PERFORMANCE QUALIFICATION
PROTOCOL
FOR
COLLOID MILL MACHINE GMP
MODAL- WATER JACKETED-
HORIZONTAL
EQUIPMENT ID:
Contents
Page 1 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
Page 2 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
Prepared By:
Name and Functional area Signature Date
Quality Assurance
Reviewed By:
Production Manager
QC Manager
Engineering Manager
Approved By:
Name and Functional area Signature Date
Quality Assurance
Page 3 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
2.0 Objective:
The purpose of carrying out Performance Qualification protocol of Colloid Mill Machine GMP Modal-
Water Jacketed- Horizontal is to establish documented evidence that the system performance is in
accordance with the predefined specifications.
3.0 Scope:
The document includes the Performance Qualification procedure of the following system:
Name of the equipment Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Equipment identification number CV/
Website: www.saimach.com
This report should be generated to qualify the initial performance of the system. In case of any deviation
observed during qualification same shall be log as per deviation SOP.
Page 4 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
4.0 Responsibility:
Department Responsibility
Review of Protocol
Production
To Co-ordination and support Performance Qualification Activity.
Review of Protocol
Quality Control
To Co-ordination and support Performance Qualification Activity.
Review of Protocol
Engineering
To Co-ordination and support Performance Qualification Activity.
Page 5 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
Page 6 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
Page 7 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
Page 8 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
4.
PQ Protocol
Page 9 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
10.1.2 Method:
Install/ ensure mesh of size as identified in BMR. Mesh opening of the Sieve to be as identified
as per SBB Mesh number.
The dispensed/ milled material is charged through scooping into the hopper of the colloidal mill.
The quantity & type of material charged and the size of the sieve selected shall be as per BMR.
The sieving is carried out as per approved parameters, in accordance with Standard Operating
Procedure & as per BMR.
Samples of milled material are taken at the high, middle & slow speed of the milling process
from the discharged chute of the colloidal mill.
The samples are analyzed for appearance and particle size by manual sieving through as
analytical sieve of approved mesh size.
Page 10 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
11.0 Reference:
Validation Master Plan
Schedule-M- “Good Manufacturing Practices and Requirements of Premises, Plant Equipment for
Pharmaceutical Products”.
WHO Essential Drugs and Medicines Policy, QA of Pharmaceuticals, Vol-2 Good Manufacturing
Practices and Inspection.
Page 11 of 12
Document Name: Performance Qualification Protocol for Colloid Mill Machine GMP Modal- Water Jacketed-
Horizontal
Identification Number: Document Number:
Effective Date: Revision No.:
16.0 Abbreviation:
WHO : World Health Organization
cGMP : Current Good Manufacturing Practices
PQ : Performance Qualification
RMG : Rapid Mixture Granulator
GMP : Good Manufacturing Practices
QA : Quality Assurance
PLC : Programmable Logic Control