Ullah 2009
Ullah 2009
Ullah 2009
Abstract—This paper examines the possibility of providing reac- wind turbines (WTs) can also provide temporary primary fre-
tive power support to the grid from wind farms (WFs) as a part of quency regulation and oscillation damping, as discussed in [9].
the ancillary service provisions. Detailed analysis of the WF capa- In the literature, reactive power as an ancillary service has
bility curve is carried out considering maximum hourly variation
of wind power from the forecasted value. Different cost components been mainly examined in the context of large thermal genera-
are identified, and subsequently, a generalized reactive power cost tors [10], [11], and not much work has been reported that exam-
model is developed for wind turbine generators that can help the ines how wind generators could contribute to system reactive
independent system operator (ISO) in managing the system and power requirements. Reactive power provision from wind farms
the grid efficiently. Apart from the fixed cost and the cost of loss (WFs) is rarely procured by the independent system operators
components, a new method is proposed to calculate the opportu-
nity cost component for a WF considering hourly wind variations. (ISOs). However, with increasing penetration of wind gener-
The Cigré 32-bus test system is used to demonstrate a case study ators into the power grid together with the increasing usage
showing the implementation of the developed model in short-term of power electronics in turbines, WFs could be useful reactive
system operations. A finding is that higher wind speed prediction power service providers in the future. Due to the advancement
errors (a site with high degree of wind fluctuations) may lead to in wind forecasting techniques in recent years, together with
increased payments to the WFs for this service, mainly due to the
increased lost opportunity cost (LOC) component. In a demon- the power smoothing effect within a WF, the WFs can now be
strated case, it is found that 2340 $/h is paid to the WF as the LOC considered as a dispatchable power source by the system oper-
payment only, when the wind prediction error is 0.5 per unit (p.u.), ators [12], [13]. Consequently, the reactive power support from
whereas 54 $/h is the expected total payment to the WF when the the voltage-source converters (VSCs) of WFs can also be treated
prediction error is 0.2 p.u. for its reactive power service. as dispatchable by the operators.
Index Terms—Ancillary service, reactive power, variable-speed The capability curve of these units needs to be defined taking
wind turbine (VSWT), voltage-source converter (VSC). the wind variations into account. Different cost components
associated with reactive power generation by these units need to
I. INTRODUCTION be examined as well. A knowledge of these cost components will
ARIABLE-SPEED wind turbines (VSWT) with power assist the ISO in formulating appropriate financial compensation
V electronic converters are increasingly penetrating the
power systems because of their flexibility in controlling the
mechanisms for their reactive power service provision. When
these issues are answered, WFs with reactive power capability
response of the turbine. In recent years, researchers have exam- can be treated by the ISOs as reactive power ancillary service
ined these wind turbine generators extensively, with regard to providers.
their grid integration issues and control of the converters [1]–[4]. The main objectives of this paper are to propose compre-
In the context of deregulation of the electricity sector, the market hensive technical models and detailed cost representation of
dispatch aspect of wind turbine generators and their role have reactive power generation from WFs. The research focusses on
also been studied [5], [6]. the development of the capability curve of a VSWT-based WF
In addition to providing active power to the grid, the wind with full-scale power electronic converter, and hence its reac-
generators with power electronic convertors can also provide tive power production taking into consideration the currently
reactive power to the system by incorporating minor modifica- existing grid codes and the wind variability factor. Representa-
tions to their design and/or control architecture [7], [8]. These tion of different cost components, and hence the development
of a reactive power cost model for WFs that can be used by
Manuscript received April 22, 2008; revised July 9, 2008. First published the ISOs for procurement of reactive power ancillary services
January 27, 2009; current version published August 21, 2009. This work was from these units is examined. A new method for defining the
supported by E.ON Sverige AB’s Research Foundation. Paper no. TEC-00137- lost opportunity cost (LOC) for WFs is proposed that takes the
2008.
N. R. Ullah was with the Department of Energy and Environment, Chalmers wind fluctuations into account. The goal is to consider WF sites
University of Technology, Göteborg 412 96, Sweden. He is now with E.ON with different degrees of wind power prediction errors and its
Elnät AB, Malmö 205 09, Sweden (e-mail: [email protected]). consequences on the payment to WFs for the reactive power.
K. Bhattacharya is with the Department of Electrical and Computer En-
gineering, University of Waterloo, Waterloo, ON N2L 3G1 Canada (e-mail: The paper is organized as follows. Section II provides the de-
[email protected]). tails of the development of the reactive power capability curve
T. Thiringer is with the Department of Energy and Environment, Chalmers of a WF considering wind variations under different grid con-
University of Technology, Göteborg 412 96, Sweden (e-mail: torbjorn.
