Final 4 DME
Final 4 DME
g) The ceiling limit of profit is fixed at 50%, of the time taken in each of the
operations/GA hours.
a. Manipulation values.
b. Loading and unloading values.
c. Setting up values.
d. Changing tool values.
e. Preparational values.
408. Rating
Rating is the assessment of the skill and effort involved in each element
and every element should be rated independently of previous elements. The
principle of rating is that an average worker when working at such a speed
and with such an effort that he is just earning basic pay i.e. working at a
time or day work rate under non-incentive conditions is said to be working
at a 60 rating. This can be interpreted as saying that he is producing 60
units of work per hour This same average worker when working under a
properly applied incentive scheme works at a speed and with such effort as
to earn 33-1/3% more i.e. at an 80 rating, can then be said to be producing
80 units of work per hour. If he is working at half the effective speed, he is
working at 30 rating or alternatively if he is working at double the effective
speed, he is said to be working at 120 rating. Similarly other ratings are
assessed by comparing the worker under study with the rating of an ave-
rage worker. Different operative workers performing the same job are
studied and the results checked by superior rate fixers which finally be
endorsed by the Senior Section Engineer of the rate fixing department.
409. Normalizing
On completion of the time study, the actual times of all the elements in the
work cycle should be converted to time at 80% rating i.e. the time which the
average worker should take to do each element when working under a
correct incentive scheme. This conversion is done by the following
calculation:
Extra time over the allowed time can be allowed due to:
a. Excess machining work required on castings forgings bars etc.
b. Hard material/alternative material.
c. Defects in the machine for which the worker is not responsible.
d. Change in batch quantity against a work order.
The rate fixer will fill up an excess Time Card and issue it to the
supervisor concerned who will get it countersigned by the SSE hand over to
the Time Booth clerk for connecting up with the relevant job/squad cards.
At least 10 to 20% of excess time cards in manufacturing shops and 2 to 5%
of inspection cum computation sheets should be personally checked by
PE/APE.
Job card /squad cards are basic documents on the basis of which
incentive bonus is calculated. Allowed time for the job is indicated in each
job card. Once the job is done, same is passed by inspector and certified by
Rate Fixer. Such completed job/squad cards should be sent to Incentive
Bonus section within 48 hours of completion of the job.
413. Out-turn
(i) The difference between the "time allowed" and "time taken" is the
time saved, if the former is greater than the latter and "time lost" if it is
otherwise, the allowed time will comprise of the following:
a. Time per piece multiplied with the quantity passed by inspection.
b. Preparatory time per batch-, and
c. Extra time allowed by the rate fixer as per extra time card.
(ii) Where two or more workers are engaged on the same job, the net
time saved/lost from each squad card as worked out will be distributed over
the workers in proportion to the time taken by each of them.
(iii) Allowed time on job cards should be printed by the computer. The
allowed times on squad cards should be supported with detailed
printed/cyclostyled inspection cum computation sheets. Hand
written/typed allowed times on job cards/inspection cum computation
sheets should be countersigned by PE/APE. The job cards and other
production documents shall be printed through the computer. Suitable
specific electronic security checks on the computer system would have to be
incorporated to prevent possibility of tampering with the job data for
different shop manufactured items.
The basic wages of all workers are guaranteed irrespective of their results
of Incentive Bonus, but losses during any particular month are adjustable
against the profits of the same month. Special procedure should be laid
down to electronically disallow completed job cards of one wage period
accounted in the bills of any other month than the current bill. Details of
painted numbers of Locos, coaches or wagons turned out every month from
the workshop or Production Unit must be fed into the system at regular
intervals. Job cards pertaining only to those of the rolling stock turned out
during the month should get accounted; and they should be accounted in
the same month and the system should reject any accumulation.
418. Incentive Bonus Rates and ceiling on profits in CLW scheme
Time saved or lost will be evaluated at the Incentive Bonus hourly rates as
fixed by the Railway Board for different categories of staff from time to time
and circulated to Railways. Time saved or lost will be evaluated at the
Incentive Bonus hourly rates. Ceiling limit on profits has been fixed at 50%
of the standard basic wages in respect of each worker on simplification of the
system as in para 414.
The ceiling limit on profit is fixed at 50% of time taken/GA hours. When
large profits (above 50%) are made more or less consistently or by the
majority of workers, the causes contributing to this result should be
carefully analyzed and any defects discovered, rectified.
420. Losses
Part 'A'
S.No. Ticket Name Category Rate Remarks
No. of
Pay
Part 'B'
Ticket Nos. of Direct workers served by the "Essential Indirect Workers".
S.No. Ticket No. Name Category Rate of Pay Remarks
Part 'B'
Ticket Nos. of Bonous workers served under the supervision of
(b) Essential Indirect Workers and Junior Supervisors are paid bonus
at 80% of the average bonus earnings of the section. For this purpose a
concept of standard hour is used to simplify calculations for hours of work
per month. The formula for working out .standard hours is:
Total No. of G.A. card hours actually worked by the direct workers
during the preceding 6 months/one year
x 208
hrs
Total No. of hours which the workers should have worked as per the
Scheduled working hours during the preceding 6-months/one year.
