Analysis & Rates

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 7

Analysis & Rates

Task Work or Out Tirn


S.noParticulars of items Quantity Per Day
Brick Work in cement or lime mortar in foundation
1 1 .25cum (45cuft) per mason
and plinth
Brick Work in cement or lime mortar in
2 1cum (35cuft) per mason
superstructure
3 Brick work in mud mortar in foundation & plinth 1.5cum (55cuft) per mason
4 Brick work in mud mortar in superstructure 1.25cum (45cuft) per mason
5 Brick in cement or lime mortar in arches 0.55cum (20cuft) per mason
6 Brick in cement or lime mortar in jack arches 0.55cum (20cuft) per mason
7 Half brick wall in partition 5sqm (50sqft ) per mason
Coursed rubble stone masonry in lime cement
8 0.8cum (30cuft) per mason
mortar including dressing
Random rubble stone masonry in lime or Cement
9 1cum (35cuft) per mason
mortar
10 Ash lars masonry in lime or cement mortar 0.4cum (15cuft) per mason
11 Stone arch work 0.4cum (15cuft) per mason
12 Lime concrete in foundation or floor 8.5cum (300cuft) per mason
13 Lime concrete in roof terracing 6cum (200cuft) per mason
14 Lime concrete 1:2:4 5cum (175cuft) per mason
15 RB work 1cum (35cuft) per mason
16 RCC work 3cum (125cuft) per mason
17 12mm (1/2) plastering with cement or lime mortar 8sqm (80sqft) per mason
18 Pointing with cement or lime mortar 10sqm (100sqft) per mason
19 White washing or colour washing coats 70sqm (700sqft ) per white washer
20 White washing or colour washing coats 200sqm (2000sqft) per white washer
21 Painting or varnishing doors or windows one coat 2.5sqm (250sqft ) per painter
22 Coal tarring or soli gum painting one coat 35sqm (350sqft) per painter
23 Painting large surface one coat 35sqm (350sqft) per painter
24 Distemper in g one coat 35sqm (350sqft ) per painter
25 2.5 cm ( 1 ’) CC floor 75sqm (75sqft ) per painter
Flag store floor laying with lime or cement mortar
26 10sqm (100sqft) per painter
excluding LC
Brick on edge in floor lime or cement mortar
27 7sqm 70sqft per painter
excluding LC
28 Brick bat floor as in above 8sqm 80sqft per painter
29 Timber framing sal or teak wood 0.07cum 2.5cuft per Carpenter
30 Timber framing sal or country wood 0.15cum 5cuft per Carpenter
31 Door & Windows Shutters Paneled or glazed 0.15sqm 7sqft per Carpenter
32 Door and window shutters paneled or battened 0.8sqm 0.8sqft per Carpenter
33 Sawing hard wood 4sqm 40sqft per pair of sawers
34 Sawing soft wood 6sqm 60sqft per pair of sawers
35 Single allahabad tiling or mangalore tiling 6sqm 60sqft per tile layer
36 Double allahabad tiling 4sqm 40sqft per tile layer
37 Breaking of brick ballest 40mm (11/2”) 0.75cum 35cuft per Labour or braker
38 Breaking of brick ballest 2.5mm (1”) 0.55cum 20cuft per Labour or braker
