002 - Method Statement - Clearing and Grubbing
002 - Method Statement - Clearing and Grubbing
GRUBBING WORKS
PROJECT NO : 57/2023
REVISION CONTROL
Second Issue
01 26.02.2024
for Approval
Mohamed Fadel Mohamed Fadel Shoukat Riaz
Doc. No: BGC-MS-02Rev01 Page 1 of 10 Method Statement for Clearing and Grubbing
INDEX
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
7.0 PROCEDURE
Doc. No: BGC-MS-02Rev01 Page 2 of 10 Method Statement for Clearing and Grubbing
2.0 SCOPE
This work shall consist of cutting, excavation, removing and disposing of all materials such as trees of
girth up to 300 mm, bushes, shrubs, stumps, roots, grass weeds, rubbish etc. and top soil up to 150mm
declared unsuitable by the Authority Engineer, including draining out stagnant water if any from the
area of road land, drain, cross drainage structure and other area as specified in the drawing or
instructed by the Engineer.
3.0 REFERENCES
a) Contract Agreement
b) IFC
c) Approved Drawings
4.1 ABBREVIATIONS
4.2 DEFINITIONS
Doc. No: BGC-MS-02Rev01 Page 3 of 10 Method Statement for Clearing and Grubbing
Doc. No: BGC-MS-02Rev01 Page 4 of 10 Method Statement for Clearing and Grubbing
He shall be overall responsible for safe execution of the complete activity including, but not limited to:
a) Organizing tools and equipment required to the work site.
b) Assigning work crew.
c) Sequence of activities to be carried out for the work as per this work procedure.
d) Stage Inspection & Surveillance.
e) Ensure all safety Regulations are followed as applicable.
f) Contract specific requirements for excavations, if any specified shall be identified and the requirements of
such specification shall prevail in addition to the non-conflicting requirements of this procedure.
g) Ensure & study the approved drawings & statements before starting the activity.
h) Communicate all HSE requirements to the entire working crew and ensure that they understand.
i) Thoroughly familiar with all MODES/RAY contract and general HSE requirements and understand it to
maintain a healthy and safe environment for employees and contract staff.
5.4 NOC Officer
5.6 Surveyor
a) Ensure all P & M Equipment being used for the activity are in good working condition.
b) Ensure P & M Operators are qualified & authorized to operate the relevant equipment.
c) Ensure the work area shall be barricaded.
d) The toolbox talk shall be carried out before starting the work.
e) Ensure all necessary PPEs are worn by workers involved in the work.
Doc. No: BGC-MS-02Rev01 Page 7 of 10 Method Statement for Clearing and Grubbing
a) Grader
b) Excavator / J.C.B
c) Skid Loader
d) Tractor Trolley
e) Rollers
f) Water tankers
g) Survey Kit / Instrument
h) Dozer
7.0 PROCEDURE
7.1 General
The following documents as a minimum shall be readily available for ready reference at work site.
Client specifications
Approved Method statement
Issued for Construction drawing &
Approved Material approval sheet
a.1.1 The toe line shall be established, with reference to the alignment based on the levels
taken earlier. The area for clearing & grubbing shall be demarcated, covering areas
of road embankment, drains, cross drainage structures and such other areas as
specified in relevant approved drawings
a.1.2 Trees up to 300 mm in girth and stumps and roots falling within the construction
zone shall be removed by the suitable equipment’s or by manual labours as per site
requirements.
a.1.3 The Grader / Excavator / Dozer shall be deployed to remove all shrubs,
bushes, vegetation, grass, weeds, rubbish and top organic soil up to 150 mm in
thickness, which is unsuitable for incorporation in the permanent work.
a.1.4 The above machines & tools shall be deployed to carry out the Clearing &
Grubbing operation and the bushes, stumps falling within proposed construction
shall be cut to the depth below ground level that in no case these fall within 500
mm of the sub grade. Also all vegetation and deleterious matters unsuitable for
incorporation in the embankment & sub -grade shall be also removed between fill
lines.
a.1.5 All branches of the trees extending above the highway shall be trimmed.
Doc. No: BGC-MS-02Rev01 Page 8 of 10 Method Statement for Clearing and Grubbing
b) Disposal of materials
b.1.1 Materials collected from Clearing and Grubbing is disposed-off to the suitable places.
b.1.2 Stacking of cleared stumps, branches & boulders shall be done neatly at the appropriate
location up to a lead of 1000M.
c) Work Safety
Safety aids shall be mobilized in required number to take care of the workers & of the adjoining road users.
c.1.1 All locations adjacent to the existing road where clearing & grubbing is progressing shall be
provided with visible safety & road signs.
c.1.2 Minimum of two flagmen with reflective vests holding a red flag each shall be deployed to
control the traffic wherever required during clearing & grubbing operations.
c.1.3 No machines or equipment’s shall be permitted to remain on the existing road or Shoulder
unattended unless it is properly protected &secured in a safe manner.
c.1.4 The Safety Officer frequently patrols at construction zones of project highway to ensure the
safety of equipment, workers & road users and safety signs are operational at all time.
d) Environmental Safety
d.1.1 Deleterious matters detrimental to the environment shall be disposed-off as directed by AE at
the designated locations provided by the Authority.
d.1.2 Vehicles tracks shall be kept moist to prevent flying of dust particles with the vehicle
movement.
Doc. No: BGC-MS-02Rev01 Page 9 of 10 Method Statement for Clearing and Grubbing