HHIC Installer Guide: Condensate Discharge Pipe Installation
HHIC Installer Guide: Condensate Discharge Pipe Installation
HHIC Installer Guide: Condensate Discharge Pipe Installation
Condensate discharge
pipe installation
October 2018 Issue 1.0
Condensing Boiler
Industry guidance for installers - endorsed by
HHIC members
In April 2005 revisions to the Building Regulations came into force, stat-
ing that all replacement gas or oil boilers must be a condensing type. The
introduction of condensing boilers has been fundamental in reducing the
UK’s carbon emissions.
In 2010 and again in 2018 the UK experienced prolonged spells of sub-zero
temperatures down to minus 20 centigrade and below in many areas. This
resulted in a significant increase in the number of calls to boiler
manufacturers and heating engineers from householders with condensing (high
efficiency) boilers where the condensate discharge pipe had frozen and become
blocked with ice causing the boiler to shut down. In the vast majority of cases
such problems occur where the condensate discharge pipe is located
externally to the building for some part or all of its length.
With the UK weather patterns showing more “extremes” in future due to the
effects of global climate change, the following guidance updates previous
recommendations on condensate discharge pipe installation. In addition to this
guidance all other technical requirements for condensate discharge installation
given in British Standard BS 6798:2014, or in boiler manufacturers’ installation
instructions should still be followed.
Condensate Pumps
Existing Installations
When servicing or repairing a boiler the heating engineer should check any
boiler installations especially those that have external condensate drains to
see if they can be terminated internally or upgraded to the latest guidance.
The responsible person (home owner) should be advised and it is
recommended that the installer completes the responsible persons frozen
condensate information leaflet as a suitable means for advising the work that
is required. See annex A
This guidance should be followed where work is carried out to “upgrade” the
condensate discharge system to reduce the risk of freezing in extreme
conditions and it is recommended that the condensate pipe is identified with a
suitable label or marking even if the responsible person does not go ahead with
the upgrade so as to allow easier identification in the future.
Manufacturers Instructions
Note - A suitable permanent connection to the foul waste pipe should be used.
Figures 1, 2(a), 2(b) show appropriate connection methods.
8
2 5
7
3
4
6
Key
1 Boiler
2 Visible air break
3 75 mm trap
4 Visible air break and trap not required if there is a trap with a minimum condensate seal
of 75 mm incorporated into the boiler
5 Soil and vent stack
6 Invert
7 450 mm minimum up to three storeys
8 Minimum internal diameter 19 mm
Figure 2(a) – Connection of a condensate discharge pipe downstream of a sink, basin, bath or
shower waste trap.
Note – Check manufacturer’s instructions to see if an air break is required.
8
2
7
11
12
5
4 3
9 10
6
Key
1 Boiler
2 Visible air break
3 75 mm trap
4 Visible air break and trap not required if there is a trap with a minimum condensate seal
of 75 mm incorporated into the boiler. In this case the 100 mm is measured to the trap
in the boiler.
5 Sink, basin, bath or shower
6 Open end of condensate discharge pipe direct into gully 25 mm min below grating but
above water level; end cut at 45 °
Note – the maximum external condensate discharge length is 3 metres
7 Sink lip
8 Minimum internal diameter 19 mm
9 Pipe size transition
10 Minimum internal diameter 30 mm
11 Water/weather proof insulation
12 Drain cover/leaf guard
Figure 2(b) – Connection of a condensate discharge pipe upstream of a sink, basin, bath or
shower waste trap
2
6 8
4 9
10
3
7
Key
1 Boiler
2 Visible air break at plug hole – alternative connection can be below sink trap
3 75 mm sink, basin, bath or shower waste trap
4 Sink, basin, bath or shower with integral overflow
5 Open end of condensate discharge pipe direct into gully 25 mm min below grating but
above water level; end cut at 45 °
Note – the maximum external condensate discharge length is 3 metres
6 Minimum internal diameter 19 mm
7 Pipe size transition
8 Minimum internal diameter 30 mm
9 Water/weather proof insulation
10 Fit drain cover/leaf guard
External waste pipes from kitchens, utility rooms or bathrooms such as sink,
basin, and bath or shower waste outlets should be insulated with waterproof UV
resistant, class 0 material, terminated below the grid but above the water line
and a drain/leaf guard fitted. The waste pipe should be cut at 45 degrees where
it terminates into the grid. (See insulation section for guidance on suitable
materials).
Condensate Pumps
3 Key
1 Condensate discharge from boiler
4 2 Condensate pump
3 Visible air break at plug hole
4 Sink or basin with integrated overflow
1 5 75mm sink waste trap
5
2
Key
1 Boiler
6 2 2 Visible air break at plug hole
4 3 75 mm sink, basin, bath or shower
8 9 waste trap
4 Sink, basin, bath or shower with
3 7 10 integral overflow
5 5 Open end of condensate discharge
pipe direct into gully 25 mm min below
grating but above water level; end cut
1 at 45 ° Note – the maximum external
condensate discharge length is 3 metres
6 Minimum internal diameter 19 mm
7 Pipe size transition
8 Minimum internal diameter 30 mm
9 Water/weather proof insulation
10 Fit drain cover/leaf guard
External Connections
The pipe work from the boiler should be of a minimum 19mm ID or as per
manufacturer’s instructions and the condensate discharge pipe shall be run in a
standard drainpipe material, e.g. poly (vinyl chloride) (PVC), un-plasticized poly
(vinyl chloride) (PVC-U), acrylonitrile butadiene-styrene (ABS), polypropylene (PP)
or chlorinated poly (vinyl chloride) (PVC-C).