39 Breaking of stone ball est 40mm (11/ 2” ) 0.4cum 10cuft per Labour or braker
40 Breaking of stone ballest 25mm (1”) 0.25cum 10cuft per Labour or braker
41 Ash lar stone dressing 0.7cum 25sqft per stone cutter
42 Flag stone dressing 1.5sqm 25sqft per stone cutter
43 Earthwork in excavation in hard soil 3cum 100cuft per beldars
44 Earthwork in excavation in hard soil 2cum 75cuft per beldars
45 Excavation in soil 1cum 25cuft per beldars
Number of bricks laid by a mason brick work up to a 600brick per
46
height of 3m(10”) mason
47 Amount of work done by a mazdoor helper per day
Mix 3cum 100cuft mortar per mandazoor
Delivery Brick 4000nos
Delivery Mortar 5.5cum 200cuft per Mazdoor
Scaffolding cost for single storey building
48 0.5cum per 100cuft mortar per mandazoor
item labor efficiency work to be
item description
no time executed
gang
hr
1 Excavation & Earth Work
1.1 site clearing to 20cm depth 1 DL 8hrs 10 m2
1.2 Trench excavation in ordinary soil
to a depth of 1.2 m 1 DL 8hrs 1.25 m3
to a depth of 2.2m 1 DL 8hrs 1.00 m3
to a depth of 3m 1 DL 8hrs 0.75 m3
bulk excavation in ordinary soil to a depth
1.3 1 DL 8hrs 1.50 m3
of 1.5m
1.4 cart away
to a distance of 500m 1 DL 8hrs 1.50 m3
to a distance of 1000m 1 DL 8hrs 1.00 m3
hard coding 25cm thick 1 M 4 DL 8hrs 18 m2
1.5 backfill around foundation
loose soil 1 DL 8hrs 2.00 m3
aggregate 1 DL 8hrs 1.50 m3
2 Concrete Work
2.1 lean concrete
5cm thick 1M 6DL 8hrs 20 m2
8cm thick 1M 6DL 8hrs 15 m2
2.2 Floor Slab
8cm thick 1M 6DL 8hrs 15 m2
10cm thick 1M 6DL 8hrs 12.5 m2
15cm thick 1M 6DL 8hrs 10 m2
ground beam 1M 6DL 8hrs 1.50 m3
footing 1M 6DL 8hrs 1.50 m3
foundation column 1M 6DL 8hrs 1.25 m3
upper tie beam 1M 6DL 8hrs 1.50 m3
lentils 1M 6DL 8hrs 1.00 m3
column up to 2m 1M 6DL 8hrs 1.00 m3
column above 2m 1M 6DL 8hrs 1.25 m3
3 Masonry Work
3.1 sub structure
40cm thick 2M 6DL 8hrs 5 m2
50cm thick 2M 6DL 8hrs 6 m2
60cm thick 2M 6DL 8hrs 7 m2
3.2 super structure
40cm thick 2M 6DL 8hrs 3 m2
50cm thick 2M 6DL 8hrs 4 m2
60cm thick 2M 6DL 8hrs 5 m2
3.3 Brick masonry wall for plastering
25cm thick up to 2m 1M 3DL 8hrs 7 m2
12cm thick up to 2m 1M 3DL 8hrs 9 m2
25cm thick up to 2-4m 1M 3DL 8hrs 5 m2
12cm thick up to 2-4m 1M 3DL 8hrs 7 m2
Hollow Block Masonry Wall for
3.4
plastering
20cm up to 2m 1M 2DL 8hrs 10 m2
15cm up to 2m 1M 2DL 8hrs 10 m2
10cm up to 2m 1M 2DL 8hrs 8 m2
20cm thick up to 2-4m 1M 2DL 8hrs 8 m2
15cm thick up to 2-4m 1M 2DL 8hrs 8 m2
10cm thick up to 2-4m 1M 2DL 8hrs 6 m2
4 Roofing Work
4.1 Leaf covering (G.C.I) 1C 2DL 8hrs 40m2
4.2 Ridge cover 1C 2DL 8hrs 70ml
4.3 Valley cover 1C 2DL 8hrs 70ml
4.4 Gutter fixing 1C 2DL 8hrs 30ml
Joining eucalyptus truss up to 10m span on
4.5 the ground 1C 2DL 8hrs 4tress
4.6 Down pipe fixing 1C 2DL 8hrs 40ml
4.7 Truss erecting 1C 2DL 8hrs 15tress