Standard No. of hours can be worked for the workers is a whole or for
certain divisions of the works. Standard hours thus worked out shall
remain current for the ensuring 6 months/12 months after which it will
again be revised. The average percentage of profit of direct workers of each
section is calculated separately as follows:
Note: The bonus payments of the supervisors supervising the direct worker
under incentive scheme as well as direct workers under non incentive,
calculated as per the above, formula should be further multiplied by the ratio of
the Direct Workers under the incentive scheme to direct workers under
incentive scheme plus direct workers under non incentive scheme supervised
by them.
Such of the service shops and sections of mill Wright and tool and
template shops where workload can be measured and quantified should be
covered under incentive scheme as for direct workers. But where it cannot
be undertaken and where the maintenance staff are wholly engaged in the
servicing maintenance and repairing of machinery, plant and equipment of
various shops, should be covered under incentive scheme as essential
indirect workers. The following guidelines should be adopted:
Apart from wages having to be paid for no work done, idle time
entails huge avoidable losses in production. All possible steps should
therefore be taken for preventing idle time. The time taken up in delays and
holdups, due to breakdown of service or plant or any other cause for which
the direct worker cannot-be held responsible should be booked to "idle time"
and all time so booked should be carefully investigated, responsibility for
the delay or breakdown located and such steps, as may be, considered
desirable, taken to prevent such waste.
To record idle time, there shall be an ''idle time card" for each worker
for each month. These cards will depict the reasons as detailed below on the
reverse of the idle time cards for the analysis of idle time. These cards will
remain in the custody of time booth clerk and shall be punched on/off with
the commencement/cessation of idle time on the authority of idle time slips
issued by JE. Idle time cards shall be signed by JE and countersigned by
SSE and shall be sent to the accounts office along with the job cards.
The JE of a shop are directly responsible for (i) lack of work and (ii) lack of
tools. Therefore, for the idle time arising out of these two causes,
proportionate deductions on the following scales should he made from the
percentage incentive bonus earned by the concerned supervisors.
If data for idle time not available at the time the bills for incentive bonus
are prepared, the position should be reviewed subsequently and necessary
adjustments carried out through the bill for the next month.
The following points should be kept in view while dealing with the
Extension/ Contraction proposals of incentive scheme in the sections
already operating under the scheme: -
The proposal for extension should only be made out wherever there is an
increase in the work load on the nature of work for which an incentive
proposal has already been noted and reasons for increase in work load have
been brought out.
a. No increase has been made in the original allowed lime and that any
increase in the strength of staff is proportionate to that indicated in the
original proposal.
b. Number of Essential Indirect Workers and Indirect Workers is strictly below
the caps prescribed.
c. In cases of extension, the possibility of using the same unskilled staff for
material handling movements under the extended load should be carefully
checked, in case of contraction of incentive scheme, the possibility of
reductions of unskilled staff should be carefully checked,
d. The provision of supervisory staff should be critically examined. In cases of
merger of sections, the possibility of reduction of supervision shall be
properly looked into.
The job cards received in Incentive section of the Accounts Office should
be checked to see that:
a. These have been inspected and signed with date by the shop inspector for
the quantity passed;
b. All corrections in the pre-printed job cards bear the dated signature of the
shop rate fixer under his designation.
c. Total of the 'Time Taken" as struck on the job cards by the Time booth clerk
tallies with the details on the job cards.
d. "Total allowed time" will be worked out on the basis of the 'passed' outturn.
The allowed time as appearing on the job card should be checked with that
approved by the P.E. by comparison with the master planning card or list of
allowed times approved by Production Engineer. For this purpose, a copy of
each master-planning card should be supplied by die P.E. to W.A.O. This
check may be exercised as a percentage post check (under orders of the
FA&CAO) in such a way that all "allowed times" get checked in rotation.
e. Time saved/lost for each operation shall be worked out taking care that the
time saved against job card/squad card is restricted to 50 % of checked up
"time taken" as recorded on each card. If simplification of job card accountal
is adopted as per para 515, the limit of 50% of time saved over time taken
should be adopted for the entire accountal month for each worker.
f. Hand written job cards are certified by AWM/P.E.
g. Excess time card is attached with the job card wherever "excess time card'
is indicated.
h. Out-turn statements are certified by the Inspector and are signed by the
shop supervisors. For excess time and for the items of work not covered by
the approved list there should be signature of the rate fixer.
i. It should be crosschecked that No. of direct workers, essentially Indirect
Workers and supervisors in whose favor bonus has been billed for, are not
in excess of the sanctioned strength.
j. All the job cards as per monthly statement showing serial nos. of job cards
supplied during the month as received from the time booths have been
taken into account.
k. Proportionate deductions are made from the profits earned by the JEs and
SEs, if idle time of production workers on account of lack of work and lack
of tools is 2% and above.
l. Amount of bonus to JEs is in the ratio which the total No. of direct workers
under incentive bears to total number of direct workers in the section.
m. Detailed instructions for checks to be exercised on the job cards and bills of
incentive bonus may be laid down by the Financial Adviser & Chief
Accounts officers of each railway to suit the local requirements.
n. The idle time cards attached with the job cards should be checked with idle
time slips issued by shop JEs. All the idle time cards should have been
personally checked by Works Manager/Assistant Works Manager within 24
hours of being punched "IN".
o. Job cards should be supported by suspension/ resumption slips if there
have been punching -OFF" and punching "IN" due to suspension/
resumption of jobs. Suspended job should be rigidity checked by Works
Manager/Assistant Works Manager and suspended jobs for one month to
another month should be checked by Production Engineer/Assistant
Production Engineer.
