Constr-001 Method Statements Cable Installation and Termination
Constr-001 Method Statements Cable Installation and Termination
Revision Number: 00
Document
Owner: MRQ
The purpose of this method statements is to define the procedure step by step to
implement correct practices for installation and termination of cables and wires
guidelines contained herein so as to ensure that the job execution complies with the
requirements and serves the intended function to satisfactory level.
2 SCOPE
This procedure covers various work procedures contained within project control
documents which explains and covers the installation, termination of cables and
wires
3. RESPONSIBILITY
4. Tool / Equipment
On receipt of the cables, wires and accessories at site necessary precautions shall be
taken for unloading shifting and storage as follows.
5.2 All materials received at site shall be inspected and ensured that the materials are as
per approved material submittal.
5.3 any discrepancies damage etc found will be notified and reported for further action
5.4 Material found not suitable for use will be removed from site immediately
7. INSTALLATION PROCEDURE
Step 1
Ensure that the work area is ready and safe to start the installation of cables and
wires
Ensure that cables and wires installation is carried out in accordance to
manufactireres installation recommendations, requirement, of applicable standards
and in accordance with recognized industrial practises and specified in project
specification to ensure that installation complies with requirements.
Prior to start the installation refer to the approved shop drawings related to the area
of installation and ensure that required materials are available at site store. All
materals and accessories should also be free of dust scale or oil
Ensure that the issued materials are of approved specification submittals and as per
the requirements of the area shop drawings
Care shall be taken to avoid direct exposure to solar radiation in storage area and at
installed area.
Wrenches shall not be used to pull cables
Don’t install through joints in cables
Don’t avoid route cables below water services pipework
Ensure that the cabling wiring is being installed as per approved drawings
All the containment system checked for thoroughness and cleanliness all along the
circuit
All the routing or wiring is to be drawn from respective distribution boards to point of
utilization and is looped from live and netral terminals of accessories for circuit
continuation as per the approved shop drawings
Final connections in luminaries and heat producing or emitting equipment shall be
made using heat resistant flexible cables
The specified wire sizes to be followed as per approved load schedule or shop
drawings
Ensure that proper color coding is followed for phase, neutral, earth wires as per
standard electrical codes and respective approved shop drawings and specifications
Ensure that each circuit is being neatly dressed or bunched at intervals
After dressing of wires, provide the respective circuit ferrules at the ends at phase,
neutral and bar ends
The cable or wires should not be jointed, those should be continuous
Wires shall not exceed the capacity of the conduit or trunking, the installations shall
comply strictly by following the standard rules and regulations
Wires shall be combined as installation proceeds and the neutral, earth conductor
shall be run with the phase wires of that circuit
Wires of one circuit shall run in the same conduit
Each wires of the circuit running in the trunking shall be grouped together with cable
ties
Do not install wiring of more than one phase in an outlet box or switch box other than
one designated for multi phase use
The color coding of wires or cables shall be followed till the termination within
distribution boards and equipments
ATTACHMENTS
Risk assessment
Inspection and test plan
Quality control procedure
Check sheets