Psoc Nov 2020
Psoc Nov 2020
Seventh Semester
Electrical and Electronics Engineering
(Regulations 2017)
Time: 3 Hours Answer ALL Questions Max. Marks: 100
PART- A (10 x 2 = 20 Marks)
8. What are all the points to be noted for an economic load dispatch including transmission
losses?
PART- B (5 x 13 = 65 Marks)
11. a) Explain the basic P-f and Q-V control loops in power system with relevant block
diagram. (13)
OR
1
b) A generation station of 1MW supplied a region which has the following demands:
Neglect transmission line losses and find the following: i) Plot the daily load curve
and the load duration curve. ii) Find the load factor, the reserve capacity, plant
capacity factor, plant use factor, the hours that the plant has been off and
utilization factor. (13)
12. a) Derive the transfer function of an uncontrolled load frequency control of a single
area system and derive the expression for static error following a step load change.
(13)
OR
13. a) The load at receiving end of a 3phase overhead line is 30 MW, 0.8 pf lag at the
line voltage of 66kV. A synchronous compensator is situated at sending end and
the voltage at both ends of the line is maintained at 66kV. Calculate the MVAR of
compensator. The line has a resistance and reactance of 6Ω/ph, 24 Ω/ph,
respectively. (13)
OR
b) Two sub-station are connected by two lines in parallel with negligible impedance,
but each containing a tap-changing transformer of reactance 0.22pu on the basis of
its rating of 200 MVA. Find the net absorption of reactive power when the
transformer taps are set to 1:1.08, and 1:0.95 respectively. Assume pu voltages to
be equal at the two ends. (13)
2
14. a) A power plant has two units with the following cost characteristics:
C1 = 0.6 P1 2 + 200 P1 + 2000 Rs / hour
C2 = 1.2 P2 2 + 150 P2 + 2500 Rs / hour
where P1 and P2 are the generating powers in MW. The daily load cycle is as
follows:
6:00 A.M. to 6:00 P.M. 150 MW
6:00 P.M. to 6:00 A.M. 50 MW
The cost of taking either unit off the line and returning to service after 12 hours is
Rs 5000. Considering 24 hour period from 6:00 A.M. one morning to 6:00 A.M.
the next morning. i) Compute the economic schedule for the peak load and off
peak load conditions, ii) Calculate the optimum operating cost per day.
(13)
OR
15. a) With the help of flowchart explain briefly how the system states are continuously
monitored and controlled. (13)
OR
b) Explain the hardware components and functional aspects of SCADA system using
a fundamental block diagram. (13)
PART- C (1 x 15 = 15 Marks)
16. a) There are three thermal generating units which can be committed to take the
system load. The fuel cost data and generation operating unit data are given below:
F1 = 392.7 + 5.544 P1 + 0.001093 P12
F2 = 217 + 5.495 P2 + 0.001358 P22
F3 = 65.5 + 6.695 P3 + 0.004049 P32
P1, P2, P3 in MW Generation limits:
150 ≤ P1 ≤ 600 MW;
100 ≤ P2 ≤ 400 MW;
50 ≤ P3≤ 200 MW
There are no other constraints on system operation. Obtain an optimum unit
commitment table. Adopt Brute force enumeration technique. Show the details of
economic schedule and the component and total costs of operation for each
3
feasible combination of units for the load level of 900 MW.
(15)
OR
The load on the system is 60 MW. Compute the power dispatch for λ = 120 Rs /
MWh. Calculate the transmission loss. Also determine the power dispatch with the
revised value of λ taking 10 % change in its value. Estimate the next new value of
λ. (15)
__________________