Software Project Management Unit 5
Software Project Management Unit 5
com
UNIT 5:
RESOURCE ALLOCATION
ER . RAJAN KARMACHARYA
DEPARTMENT OF CSIT
ST. XAVIER ’ S COLLEGE , MAITIGHAR
Includes…
1. Prelude, The nature of resources, identifying
resource requirements
2. Scheduling resources creating critical paths,
counting the cost, being specific
3. Publishing the resource schedule, cost
schedule, the schedule sequence
For more notes visit https://collegenote.pythonanywhere.com
After the activities have been identified using various techniques and tabulated into a Work-Break-Down the
resources need to be allocated to complete the identified tasks. This process is considered resource allocation
The final result of resource allocation will normally e a number of schedules including………
Activity schedule >> indicating the planned start and completion dates for each activity
Resource schedule >> showing the dates on which each resource will be required and the level of that requirement
Cost schedule >> showing the planned cumulative expenditure incurred by the use of resources over time
0 Select project
3 Analyse project
characteristics
4 Identify the
products and activities
Review
5 Estimate efforts
for activity For each
Lower level activity
detail
6 identify
activity risks
9 Execute 8 Review/
ER. RAJAN KARMACHARYA plan publicize plan 3
For more notes visit https://collegenote.pythonanywhere.com
Project Manager
Concentrate on resources where there is a possibility that, without planning, they might not be sufficiently
available when required.
Senior Software Developers are the hardest to find – these need to be very carefully planned for in advance.
Developers do not like to wait for work, they prefer to be busy with activities and tasks that show clear
progress.
RESOURCE ORGANIZATION
RESOURCE SCHEDULING
After all the required resources have been identified, they need to be scheduled effectively.
The earliest start dates, last start dates will need to be taken into account to schedule resources
efficiently.
Resources should be balanced throughout the project.
Human resource scheduling issues,
Planned Leave, Public Holidays.
Possible sick leave (random, subjective at best and hard to predict).
General motivation and enthusiasm for the task allocated (If they dislike the task, it will flow
through into the output).
Work load and stress in project.
Stress outside work.
RESOURCE SCHEDULING
After all the required resources have been identified, they need to be scheduled effectively.
The earliest start dates, last start dates will need to be taken into account to schedule resources
efficiently.
Resources should be balanced throughout the project.
Human resource scheduling issues,
Planned Leave, Public Holidays.
Possible sick leave (random, subjective at best and hard to predict).
General motivation and enthusiasm for the task allocated (If they dislike the task, it will flow
through into the output).
Work load and stress in project.
Stress outside work.
RESOURCE HISTOGRAMS
Category Vs Week
RESOURCE HISTOGRAMS
EXTERNAL DEPENDENCIES
When planning any resources that rely on external factors, these need to be planned with the
associated risks involved.
PRIORITISATION TECHNIQUES
Activities that can proceed at the same time are ordered according to a set of simple criteria.
Burman’s priority list takes into account activity duration as well as total float:
1. Shortest critical activity.
2. Critical activities.
3. Shortest non-critical activity.
4. Non-critical activity with least float.
5. Non-critical activities.
Note: Other ways of ordering are also possible.
COST OF RESOURCES
All projects concentrate on completion in the shortest time span with minimum resources (in
planning stage).
However, once the project starts – all un-planned for issues and any risks will cause some strain on
the cost.
COST SCHEDULING
Weekly or monthly cost over the life of the project which will provide a more detailed and accurate
estimate of costs and will serve as a plain against which project progress can be monitored.
Broad Categories
Staff Costs: (staff salaries, social security fund, pension scheme contribution, holiday pay)
Overheads (Office Space, Interest charges, Travel Costs, Insurance and so on).
Usage charges (for external resources or contractors, leased/rental equipment).
SCHEDULING IN PRACTICE
It should always be in the project planner’s mind, right from the start of the project.
During the resource scheduling and allocation phase of the planning activity a lot of the plan will
change.
Most of the issues with respect to resource allocation and scheduling arise after the project starts
(normally after about 30% of the activities are complete).