Annexure 4.3 compares the features of the Group incentive scheme with
those of the earlier Chittaranjan model.
435. Special Management responsibility in incentive schemes
436. Training
While the establishment related issues of training are spelt out in the
Establishment Manual, the exposure necessary for employees in various
activities in a Production Unit, Repair Workshop, Loco shed or C&W depot
is elaborated here.
As seen from the table below, there are no tight compartments and
some overlap of traits between the groups is not only essential, but also
inescapable. Apart from improving attitude and commitment to
organization, Training courses should intensively target the core
competence on aspects as highlighted in this table:
Training to concentrate on
Designati Skills Rules Knowledg Stra
on e teg
of Trainee y
Unskilled
to Skilled
Skilled to
JEII, JE I
JEII, JE I
to SE/SSE
SE/SSE to
Junior
officers
Junior to
Senior
officers
Senior
officers
Remarks:
a. Irrespective of the grade of entry, every employee should be given a short
orientation course on his/her first appointment, explaining organizational
structure, work environment and basic rules of the Railway and how he/she
is expected to conduct himself/herself.
b. Special care must be taken to ensure that employees are not qualified
routinely without acquiring necessary skills before being deployed in “safety
critical work”, that is likely to affect safety of the organization or the society
at large (fitters or electricians for e.g. deployed in wiring, maintenance of
brakes etc).It is incumbent on the management to ensure that-
The employee is competent and has developed adequate skills in that trade
and is so certified fit to undertake that work by an competent agency like
NCTVT.
There is an existence of an adequate record of training and an assessment
as said above undergone by the employee and that the employee has been
issued with means of identification.
c. Promotion to any of the entry grade should be preceded by a structured
training. In fact, such training will be a “pre-requisite” for promotion to the
entry grades (skilled artisan, JE II, SSE, junior scale/assistant officers etc.).
439. Multi-skilling
Four levels of managerial statements are required for analysis and effective
utilization of manpower.
Industrial Safety
a. Putting in place, fire fighting systems and to ensure its efficacy in times of
distress by conducting regular drills.
b. Evolve an Emergency Preparedness Plan‖ for the shop and ensure that it works
by frequent mock drills.
c. Battery management and handling as per rules.
d. Maintenance of fire extinguishers, fire hydrants and static water tanks and other
equipments
e. Setting up of disaster management system and to conduct periodic drills to deal
with any eventuality.
f. Medical examination of operators of dangerous machines.
g. Accident preventive measures, counseling, safety propaganda campaign.
h. Training in Safety & Environmental issues:
i. Conduct safety audits internally and externally and implement recommendation
based on audits.
j. Investigation and enquiry of accidents of major nature.
k. Other safety related activities.
l. Training employees in reducing repetitive motion injuries.
m. Eye water wash facility for staff working in welding and painting area.
n. Assessment and provision of personal protective equipment like industrial safety
shoes, helmets, goggles, ear muffs, nose mask and gloves.
o. Testing and examination of EOT cranes, hoists, lifting tackles pressure vessels,
power presses, grit blasting plant, Forklifts, mobile cranes by competent
personnel.
p. Work permit system for contract workers
q. To ensure that contract labour, when employed, use necessary protective
clothing.
Environment Management
1.Air management
c. Remedial measures to improve air quality in consultation with Pollution Control Board
(PCB)
e. Effective operation and maintenance of air pollution equipment like wet scrubbers and
dust collectors
2. Water management
b. Regular sampling and evolving control measures to neutralize Toxins and Pollutants.
g. Rainwater harvesting.
In case of repair workshops, separate cleaning area should be created outside the
workshop security zones, where incoming coaches and wagons are cleaned thoroughly by
a separate contract. In the divisions, On-Board Housekeeping System (OBHS) should be
adopted to ensure faster cleaning of coaches.The effluent water may be recycled and the
debris should be cleared by the same contractor on a day to day basis
Waste generation
Any by product of the repair/manufacturing processes and activities executed inside the
workshop premises, not useful to the Railways is termed “waste”. Waste in any form is a
cost to the Railways and therefore generation of waste must be creatively and actively
eschewed. Accordingly an important environmental initiative is to frequently review input
material specifications, processes and final products so as to minimize, if not, completely
eliminate pollution or hazardous and other wasters through capital and process
improvements. The efficacy of these initiatives may be assessed by the reduction in the
“solids-per-pound of product” from the workshops, as well as waste liquid discharged, the
eventual goal being Zero waste discharge