Irrigation Engineering Analyze4u
Irrigation Engineering Analyze4u
Important Definitions
Crop period- It is the time period elapsed from the instant of
sowing to the instant of harvesting.
Base period - It is the time between the first watering of a crop at
the time of sowing to its last watering before harvesting. Frequently of
irrigation/rotation period It is the time interval between two
consecutive watering to a crop.
Delta- Total depth of water (in mm) required by a crop to come to
maturity is called its delta. It may be expressed in hectare-metre also.
Duty of water- It is the number of hectares of land irrigated for full
growth of a given crop by supply of 1 m3 /sec of water continuously
during the entire base period of the crop.
Soluble Salts- Excess salt is harmful for plant. Amount in excess of 700
ppm is harmful to some plants and more than 2000 ppm is injurious to all
crops.
Low salinity (C1 ) – 100 to 250 micro mhos/cm at 25°C
Medium salinity (C2 ) – 250 to 750 micro mhos/cm at 25°C
High salinity (C3 ) – 750 to 2250 micro mhos/cm at 25°C
Very high salinity (C4 ) – more than 2250 micro mhos/cm at 25°C
2. Inundation Canal
Inundation canal is a type of canal in which water is available only during the
flood periods. These type of canals are taken off from rivers to control the
water level in rivers during floods. A canal head regulator is provided to
regulate the flow into the canal.
2. Power canal
A canal constructed especially for the generation of hydraulic power is
termed as power canal.
3. Feeder canal
As the name says, a feeder canal is constructed to feed two or more other
canals or branch canals.
4. Carrier canal
A carrier canal is multi-function canal which serves the purposes of both
irrigation canal and feeder canal. It means the carrier canal feeds the other
canals as well as provides water for direct irrigation.
5. Navigation canal
A canal which is constructed especially for navigational purposes is known as
navigation canal.
The water level required in a navigation canal is generally a lot higher to
accommodate large ships, vessels, etc.
2. Productive Canal
Productive canals are those which will produce enough revenue for its
maintenance and running costs and also to recover the initial investment
made on the construction of the canal.
Based on Discharge
1. Main canal
2. Branch canal
3. Major distributary canal
4. Minor distributary canal
5. Field canal
1. Main canal- The main canal takes off directly from a river or reservoir. It
carries water in large amounts to feed the branch and distributary canals.
Due to conveying of very high discharge through the main canal it is not
recommended to do direct irrigation from it.
2. Branch Canal- The branch canal takes off from main canals at regular
intervals. These canals supply water to major and minor distributary canals.
The discharge of the branch canal is generally over 5 m3 /sec.
In the case of branch canals also, direct irrigation is not recommended unless
their water carrying capacity is very low.
3. Major Distributary Canal- Major distributary canal takes off from the
branch canal or in some cases from the main canal.
They supply water to minor distributaries and field channels. A canal is said
to be major distributary when its discharge lies between 0.25 to 5 m3 /sec.
4. Minor Distributary Canal
Minor distributary canal takes off from major distributaries and sometimes
directly from branch canals depending upon the discharge of canals. Their
discharge is generally below 0.25 m3 /sec.
These canals supply water to the field channels.
5. Field Channels
Field channels also known as watercourses are small channels excavated by
cultivators in the irrigation field. These channels are fed by the distributary
canals and branch canals through canal outlets.
1. Ridge Canal
A canal aligned along the ridgeline or watershed line of an area is said to be
ridge canal or watershed canal. Since it is running at the peak altitude of the
area, irrigation on both sides of the canal up to a larger extent of the area is
possible. There is no interception of natural drains on ridge lines hence, no
cross drainage works are required for this type of canal.
2. Contour Canal
A canal aligned roughly parallel to the contours of the area is called a contour
canal. This type of canal can be used in hilly regions. Since it is parallel to the
contour line, the ground on one side of the canal is higher and hence
irrigation is possible only on the other side of the canal. A contour canal has
to pass the drainage and hence cross drainage works are required to be
provided.
3. Side-slope Canal
A canal aligned nearly perpendicular to the contour of the area is called a
side-slope canal. It is located neither on the ridgeline nor on the valley line
but is approximately in between them. It is parallel to the natural drainage
line and hence no cross drainage works are required. The bed slope of side
slope canal is very steep
HYDRAULIC JUMP
Hydraulic jump is the jump of water that takes place when a
supercritical flow changes into a subcritical flow.
The loss of head in hydraulic jump is given by
HL =
Types of falls
1. Ogee falls: Water is gradually led down by providing convex and
concave curves.
2. Rapids fall : Long slopes of 1 : 15 to 1 : 20 with boulder facings are
known as rapids. They are quite satisfactory but very expensive
and hence became obsolete.
8. EnglisH fall or Baffle fall : For as straight glacis type fall a baffle
platform and a baffle wall are added.
Canal Escapes
A canal escape is a side channel constructed to remove surplus water
from an irrigation channel.
Note- Weir type and sluice type (regulator type) canal escapes are in
use.
Bed bars- Bed bars are masonry or concrete toe wall like structure
constructed along unlined canal, so as to serve as permanent reference
marks, and thus to indicate the correct alignment and theoretical bed
levels of the canal.
Drip Irrigation - Drip irrigation involves placing tubing with emitters on
the ground along side the plants. The emitters slowly drip water into
the soil at the root zone