2.NOTES-Introduction To The Construction Process - (BWT110 - S1 - 2020 (2of4) )
2.NOTES-Introduction To The Construction Process - (BWT110 - S1 - 2020 (2of4) )
2.NOTES-Introduction To The Construction Process - (BWT110 - S1 - 2020 (2of4) )
DEPARTMENT OF
CONSTRUCTION ECONOMICS
PART 2:
INTRODUCTION TO
THE CONSTRUCTION PROCESS
DATE OF LAST
REVISION: JANUARY
2020
BWT 110 PART 2: STUDY THEME 2
INTRODUCTION TO THE CONSTRUCTION PROCESS
The general objective of the study theme is to provide you with a basic
understanding of the pre- and post contract processes involved in the construction
of buildings
LEARNING OUTCOMES:
ADDITIONAL READING:
There are no additional requirements for this study theme, but the work done in
BGG121 will help to explain this part in greater depth, and should be studied
simultaneously
2
1. STEPS IN THE DEVELOPMENT PROCESS
The decision to construct a building or develop a property is not lightly taken as it involves a lot of
money, effort and risk. Property development, which includes construction, usually comes about
because an individual or organisation identifies a need for additional accommodation (residential,
commercial, institutional, etc.), or a landowner or developer spots an opportunity to provide for a
need in the market by erecting a building for letting or selling to end-users at a profit.
Once it is decided to investigate further whether or not the development or construction should be
proceeded with, the steps usually are as follows:
3
1.2 CONSTRUCTION OR POST-CONTRACT PHASE
After signing of the building contract the contractor takes possession of the site for the duration of
the contract. This is done formally through a site hand over meeting. At this meeting times and
agendas for future meetings are usually agreed, boundary pegs and datum level benchmarks are
pointed out to the contractor (after which he takes responsibility for their maintenance and
protection) and samples of brickwork, etc. are asked for to set acceptable standards.
There are standard procedures for contract administration. These include holding regular (weekly,
fortnightly or monthly) site meetings where progress, quality, contractor’s queries and information
needs, etc. are monitored and discussed in order to facilitate the smooth flowing of the project.
There are also procedures for claims from the contractor, variations required by the employer,
interim progress payments to the contractor, and for practical and final completion of the contract.
First the right professional team has to be selected, appointed and briefed. Selection could
happen on the basis of recommendation, existing/previous relationships or
competitions/calls for proposals.
The second part involves securing a main contractor to assume responsibility for execution
of the actual construction work at the right price and under the supervision of the professional
team.
The procurement (tender) and contract documentation on a building project usually consists
of the following:
Specification:
Drawings Standard Description of work
And + = to be done
Project or
schedules
particular
4
3. BUILDING DRAWINGS
3.1 INTRODUCTION
Building drawings form part of tender and contract documentation, which is required among other
things to:
communicate to all parties a common understanding of what needs to be done, and their role in
it
regulate the roles, responsibilities and relationships between parties to the development
record agreements and ensure those agreements are kept to
Because drawings provide the visual description of the works that contractors need to “read” to be
able to execute the construction of the project, they need to contain all the necessary information,
and at the same time be clear, uncluttered, properly dimensioned, and drawn to a scale that is legible.
Visual presentations of concepts for appraisal and approval by clients, investors, financiers,
and for marketing
Quantification of the work for estimating purposes
Preparation of tenders
Obtaining approval to build from local authorities
Construction
Calculation of variations and final accounts
A record of what was built for future property management and maintenance purposes
1. Sketch plans
2. Perspective drawings and presentation drawings
3. Location plans
4. Site plans
5. Key plans
6. Detailed floor plans
7. Elevations
8. Sections
9. Construction details
10. Sewerage plans
11. Water reticulation layouts
12. Structural details
13. Electrical reticulation layouts
14. Mechanical details
15. Fire protection plans
Designs and details of buildings are frequently changed during construction. To ensure that after
completion of the project the employer has a true record of how the building was actually built, and
where the different services run (for maintenance purposes, etc.) the design team will usually prepare
a set of drawings called:
5
16. "As built" drawings
Some of the more common kinds of drawings and schedules are more fully described below.
(Building drawing will be studied in more detail in the second semester module BOU 120)
Sketch plans:
Example:
6
SCALE, CONTOURS, DATUM LEVELS, BUILDING LINES:
7
8
Perspective and presentation drawings:
Location plans:
Site plans:
Example:
9
Key plans:
Indicates portion of building or building detailed on that particular drawing - large projects
only
Horizontal section showing structure as seen from a point somewhere above floor level
(position and size of walls, columns, lift shafts, ducts, stairs, cupboards, doors and windows,
etc)
Dimensions to enable contractor to lay out walls, etc.
Levels
Sections:
Vertical section – cut-away view through structure inside (foundations, floors, walls, columns,
slabs, roofs, etc) showing vertical dimensions and type of construction
Elevations:
Vertical views of front, back, and sides of buildings as seen from outside
Dimensions, levels, heights
Doors, windows, finishes
Levels
Slope of ground
10
Example:
11
Drainage plans (waste, sewerage, storm water):
Water, electrical reticulation, air conditioning and fire protection layouts, etc:
Construction details:
Where it is not practical to show intricate details clearly on the plans, sections or elevations
themselves, the relevant part is marked and referred to a detail drawing where it is drawn in
full detail on a larger scale
If all the detailed information required for construction were to be put directly onto the drawings, they
would be far too cluttered to be legible. More detailed descriptions of materials, etc. are therefore,
provided in text form in separate specifications. Doors, windows, cupboards, sanitary fittings, etc. are
indicated on drawings in simplified form and referred back to more detailed schedules by code.