4.8 Fixing corrugated asbestos 1C 2DL 8hrs 25m2
4.9 Fixing EGA sheet joining 1C 2DL 8hrs 30m2
Joining Zigba Truss up to 10m span on
4.10 ground 1C 2DL 8hrs 3tress
4.11 Zigba truss erecting 1C 8DL 8hrs 15tress
4.12 Facial board fixing 1C 2DL 8hrs 70ml
5 Joinery - Work
5.1 Leaf covering (G.C.I) 1C 2DL 8hrs 3pcs
5.2 Ridge cover 1C 2DL 8hrs 4pcs
5.3 Valley cover 1C 2DL 8hrs 10m2
5.4 Gutter fixing 1C 2DL 8hrs 10m2
Joining eucalyptus truss
5.5 up to 10m span on ground 1C 2DL 8hrs 13m2
6 Metal Work
metal door fixing 1C 2DL 8hrs 3pcs
metal window fixing 1C 2DL 8hrs 4pcs
french window fixing 1C 2DL 8hrs 2pcs
7 Plastering and Pointing
7.1 1st coat plastering 1PL 2DL 8hrs 35 m2
7.2 2nd coat plastering 1PL 2DL 8hrs 10 m2
7.3 3rd coat plastering 1PL 2DL 8hrs 14 m2
7.4 pointing on brick wall 1PL 2DL 8hrs 8 m2
7.5 pointing on hollow concrete block 1PL 2DL 8hrs 14 m2
7.6 pointing on dressed stone 1PL 2DL 8hrs 12 m2
7.7 rendering 1PL 2DL 8hrs 20 m2
8 Flooring
8.1 cement screed 1M 2DL 8hrs 14 m2
8.2 ceramic tile fixing 1M 2DL 8hrs 10 m2
8.3 plastic tile fixing 1M 2DL 8hrs 17 m2
8.4 per quiet flooring 1M 2DL 8hrs 15 m2
8.5 wooden flooring 1M 2DL 8hrs 8 m2
8.6 ceramic wall tile 1M 2DL 8hrs 7 m2
8.7 plastic wall tile 1M 2DL 8hrs 40 ml
8.8 cement tile skirting 1M 2DL 8hrs 12 ml
8.9 marble slate flooring 1M 2DL 8hrs 12 ml
8.10 marble slate skirting 1M 2DL 8hrs 16 ml
8.11 fixing pre cat windows will 1M 2DL 8hrs 10 ml
9 Glazing
cutting 1P 2DL 8hrs 50m2
fixing 1P 2DL 8hrs 20m2
10 Painting
a)Plastic Paint
10.1 Painting plastered wall 3 coats 1P 1DL 8hrs 30m2
10.2 Painting Rendered wall surface 1P 1DL 8hrs 25m2
10.3 Painting Abujedid wall 1P 1DL 8hrs 20m2
10.4 Painting Hard board obi 1P 1DL 8hrs 20m2
10.5 Painting Cheap board ceiling 1P 1DL 8hrs 20m2
b) Synthetic paint
10.6 Plastered wall surface in 3 coats 1P 1DL 8hrs 25m2
10.7 Wooden surface 1P 1DL 8hrs 25m2
10.8 Metal surface 1P 1DL 8hrs 25m2
11 Sanitary work
11.1 G.1. pipe laying in Ground ½ - 11/4 1P 2DL 8hrs 120m2
11.2 Fixing – Bath tube Shower complete, wash 1P 1DL 8hrs 1pcs
12 Electrical Installation
12.1 Fixing conduits 1E 1DL 8hrs 40ml
12.2 pulling wires 1E 1DL 8hrs 50ml
12.3 Fixing switch &out-lets 1E 1DL 8hrs 20pcs
12.4 Fixing fittings 1E 1DL 8hrs 10pcs
12.5 Fitting distribution board 1E 1DL 8hrs 10pcs
13 Site Work
13.1 Drain laying
0.10 - 0.30m 1M 3DL 8hrs 30ml
0.40 - 0.60 m 1M 3DL 8hrs 20ml
0.80 - 1.00 m 1M 3DL 8hrs 10ml
13.2 Curb Stone 1M 3DL 8hrs 30ml
13.3 0.60 x 0.60 x 0.60m manhole out of brick 1M 3DL 8hrs 3pcs
0.60 x 0.60 x 0.60m manhole out of hollow 8hrs
13.4 1M 3DL 2pcs
block
13.5 Fencing with Galv.fencing net 1C 2DL 8hrs 50m2
MATERIALS FOR DIFFERENT ITEMS OF WORKS
The requirement of materials for different items of works is as given below:-
