Pert CPM
Pert CPM
Project Management
Project Management
Used to manage large complex projects
Level
1 Project
2 Major tasks in project
3 Subtasks in major tasks
4 Activities to be completed
Project Scheduling Phase
Commonly used techniques:
ES EF
Activity Time
LS LF
Forward Pass: Earliest Start and Finish Times
Forward Pass: Earliest Start and Finish Times
Backward Pass: Latest Start and Finish Times
Backward Pass: Latest Start and Finish Times
Slack Time and Critical Path(s)
Slack is the length of time an activity can
be delayed without delaying the project
Slack = LS – ES or LF – EF
Slack = LS – ES or LF – EF
Critical Path and Slack Times
Critical Path: A→ C → E → G → H: ECT = 15 Weeks
Variability in Activity Times
a 4m b (b a) 2
E[T ] V [T ]
2
6 36
Project Variance and Standard Deviation
Project variance (σp2) is the sum of the
variances of the CRITICAL activities only
= ∑ (variances of all critical path activities)
σp2 = 0.11 + 0.11 + 1.0 + 1.78 + 0.11
= 3.11
Project standard deviation (σp)
= SQRT (Project variance)
σp = SQRT ( 3.11) = 1.76
Probability of Project Completion
What is the probability of finishing the
project within 16 weeks?
Assumptions:
Project duration is normally distributed
Activity times are independent
Normal distribution parameters:
μp = expected completion time= 15 weeks
σp = proj standard deviation = 1.76 weeks
Normal Probability Calculations
x 16 15 1
Z 0.57
1.76 1.76
This means 16 weeks is 0.57 standard
deviations above the mean of 15 weeks.
Z(0.57) = 0.2157. Add 0.5 to get 0.7157
Prob (proj completion < 16 weeks) = 0.7157
Acti Immediate
vity Predecessors a m b
A -- 2 4 7
Required
B A 3 6 10
C A 1 2 3 1. Draw The Project Networks
C A 1 2 3
D B 2 4 6
E B 2 3 5
F B, C 3 4 6
G B 1 2 4
H F 2 3 4
I F, H 1 1.5 2
J I 2 3 4
K D, E 4 7 10
Immediate
Activity Predecessors a m b
A – 8 10 12
PROJECT 2
B – 6 7 9
C – 3 3 4
D A 10 20 30
E C 6 7 8
F B, D, E 9 10 11
G B, D, E 6 7 10
H F 14 15 16
I F 10 11 13
J G, H 6 7 8
K I, J 4 7 8
L G, H 1 2 4
Activity Immediate Predecessors
A –
B –
PROJECT 3
C A
D B
E B
F B, C
G B
H F
I F, H
J I
K D, E
Activity Immediate
Predecessors
(a) (m) (b)
–
PROJECT 4
A 3 6 8
B A 5 8 10
C A 5 6 8
D B, C 1 2 4
E D 7 11 17
F D 7 9 12
G D 6 8 9
H F, G 3 4 7
I E, F, H 3 5 7
Activity Predecessors Normal Time
A 5
B 6
PROJECT 5
C A 4
D A, B 3
E B 5
F C, D 2
G E 4
H E, G 2
I F, H 3
J G 2
K I, J 5
Activity on Node (AON) Network Project 1
G
H
F
I