12
Example of an item on a window schedule:
13
What is a specification?
One dictionary definition of specification reads: "...details, instructions, etc. for the design and making
of something".
In the case of building projects, the specification is a comprehensive and detailed description of the
type and quality of materials and components to be used, and the
standards of workmanship required. It is a communication tool between the parties involved, and
supplements the architect's or engineer's drawings with information which cannot be clearly or easily
shown on the drawings. Sometimes, on smaller projects or often in the case of repair/renovations
and maintenance contracts, there are no drawings and the specification serves as the only description
of the work to be done.
Buildings are divided into elements (e.g. foundations, structural frame, external envelope, roofs, internal
divisions, internal plumbing, etc.) An element is that part of a building that always performs the same
function irrespective of its construction or specification. It doesn’t matter for instance that the external
envelope of a building is made of brick walls and steel windows, or of reinforced concrete walls, or of
steel/aluminium curtain walling, or of corrugated iron cladding for that matter; it would still be seen as the
element external envelope, because its function remains the same – that of enclosing the building for
protection against the elements, and security and privacy of the occupants.
Each element is further sub-divided into components e.g. the element external envelope could be divided into the
components: brick and block walling, external finishes, windows, doors, etc. The method of division and sub-division
is defined and consistent for all buildings.
Note that this method of dividing up a building into smaller parts differs fundamentally from the method used in the
standard measurement method for bills of quantities, where work is divided into “trade bills”.
In the elemental method for instance there could not be an element such as “Concrete Work”. Concrete work can
occur in more than one element, for instance in the element:
“Brick walls” could likewise not be an element. Brick walls can occur in the element:
Trades on the other hand refer to particular types of work done by artisans or tradesmen trained in that
particular type of work, for instance:
A bricklayer is an artisan trained in the trade of bricklaying (included in the trade bill “masonry”
in the standard system of measurement)
A carpenter is an artisan trained in the trade of carpentry
A tiler is an artisan trained in the trade of tiling, and so forth
14
TYPICAL BUILDING ELEMENTS:
15
5. STEPS IN THE CONSTRUCTION OF A SIMPLE BUILDING
1. PRE-CONSTRUCTION PHASE
1.1 Obtain the site/property and register transfer at the deeds office (owner / employer with estate agent and
lawyer)
1.2 Determine position of erf boundaries and corner pegs, prepare contour plan if required
1.3 Do geotechnical investigation if necessary (owner with geotechnical engineer)
1.4 Apply for re-zoning, consent use, relaxations, etc. if required (owner with townplanner)
1.5 Prepare sketch plans (owner with architect)
1.6 Prepare cost estimates (owner with quantity surveyor)
1.7 Prepare and submit building plans for scrutiny by city council (owner with architect)
1.8 Apply to bank for building loan
1.9 Prepare documents (plans, specification, contract), call for tenders and appoint building contractor (owner
with architect and quantity surveyor)
1.10 Ensure that contractor complies with pre- contract obligations
-guarantees/surety
-proof of insurance
-building programme
-priced bills of quantities (if applicable}
-authorisation of signing powers
1.11 Signing of building contract (owner andcontractor with architect and quantity surveyor)
1.12 Formal handing over of site to contractor
-point out pegs and benchmarks
-provide 3 sets of documentation
-agree format and schedule of site meetings
NOTE: EXTERNAL WORK LIKE DRIVEWAYS AND WALKWAYS, PAVING, GARDENING, ETC. IS
CARRIED OUT CONTINUOUSLY
17
3.2 By professional team (with inputs from contractor as required):
3.2.1 Contract management and administration:
- Site and other meetings
- Flow of information and documentation required by contractor
- Progress payments
- Cost reports to owner
- Variations and claims
- Supervision and monitoring of quality, progress, etc.
- Preparation of final account by quantity surveyor for signing by owner and contractor
The above information is processed into a building programme for the work
Purpose:
a) To record agreed intentions with the client
b) To supply a time table for co-ordinating the issue of drawings and information, the
placing of orders and deliveries of materials, and the operation of plant and
subcontractors
c) To prepare for the basis for the introduction of an incentive scheme where used
d) Show the sequence of operations and the total output rates required of labour and
plant
e) To provide an indicator for progressing and costing
f) To furnish the promoter with the likely financial requirements
g) To discourage changes in design by indicating the natural consequences, whilst at
the same time facilitating amendments and minimizing their harmful effects should
changes arise
Process (SIMPLIFIED)
List each discrete activity
Quantify amount of work that goes into each activity
Determine resources (labour, plant, etc.)
Work out how long each activity should take
Determine critical path and put activities on the path in sequence ( with earliest and
latest start and finish dates
Determine overlaps, float times etc. and fill in rest of activities
Present in visual form (bar chart / Gannt chart)
18
Example of construction programme
19