Sl # Particulars Quantity
Bricks (9”x4½“x3” or 20cmx10cmx10cm
1 5000nos per %cum (500nos per cum)
nominal size) for brick work
2 Dry mortar for brick work 30% 30cum for 100cum
3 Stone for rubble stone masonry 125% 125cum for 100cum
4 Dry mortar for rubble stone masonry 42% 42cum for 100cum
5 Bricks for brick ballast for lime concrete 3700cum for 100cum
6 Brick bats or brick ballast for lime concrete 150cum for 100cum
7 Brick ballast for lime concrete 100cum for 100cum
Dry mortar for lime concrete in foundation and
8. 35cum for 100cum
floor 35%
Dry mortar for lime concrete in roof terracing
9. 45cum for 100cum
45%
10 . Materials for cement concrete 1:2:4
Ballast or grit 88% 88cum for 100cum
Sand 44% 44cum for 100cum
Cement 22% 22cum (60bags) for 100cum
11. Materials for 2.5cm(1”) cc 1 : 2 : 4 floor
Stone grit 2.4cum for 100cum
Sand 1.2cum for 100cum
Cement 0.08cum (24bags) for 100cum
12 . Bricks for RB work 42000nos/%cum (420mps (erci)
13 . Dry mortar for R B work 45% 45cum for 100cum
14 Dry mortar for 12mm (1/2) plastering 2cum for 100cum
15. Dry mortar for pointing in brick work 0.6cum for 100cum
16 . Lime for white washing one coat 10kg for 100sqm
17 . Dry distemper for is t coat 6.5kg for 100sqm
18 . Dry distemper for 2nd coat 5kg for 100sqm
19 . Snow Cem for 1st coat 30kg for 100sqm
20 . Snow - Cem for 2nd coat 20kg for 100sqm
21. Paint ready mixed for painting one coat 10ltr for 100sqm
22 . Paint (stiff) for painting one coat 10kg for 100sqm
Bricks (20x10x10cm) for brick floor or half
23 . 500nos for 100sqm
brick wall
24 . Dry mortar for brick floor or half brick wall 3.2cum for 100sqm
25. Bricks (9”x4½“x3”) for brick flat work 3500nos for 100sqm
26 . Dry mortar for brick flat floor 2.25cum for 100cum
Bricks (9”x4½“x3”) required for honey comb
27 . 3250nos for 100sqm
wall
28 . Dry mortar for honey comb wall 2.5cum for 100sqm
Materials for 2cm (3/4”) thick damp proof
29 .
course of 1:2 cement mortar
Cement 0.9cum (27bags) for 100cum
Sand 1.8cum for 100sqm
Compound or impermo @ 1kg per bag of
2 7kg for 100sqm
cement
Materials for 2.5cm (1”) cc 1:1½:3 damp proof
30 .
course
Stone grit 2.25cum for 100cum
Sand coarse 1.13cum for 100cum
Cement 0.75cum for (221/2bags) for 100cum
Compound or impermo@ 1kg per bag of
22½ kg for 100sqm
cement
Bitumen or asphalt for painting on DPC or on
31. 150kg for 100sqm
roof – 1st coat
2nd coat 100kg for 100sqm
32 . GGI sheet for roof 128sqm for 100sqm
33 . AG corrugated sheet for roof 115sqm for 100sqm
Timber for paneled door shutter 4cm (1½”)
34 . 4.5cum for 100cum
thick
Timber for battend door shutter 4cm (1½”)
35. 4cum for 100cum
thick
Timber for paneled & glazed shutter 4cm (1½”)
36 . 3cum for 100cum
thick
Timber for fully glazed shutter 4cm (1½”) thick 2cum for 100cum