should be developed to minimize the risks.
In particular, review the following: construction progress and available resources;
changes; market issues; and QA/QC.
2. Known process risks, line flushing, passivation, system dry-out (where critical),
and system operation while other or connected systems are still under construction
must be considered.
3. Ensure closure of HAZOPS (and identification of all needs for changes).
4. Finalize plans for preventive or corrective action. Implement such action as
appropriate.
5. Update documentation.
H. Tools Needed/Provided:
Needed: pre-startup safety review procedures
I. Challenges to Successful Implementation:
• Limited availability of experienced process and manufacturing personnel.
• Assumption that the startup team “can fix it all.”
• Procrastination in addressing previously identified risks.
130
Phase 6: Construction
A. Phase: Construction
B. Key Concepts: Transition from construction in a discipline/area mode to startup
systems-based completion.
C. Deliverables: All systems ready for commissioning.
D. Motive/Rationale: While construction is a discipline- or area-based activity,
commissioning and operations are systems-based. Therefore, it is necessary to
facilitate the switch from area-based installation to startup systems-based testing and
commissioning.
E. Responsibility: Contractor Project Mgr., Construction Mgr., Startup Mgr.
Accountability: Owner Project Manager
Consult: Manufacturing Operations Representative
Inform: Planner/scheduler
F. Quality Gate/Sequencing Constraints: This activity is not a quality gate.
G. Basic Steps:
1. Use the Startup Execution Plan (Activity 4-O) and the System Turnover Plan
(Activity 4-N) as the points of departure for this activity. Review both the
construction scheduling requirements and startup sequencing requirements.
2. Assign system responsibilities to field construction craft supervision.
3. Look for opportunities to link construction testing requirements with startup
testing requirements.
4. Communicate individual system milestones and requirements to the various
construction disciplines and crews.
5. Maintain a well-kept construction punchlist that is effectively prioritized and
communicated to appropriate personnel.
6. Track construction percent completion on a systems basis (actual vs. planned).
Redirect construction forces as needed.
H. Tools Needed/Provided:
Needed: CPM-based schedule management tools available per company standards;
methods for tracking construction completion by system; forms for systems-based
punch lists.
I. Challenges to Successful Implementation:
• Construction contracts are usually awarded by discipline, not systems; thus, this
is a difficult step requiring both organizational and contractual interfaces
• Two management systems must interface
• Ineffective approaches to micro-level activity planning
• Site-based planning resources are often unavailable at this point in the project.
131
Phase 7: Checkout and Commissioning
133
Phase 7: Checkout and Commissioning
135
Tool
Tool
Tool
Tool
Tool
Tool
Tool
143
8-B: Conduct Performance Testing
144
Phase 8: Initial Operations
The Planning for Startup Model and tools were tested and evaluated
on a full-scale demonstration project. The model was applied by the
project team in planning and executing the startup. This chapter summarizes
both the experience in implementing the model and the success of the
startup.
The model was made available to the project manager late in the
project at the beginning of detail design (Phase 4 in the Startup Planning
Model). The project team followed the flow chart presented in Chapter 2
and recorded their experiences, including the ease of activity implementation
and the relative importance of the various planning activities. At the end
of the project, the project and startup managers evaluated both overall
project and startup success.
147
Implementation Case Study
Figure 3.1 illustrates the project team and its relationship with the
Planning for Startup Model. The startup manager was an operations
engineer assigned to the project team, had the primary responsibility to for
startup planning, and was the primary contact between the operations,
maintenance and construction groups. This was the first assignment for
the startup manager.
Plant
Manager
Project Operations
Project Startup Group
Manager
Manager Manager
Maintenance
Group
Contractor
148
Implementation Case Study
All plan activities in the model were judged by the project and startup
managers to be relevant and were addressed during the project. The model
proved to be an effective training and communication tool. It provided a
common vocabulary that facilitated communication within the project
team, was particularly useful in developing the Startup Execution Plan,
and provided a systematic approach to developing the documentation
necessary for executing the startup.
The most challenging aspect of the planning effort was estimating the
level of product inventory and market demand. These data were not
known until approximately 30 days prior to the actual shutdown date, and
thus delayed final completion of the Startup Execution Plan. However,
since a draft of startup activities and schedule were already in-hand,
subsequent schedule adjustments were much easier than what they would
have been had it been necessary to wait for final inventory estimates.
