Status Man Power Update
Status Man Power Update
Status Man Power Update
Senin, 21-9-20
No Jenis pekerjaan Status Pekerjaan Status Drawing Status Material Peralatan Pendukung Durasi Qtty Remarks
Man Power
2 Instalasi Main Supply IHB level 1 Very Urgent Approve Onsite N/A N/A 2
3 Instalasi Inergen Alarm Switch Room Very Urgent Approve Onsite Scaffolding 2 Set Ok 3
5 Instalasi Pre-Action Coridor Utility area Very Urgent Approve x Scaffolding 3 Set x 0
6 Instalasi Alarm Building Data Hall-2 Normal Approve Onsite Scaffolding 6 set x 2
+ Bracing + Roda
8 Instalasi Wet Sprinkler Chiller Room Urgent Approve Onsite Scaffolding 6 Set Ok 4
9 Instalasi Wet Sprinkler Staging Room Normal Approve Onsite Scaffolding 3 Set x 0 Repair instalasi 1 cabang
10 Instalasi valve pillar & Siamesse Very Urgent Approve x Jack hammer Ok 0
11 Instalasi Mainline Corridor Wet sprinkler balance area Urgent Approve Onsite Scaffolding 3 Set x 0
15 Instalasi Pre-Action low level Datahall 1 Urgent Approve x N/A N/A 0 Raised Floor sudah terpasang
19 Pengetesan Data Hall-1 Urgent N/A N/A Scaffolding 6 set x 0 Pipe sprinkler sebagian belum
+ Bracing + Roda dipasang dop
TOTAL 0
MONITORING PEKERJAAN LAPANGAN
Senin, 21-9-20
No UTILITY AREA Room Installation Status Pekerjaan Status Drawing Status Material Peralatan Pendukung Durasi Qtty Remarks
Man Power
1 TX - A GAS SUPPRESSION
2 TX - 1A GAS SUPPRESSION
4 TX - 1A GAS SUPPRESSION
ASD
IHB Approved
6 TX - 1A GAS SUPPRESSION
IHB Approved
10 TX - 1B GAS SUPPRESSION
GAS SUPPRESSION
30 CORRIDOOR LV & UPS SWITCH ROOM 1A WET SPRINKLER Approved With Note
31 CORRIDOOR LV & UPS SWITCH ROOM 1B WET SPRINKLER Approved With Note
32 CORRIDOOR LV & UPS SWITCH ROOM 1C WET SPRINKLER Approved With Note
35 CORRIDOR LV & UPS SWITCH ROOM B WET SPRINKLER Approved With Note
36 CORRIDOR LV & UPS SWITCH ROOM 2B WET SPRINKLER Approved With Note
No AREA DATAHALL 2 Room Installation Status Pekerjaan Status Drawing Status Material Peralatan Pendukung Durasi Qtty Remarks
Man Power
No AREA DATAHALL 2 Room Installation Status Pekerjaan Status Drawing Status Material Peralatan Pendukung Durasi Qtty Remarks
Man Power
FIRE EXTINGUISHER Approved
DATAHALL 3
FIRE ALARM BUILDING Approved With Note
No AREA DATAHALL 2 Room Installation Status Pekerjaan Status Drawing Status Material Peralatan Pendukung Durasi Qtty Remarks
Man Power
FIRE EXTINGUISHER Approved
DATAHALL 4
FIRE ALARM BUILDING Approved With Note
No AREA DATAHALL 2 Room Installation Status Pekerjaan Status Drawing Status Material Peralatan Pendukung Durasi Qtty Remarks
Man Power
GAS SUPPRESSION
GAS SUPPRESSION
6 IHB Approved
ASD
IHB Approved
FIRE ALARM BUILDING Approved With Note
GAS SUPPRESSION
GAS SUPPRESSION
GAS SUPPRESSION
IHB Approved
GAS SUPPRESSION
24 CORRIDOR AS 5,6
WET SPRINKLER Approved With Note
GAS SUPPRESSION
25 CORRIDOR AS 9
PRE-ACTION SPRINKLER Approved With Note
25 CORRIDOR AS 9
WET SPRINKLER Approved With Note
NO AREA LANTAI LEVEL INERGEN SYSTEM WET SPRINKLER PRE-ACTION SYSTEM IHB
Under Raised Floor Seamless Pipe Sch.80 x Seamless Galvanise Pipe Sch.40 Black Steel Pipe Sch.40
1 Balance Area Mid Level Seamless Pipe Sch.80 Black Steel Pipe Sch.40 x x
Under Raised Floor Seamless Pipe Sch.80 x Seamless Galvanise Pipe Sch.40 Black Steel Pipe Sch.40
2 Utilitty Area Mid Level Seamless Pipe Sch.80 Black Steel Pipe Sch.40 x x
Under Raised Floor Seamless Pipe Sch.80 x Seamless Galvanise Pipe Sch.40 x
3 Data Hall-1 Mid Level Seamless Pipe Sch.80 x Seamless Galvanise Pipe Sch.40 x
Upper Ceilling x x x x
Upper Ceilling x x x x
Upper Ceilling x x x x