To (SSR)
To (SSR)
AbstructSeries capacitor compensation of AC transmission time domain simulation, rotor natural frequencies, network
systems provides an economical solution for the power natural frequencies.
transmission companies to increase maximum power carrying
capacity of existing transmission lines, control of load sharing of I. INTRODUCTION
parallel lines and enhance transient stability. However, looking at
it from generating utility point of view, the series compensation of EREGULATION of electricity markets has resulted in
lines may lead to possible Subsynchronous Resonance (SSR), in
case of transient faults, of turbine generator units resulting in
D separation of Utility Companies (responsible for power
generation) and Transmission Companies, (responsible for
fatigue life reduction of turbine generator rotors and even
damages which may prove to be very costly. In power stations power transmission). The decision making with respect to
having more than one bus connected parallel generating units, the power system planning is no more under the same umbrella. In
SSR consequences depend on the number of units in parallel fact, companies on both sides hwe a severe cost reduction
operation at the time of transient fault occurrence. In this paper, focus due to the competitive pressure. As a result, each side is
these consequences have been simulated for different com-
tempted to make independent decisions favorable to it. One
binations of parallel operating units for a power station having
five generating units to determine the worst case combination. such important decision is relaled to the extent of series
Simulations have been done for varying compensation ratio. capacitor compensation for the long AC transmission lines.
Acceptable value of series compensation ratio has been For the transmission side, larger the series capacitor com-
determined considering worst case operating units combination pensation ratio greater is the enhancement in load carrying
and the fatigue limit of turbine generator rotor. Frequency capability of the existing transmission lines. Rather than
domain analysis of electrical torque to determine the turbine
generator rotor natural frequencies, frequency scanning of investing huge amounts in laying new lines the series
passive electrical network reactance viewed from a point behind compensation in existing long lines (particularly in the
the generator stator winding to determine the network natural scenario of transmission of power across the countries) is an
frequencies, and finally the time domain simulation to capture the attractive economical solution for the transmission side.
system dynamics following a transient fault have been
demonstrated for different operating unit combinations. Looking at it from generation utility's point of view, more the
Simulation methodology demonstrated in this paper can prove to series capacitor compensation ratlio greater is the risk of SSR
be very useful for system planning decisions related to which may lead to very significanl reduction in fatigue life and
determining SSR risks of series compensation for bus connected even failures of the turbine generator rotor. This may prove
parallel generating units.
very costly for the generation side in terms; of downtime and
Index Term- Bus connected parallel generating units, fatigue
life of rotor, frequency domain analysis, frequency scanning, repairs of the generating units. The issue becomes more
series capacitor compensation, Subsynchronous Resonance (SSR), important when the utility company has bus connected parallel
generating units. In this case t h e SSR behavior of units is
dependent on how many units arc in operation at the time of
R. Kumar*, A. Harada, M. Merkle, A. M. Miri are with occurrence of a transient fault in the series compensated
Institute of Electric Energy Systems and High-Voltage transmission system. Depending on compensation ratio and
Technology (IEH), University of Karlsruhe (TH), combination of units in parallel operation, the SSR oscillations
Kaiserstr. 12, 76128 Karlsruhe, Germany ( Telephone : +49 / may get damped or amplified. In fact the SSR problem may be
721 / 608-6125, fax. : +49 I 7 2 1 I 6 9 52 24, dormant with many units in operaltion but if the transient fault
e-mail: [email protected] (*))
in the system occurs at a time when some units are not in
operation (due to reasons of maintenance or lower load
demand), there may be serious SSR oscillations affecting the
turbine generator rotor fatigue lifc or causing damages. Hence
0-7803-7967-5/03/$17.0002003 E E E
simulation of different unit operating combinations to identify for (1) single generator connected to infinite bus, (2) two
the worst case becomes very important. This paper simulates parallel generators connected to infinite bus and (3) five
power system dynamics and investigates the SSR behavior of parallel generators connected to infinite bus for different series
turbine generators when they are in bus connected parallel compensation ratios. Time domain simulations have also been
operation for varying series compensation ratio. Based on the done for enhanced power transmission capacity by
analysis method presented in this paper, the acceptable value incorporating five identical parallel transmission lines. Finally,
of series compensation ratio considering the worst case SSR as considering SSR as a constraint the acceptable compensation
a constraint can be worked out. This contribution can be very ratio has been determined for the worst case.
useful for finding a solution acceptable to both transmission
and generation side with respect to series Compensation ratio. 111. CASE STUDIES
I
HP
I I I IP LPA LPB GEN
f
EXC
Fig. 1. Power system network for SubsynchronousResonance (SSR) studies. Spring Constant @.u.) :
Km.y=7.277 Ku.mA=13.168 K,,,,,,=19.618 KLpsc&26.713 &~.~,+o&r
- 0.5 I /
h
v
21
0
Frequency (Hz)
OirI 1
d
2
-0.5
0 05 01 0 15 02 0 25 03
Time (seconds)
Fig. 6. Transient time domain simuhtion results with 74.2% series
compensation ratio (generator current, electrical torque and mechanical
Fig. 5. Reactance characteristics of passive network with 74.2% series torque characteristics as a function of time).
compensation ratio.
