Pre-Energization Check List
Pre-Energization Check List
Pre-Energization Check List
`
Doc. No:
Page NO: Pre-Energization CheckList
DATE :
Status Remark
S. N Item
Yes No N/A
The categorization of punch list (A/B) is finalized, and all
1.
Type A snags of the subject equipment are cleared.
2. All equipment are properly labeled.
All tests results for the below equipment are signed by the
T&C Contractor and Owner staff.
3.1 AIS Equipments
3.2 Power Transformers
3.3 MV Switchgear
3.4 Auxiliaries (AC & DC Panels, Batteries & Battery
3. Chargers, Auxiliary Transformers, and UPS)
3.5 SVG
3.6 SAS (Open-loop test, and Close loop test)
3.7 SCADA (Close-loop test of Conventional Substations)
3.8 Under Ground Cables / Overhead Lines
3.9 Protection Panels (including Final Trip Tests)
3.10 Control Panels
4.1 Repeated Punch List (if any)
4.2 Scanned soft colored copy of marked up drawings
4.3 Native files of the protection relays
4. 4.4 Scanned soft colored copy of all site test results
4.5 Original copy plus one soft copy of final settings
review documents
4.6 SAS handover documents
CT Circuits Normalization :
- Make sure that all CT circuits are connected, shorted,
isolated, and single point earthed as per the marked-up
5. drawings.
- Ensure proper connections and tightness for all CT
circuits by a screwdriver, and pull each wire gently to
ensure that all CT wires terminated properly.
VT Circuits Normalization :
- Make sure that all VT circuits are connected, and
isolated as per the marked-up drawings.
6.
- Ensure proper connections and tightness for all VT
circuits by a screwdriver, and pull each wire gently to
ensure that all VT wires terminated properly.
Power Transformer & Outdoor Equipment :
7.1 Ensure that there is no temporary grounding or
shorting between phases of any transformer winding (high
7. side, low side)
7.2 Confirm that all covers of mechanical protection,
outdoor boxes, and panels are properly closed, tighten,
and sealed.
200MW KOM OMBO S/S
`
Doc. No:
Page NO: Pre-Energization CheckList
DATE :
Auxiliaries:
- Confirm that there is no temporary shorting or grounding
available at auxiliary transformer
8. - Confirm that no oil leakage from the auxiliary
transformer.
- Tap changer of the auxiliary transformer is set on the
normal tap.
Alarms:
9. - Make sure that there are no alarms on annunciators,
relays, and SAS HMI (as applicable).