Note - Fixing centres for brackets should be a maximum of 300mm for flexible pipe and
500mm for solid pipe and manufacturer’s recommendations should be followed.
The condensate pipe should be run internally as far as possible before going
externally and the pipe diameter should be increased to a minimum of 30mm
ID (typically 32mm OD) before it passes through the wall. The angle of the pipe
should slope downwards by at least 3 degrees as it passes through the wall to
assist in maintaining a good velocity as the condensate exits the building.
Manufacturers
Manufacturers Instructions
Instructions must
must be be referred
referred to when
to when
installing
installing
Manufacturersboiler
boiler condensate
condensate
Instructions discharge
discharge
must pipes
pipes
be referred to when
installing boiler condensate discharge pipes
External Connections
Figure 4 – Connection of condensate discharge pipe to external soil and vent stack
11
8 2 9
5
10 7
3
4
6
Key
1 Boiler
2 Visible air break
3 75 mm trap
4 Visible air break and trap not required if there is a trap with a minimum condensate seal
of 75mm incorporated into the boiler.
5 Soil and vent stack
6 Invert
7 450mm minimum upto three storeys
8 Minimum internal diameter 19 mm
9 Pipe size transition point
10 Minimum internal diameter 30mm
11 Water/weather proof insulation
Alternative Solutions
Cold weather protection methods approved or endorsed by boiler manufacturers
and/or service organisations may be adopted if these are considered suitable by
the parties involved. It is the responsibility of the manufacturer of these products
to ensure they have completed the necessary testing or calculations to ensure
the product offers suitable protection to prevent the condensate pipe from
freezing. The product manufacturer should provide information as to what level
of external temperature and for what time period the product can protect against
sub-zero temperatures, i.e. -15°C for 48 hours. BS6798 refers to devices that
pump the condensate produced by a condensing boiler to a fine misting nozzle
in the boiler flue terminal so that the condensate is discharged with the hot flue
gas. (BS6798 section 6.3.8 note 4). The boiler manufacturer’s instructions will
provide advice regarding fitting and siting of the flue terminal to ensure safe
disposal of the condensate.
Additional Measures
Manufacturers
Manufacturers Instructions
Instructions must
must be be referred
referred to when
to when
Manufacturers
installing
installing boiler Instructions
boiler condensate
condensate must be referred
discharge
discharge to when
pipes
pipes
installing boiler condensate discharge pipes
External Connections
Insulation Materials
Insulation used for external condensate pipes, sink or washing machine waste
pipes should be of class ‘O’ grade with an outer coating that is weather proof,
bird/animal proof, and UV resistant finish. A minimum of 19mm thick insulation
is recommended for 32mm external pipes.
Manufacturers Instructions
Manufacturers Instructions must
must be
be referred
referred to
to when
when
installing boiler
installing boiler condensate
condensate discharge
discharge pipes
pipes
External Connections
5
1
3
9
2
6
7
10
4 8
11
Key
1 Condensate discharge pipe from boiler
2 Pipe size transition point
3 Water/weather proof insulation
4 43mm 90° male/female bend
5 External rain water pipe into foul water
6 External air break
7 Air gap
8 68mm PVCu strap on fitting
9 Minimum internal diameter 19mm
10 Minimum internal diameter 30mm
11 End cut at 45°
Manufacturers
Manufacturers Instructions
Instructions must
must be be referred
referred to when
to when
installing
Manufacturers
installing boiler
boiler condensate
Instructions
condensate discharge
must pipes
be referred
discharge pipes to when
installing boiler condensate discharge pipes
External Connections
The use of a drain cover (such as those used to prevent blockage by leaves)
must be fitted to offer further protection from wind chill. Figure 6 (following
page)shows a suitable connection method. Where the condensate drain pipe
terminates in a purpose-designed soakaway (see BS 6798:2014 or boiler
installation manual for soakaway design requirements) any above-ground
section of condensate discharge pipe should be run and insulated as described
above. Figure 7 (following page) shows a suitable connection method.
1
2 9 10
7 5
11
4 8
6
Key
1 Boiler
2 Visible air break
3 38mm minimum trap
4 Visible air break and trap not required if there is a trap with a minimum condensate seal
of 38 mm incorporated into the boiler – refer to manufacturers instructions
5 External length of pipe 3 m maximum
6 Open end of condensate discharge pipe direct into gully 25 mm min below grating but
above water level; end cut at 45 °
7 Minimum internal diameter 19 mm
8 Pipe size transition point
9 Minimum internal diameter 30 mm
10 Water/weather proof insulation
11 Fit drain cover/leaf guard
11
1 9 10 2
6 7
Key
1 Condensate discharge pipe from boiler
2 Ground (this section of the condensate discharge pipe may be run either above or below
round level); End cut at 45°
3 Diameter 100 mm minimum plastic tube
4 Bottom of tube sealed
5 Limestone chippings
6 Two rows of three 12 mm holes at 25 mm centres, 50 mm from bottom of tube and facing
away from house
7 Hole depth 400 mm minimum by 300Manufacturers
mm diameter Instructions must be referred to w
8 Minimum internal diameter 19 mm installing boiler condensate discharge pipes
9 Pipe size transition point
10 Minimum internal diameter 30 mm
11 Water/weather proof insulation
Customer information:
Frozen boiler
condensate discharge
October 2018 Issue 1.0
Condensing Boiler
Guidance and advice for customers- endorsed by the Heating and
Hotwater Industry Council, HHIC