5
get disturbed as the generator feeds the fault. Frequency
3
spectrum of the disturbed current wave form is shown in
- Two Parallel Generators
; 0
Fig. 7. We can observe that following the disturbance,
generator current has a very large component near to 40 Hz
fiequency leading to the induction generator effect. As a result
z
U
5
5
the electrical torque oscillations begin and the mechanical
rotor torque oscillations follow. Further, the 40 Hz component
of current corresponds to 20 Hz slip fiequency which happens
to be very close to the natural kequency of the rotor. Hence,
the rotor starts oscillating and helps the subsynchronous
electrical torque as the damping is less than the torque. There 0 0 05 0.1 0.15
Time (seconds)
0.2 0 25 03
is a growing exchange of energy between the electrical system Fig. 8. Comparison of mechanical torque oscillations following
and the mechanical rotor at subsynchronous frequency and disturbance when (1) single generator, (2) two parallel generators and (3)
both the electrical and mechanical systems get excited as seen five parallel generators are in operation (with 74.2% series capacitor
-
in Fig. 6. The mechanical torque reaches 2 p.u. at time instant compensation ratio for each case),
0.2 s (i.e. within about 0.15 s of fault occurrence) thereby
seriously affecting the fatigue life of the rotor. The simulation 5
h
results compare well with IEEE Benchmark [2], hence
establishing the validity of our model.
v2
5
IV. CONC1,USION
'?
2 0
This paper has clearly demonstrated the methodology for
w carrying out simulation studies for a power station having five
-51 ,
identical generating units to determine the worst case
0 0 05 01 0.15 0.2 0 25 0.3
combination of bus connected parallel units considering the
SSR consequences. The study cases indicate that the SSR
consequences of series capacitor compensation of long
transmission lines are greatly influenced by the number of bus
0 0 05 0.1 0 15 0.2 0.25 03 connected parallel generating units in operation at the time of
5
transient fault occurrence and the worst ca:se SSR oscillations
c occur when two units are in operation. Generally, in large
2 0
w power stations many identical generating units are employed to
5
achieve the required installed capacity. In :such a case it is of
0 0 05 0. I 0 15 02 0.25 03
Time (seconds) great importance for the generating utilities to determine the
Fig. 10. Comparison of mechanical torque oscillations following disturbance worst case combination of generating units with respect to the
with five identical transmission lines connected in parallel when (1) single SSR problem. Thereafter the acceptable value of series
generator, (2) two parallel generators and (3) five parallel generators are in compensation ratio can be detemiined considering the fatigue
operation (with 74.2% series capacitor compensation ratio for each case). limits of turbine generator rotor as demonstrated in this paper.
The transmission companies need to respect this acceptable
value (e.g. only 15% in the case simulated here) as the upper
D. Determination of the Acceptable Value of Series limit for their decision making with respect to the series
Compensation Ratio compensation. Similar simulation studies can be carried out in
Investigations of SSR behavior following a system case the generating units are non identical.
disturbance in parallel generating units environment for series
compensated lines has revealed that the worst case is when two
generating units are running in parallel. For this worst case, we V. REFERENCES
have carried out simulations, with five identical transmission
lines connected in parallel (as in case studyC above) with
Periodicals:
varying ratio of series compensation and observed that only I. M. Canay, "A novel approach to the torsional interaction and
when the series compensation ratio is up to 15%, the torque electricd damping of the synchronous machine, Part I: Theory," IEEE
oscillations are within 2.0 p.u. and reduce in amplitude after Trans. On Power Apparatus and Systems, Vol. PAS-101, N0.10, 1982,
time instant 0.25 s (i.e. in about 0.20 s after the occurrence of ~ ~ 3 6 3 0 - 37.6 3
IEEE SSR Working Group, "First Benchmark Model for Computer
disturbance) as seen in Fig. 11. Considering 2.0 p.u. (i.e. Simulation of Subsynchronous Resonance," IEEE Trans. on Power
1.0 p.u. above the nominal value of 1.0 P.u.) as the worst case Apparatus and System, Vol. PAS-96, NoS,Sep./Oct. 1977, pp. 1565-
upper limit constraint for fatigue life reduction of the turbine 1572.
generator rotor, 15% series compensation ratio is determined B. L. Agarwal, R.G. Farmer, "Use of ffequency scanning technique for
subsynchronous resonance analysis," IEEE Tram On Power Apparatus
and Systems, Vol. PAS-98, N0.2, 1979, pp341-348.
X. Lei, B. F. Buchholz, E. Lerch, D. Povh, D. Retzmann, "A
Comprehensive Simulation Program for Subsynchronous resonance
Analysis".0-7803-6420-1/00/$10.00(c)2000IEElT ,pp. 695-700.
Books:
[5] Subsynchronous Resonance in Power Systems.,P. M. Anderson, B. L.
Agarwal, , J. E. Van Ness, IEEE Press, 1990.
[6] Analysis of Subsynchronous Resonance in Power Systems, K. R.
Padiyar, USA, Kluwer Academic l'ublishers, 1999.
[7] Power System Stability and Conlrol. New York, Prabha Kundur,
Time (seconds) McGraw-Hill, Inc., 1993.
[8] Voltage Stability of Electric Power Systems, Thieny Van Cutsem,
Fig. 11. Mechanical torque oscillations following disturbance with five Sostas Vournas, USA Kluwer Academic Publishers, 1998.
identical transmission lines connected in parallel when two generators [9] Understanding FACTS, Narain Ci. Hingorani, Laszlo Gyugyi, IEEE
are in operation (with 15% compensation ratio). Press, 2000.
VI. BIOGRAPHIES