149
Implementation Case Study
Table 3.2. “Very Significant” Startup Planning Activities and Ease of Implementation
Relative Ease of
Activity Comments
Implementation*
Easy Moderate Difficult
3A Est. SU Objectives S
3B Dev. Startup Execution Plan P S The overall objectives, sequencing,
and priorities did not change over
the course of the project which was
key to startup success.
3C. Make Startup Team S If possible, make formal team
Assignments assignments with RACI chart.
Resource limitation prevented it for
this project.
3D. Identify Startup Systems P S System identification required
additional engineering effort.
3H. Identify Startup Procurement P S Supplier support was thoroughly
Requirements planned.
4A. Address Startup Issues in Team P
Bldg.
4C. Plan for Supplier Support S
4D. Include Startup in CPM P Resource loading not included at
Schedule this stage.
4F. Refine Startup Team S
Organization
4I. Refine Startup Risk Assess. S
150
Implementation Case Study
Table 3.2. “Very Significant” Startup Planning Activities and Ease of Implementation
Relative Ease of
Activity Comments
Implementation*
Easy Moderate Difficult
6A. Finalize Startup Execution Plan S P Operators had difficulty using the
tool product. Thoroughly review the
work product from the planning
tool with operators.
6B. Conduct Construct. Startup P
Team Bldg.
6C. Refine Startup in CPM S
Schedule
6D. Conduct O&M Training S P
6E. Implement QA/QC Plan P
6F. Finalize Startup Risk Assess. P
6G. Transition to Startup System S P
Based Execution
7B. Checkout Systems S P
7C. Commission Systems S
8A. Introduce Feedstock S
8B. Conduct Performance Testing S
The startup was successful with a computed Startup Success Index for the project of 0.81
(on a 1.00 scale, where 1.00 is most successful). The primary factor affecting the success was
the achievement of the production capacity goals. An equipment failure delayed the startup
schedule by one week, but product deliveries were not affected. Table 3.3 summarizes the levels
of satisfaction and relative importance for the criteria for startup success.
With respect to implementation lessons learned, early buy-in to the model is critical to its
effective use. To facilitate acceptance, implementers should consider an early Startup Planning
Model training session with all members of the project team. The team should customize model
nomenclature to be consistent with the company’s organization and work processes in order to
increase understanding and acceptance.
151
Implementation Case Study
Relative Weight or
Startup Success Criterion Level of Satisfaction
Importance to Outcome
Product Quality Very Satisfied Product quality goals were Above Average
Performance consistently met. Importance
Product Quantity Very Satisfied Production rates met project Most Important
Performance goals.
Schedule Performance Satisfied The startup duration was as Above Average
planned but meeting the Importance
schedule required extra
levels of labor.
Safety Performance Extremely The startup had no Above Average
Satisfied reportable incidents and Importance
only a minor number of
incidents requiring some
type of medical attention.
Environmental Extremely There were no reportable Above Average
Performance Satisfied releases or spills during Importance
startup.
Operations Team Very Satisfied Operations Team was more Average Importance
Performance than adequately prepared for
plant operations challenges
Impact on On-going Satisfied There were no unanticipated Above Average
Operations impacts on on-going Importance
operations.
Level of Effort Required Satisfied startup work hours were on Above Average
by the Start Up Team budget. Level of stress was Importance
typical.
152
Appendix A
Glossary of Startup Terms
AFC Approved for construction (see P&ID tools 3-E-1 and 3-E-2).
AFD Approved for detailed design (see P&ID tools 3-E-1 and 3-E-2).
AFM Approved for multi-discipline review (see P&ID tools 3-E-1 and 3-
E-2).
AFO Approved for owner review (see P&ID tools 3-E-1 and 3-E-2).
AFP Approved for preliminary review (see P&ID tools 3-E-1 and 3-E-2).
AFS Approved for Startup and operations (see P&ID tools 3-E-1 and 3-
E-2).
EPC Engineering/Procurement/Construction
153
Appendix A: Glossary of Startup Terms
Initial Operations The point in time when feedstocks are introduced and
first product is made.
Punchlist A list of action items developed near the end of a project that
must be completed prior to the constructor turning over a project to
the owner. Critical punchlist items must be completed before the unit
may be started. Non-critical punchlist items can be completed post-
Startup.
154
Appendix A: Glossary of Startup Terms
155
Appendix B
References
O’Connor, James T., McLeod, John S., and Graebe, Garrick B.,
“Planning for the Startup of Industrial Facilities,” Research
Report to the Construction Industry Institute, The University of
Texas at Austin (in press).
157
Planning for Startup Research Team
* Principal author