0% found this document useful (0 votes)
44 views3 pages

Slide 1: Probability and Activity Times

Uploaded by

Elle Legaspi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views3 pages

Slide 1: Probability and Activity Times

Uploaded by

Elle Legaspi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Slide 1: Probability and Activity Times

Let's begin with single activity time estimates. In our example, building a house, we assume
activity times are known with certainty, meaning we have a single estimate with no significant
variation. For instance, laying the foundation is estimated to take 2 months, assuming no
deviation from this time."

Slide 2: The Reality of Estimations

"In reality, it's rare to have such certainty in activity time estimates. Most project activities are
unique and lack sufficient historical data for accurate prediction. This brings us to a comparison
between CPM and PERT. The Critical Path Method, or CPM, uses deterministic times, whereas
the Program Evaluation and Review Technique, or PERT, uses probabilistic activity times."

Slide 3: Focus on Probabilistic Times

"Today's discussion will focus on using probabilistic methods for estimating activity times in
project networks. We'll explore how these methods can provide more realistic and flexible time
estimates compared to single deterministic estimates."

Slide 4: Project Crashing

"Next, let's look at project crashing. For example, if an original activity duration is 12 weeks at a
cost of $3000, and we want to crash it to 7 weeks at a cost of $5000, the total crash cost would
be $2000. This is calculated by subtracting the normal cost from the crash cost. The crash time
is 5 weeks, and the crash cost per week is $400, which is the total crash cost divided by the
crash time."

Slide 5: PERT Methodology

"Now, we turn to the PERT methodology. Traditionally, a single time estimate is assigned to
each activity, but PERT uses three estimates to model uncertainty: the most likely time, the
optimistic time, and the pessimistic time. These estimates help calculate the mean and variance
for a beta distribution of activity times."

Slide 6: Beta Distribution

"The beta distribution is chosen for its flexibility and ability to approximate mean and variance
using three estimates. It’s a continuous distribution without a predetermined shape, meaning it
can be skewed based on the estimates provided. This makes it a traditional choice for
probabilistic network analysis."

Slide 7: Time Estimates

"Time estimates in PERT are subjective. The most likely time is the most frequent occurrence if
the activity were repeated many times. The optimistic time is the shortest possible time under
ideal conditions, and the pessimistic time is the longest possible time under the worst
conditions."

Slide 8 and 9: Mean and Variance Calculation

"Using these three time estimates, we can calculate the mean and variance of a beta
distribution. Here, 'a' represents the optimistic time estimate, 'm' the most likely time estimate,
and 'b' the pessimistic time estimate."

While mean or the expected time is equals to a + 4m + b divided by 6

And the variance is equals to b - a divided by 6 raise to the power of 2

Slide 10 and 11 :

Using the normal distribution, probabilities can be determined by computing the number
of standard deviations

Next is the network for processing system installation

Slide 12 and 13:

This is the table for time estimate activities

As an example of the computation of the individual activity mean times and variances,
consider activity 1. The three time estimates 1a = 6, m = 8, b = 102 are substituted in our
beta distribution formulas and it follows

Slide : Summary
"In summary, using probabilistic time estimates such as those in PERT allows for a more flexible
and realistic approach to project management. This helps in planning and managing project
timelines more effectively by accounting for uncertainties and variations in activity times."

You might also like