[email protected]). nectivity standards. Section III identifies different cost compo-
Digital Object Identifier 10.1109/TEC.2008.2008957 nents (fixed cost, cost of loss, and LOC) associated with reactive
B. Limiting Factors
The grid-side converter (GSC) has a certain maximum
current-carrying capacity, which will impose a limit on the P -
and Q-capability of the turbine. In the PQ plane, it will be a cir-
cle similar to that of the armature current limit of a synchronous
generator, as shown in Fig. 3. The relationship between the
active and reactive power at the converter current limit is
P 2 + Q2 = (Vg Ic )2 (1)
where Ic is the converter current.
The converter voltage Vc will impose another limit on P -
and Q-capability of the wind turbine, which is similar to that
of the field current limit of a synchronous generator. Based on
these analogies of the capability curve of a wind turbine with
full power converter (see Fig. 1) with that of a conventional
synchronous generator [14], the relationship between P and Q
Fig. 2. Typical wind park layout considered in this paper. at the converter voltage limit is given by
2 2
2
Vg2 Vc Vg
power support from a WF. Section IV brings out the various cost P + Q+ = (2)
X X
components of reactive power from WFs, and then proposes a
unified cost model for the same, which can be used by ISOs where X is the total equivalent reactance from the wind turbine
in the procurement of these services. Section V presents a case low-voltage terminal to the grid connection point (see Fig. 2).
study demonstrating the integration of the WF reactive power Equation (2) represents a circle in the PQ plane with center (c)
capability (Q-capability) in short-term system operations. and radius (r) given as
Vg2 Vc Vg
II. REACTIVE POWER (Q) CAPABILITY OF WFS UNDER c = 0, − , r= . (3)
X X
DIFFERENT GRID CODES
A. Investigated WF Layout C. Design Values
A VSWT with a full-scale power electronic converter is Grid codes of utilities often require a WF to be able to op-
shown in Fig. 1, where Ic is the converter current. The typi- erate continuously at the rated value at a certain power fac-
cal layout of a WF is shown in Fig. 2 wherein Vg , P , and Q tor (pf) within a certain band of voltages and frequencies
represent the voltage at the grid connection point, WF active and at the grid connection point, see [15] and [16], for exam-
reactive power production at the grid connection point, respec- ples. Let us define the upper and lower values of voltage and
tively. Vc represents the converter voltage, which depends on frequency as Vg ,m ax = 1.05, Vg ,m in = 0.9, fm ax = 1.01, and
the dc-link voltage of the converter (Vdc ), the modulation tech- fm in = 0.98, respectively [all in per unit (p.u.)], and the rated
nique used, and the amplitude modulation index [4]. For a given pf as cos θR , where θR is the rated pf angle of the WF. These
ULLAH et al.: WIND FARMS AS REACTIVE POWER ANCILLARY SERVICE PROVIDERS—TECHNICAL AND ECONOMIC ISSUES 663
TABLE I
Ic , m a x , V c , m a x , P c , m a x , AND V d c , m a x FOR DIFFERENT DESIGN CASES
Fig. 6. Maximum capacitive reactive power capability with different design cases are summarized in Table I. In the table, the corresponding
pf as a function of wind speed. Approximate active power is also shown. maximum dc-link voltage is also given [calculated from (9)].
Note that converter voltage limitation will not occur if the
converter maximum voltage Vc,m ax is such that (from Fig. 3)
Vc,m ax Vg Vg2
≥ + Vg Ic,m ax
X X
⇒ Vc,m ax ≥ Vg + Ic,m ax X. (14)
Within the continuous operating region of the WF, if Vc,m ax ≥
1.4 (i.e., Vdc,m ax ≥ 2), then the converter voltage will not im-
pose any limit on the capability of the WF, only the converter’s
maximum current-carrying capacity will limit its capability. See
Fig. 7(b) for the new set of capability curves where voltage limit
does not occur. Note that the reactive power margin of the WF
Fig. 7. (a) WF’s capability diagram for different design pf values when V g = will largely depend on the initial reactive power output from the
1.0 p.u. (b) WF’s capability diagram for different design pf values at V g = 1.0 WF.
when the converter voltage limit does not occur.
TABLE II
INVESTMENT COST OF SOME WFS [21]–[23]
the total losses in the GSC for the three transistor legs become
Ploss,GSC = 3(Pc + Ps,T + Ps,D ). (26)
Fig. 9. Model of the transistor (T) and the reverse diode (D) of each switch
Equation (26) can also be written as
for the loss modeling of the converter. 2
Ploss,GSC = al Irm s + bl Irm (27)
s
TABLE III where al and bl are the power module constants and can be
EXTRACT FROM SEMIKRON POWER MODULE SKIIP 1803GB172-3DW DATA
SHEET [26]
expressed as
√
6 2 EON + EOFF Er r
al = VIGBT + fsw + fsw (28)
π IC ,nom IC ,nom
bl = 3rIGBT . (29)
The increased active power loss (∆Ploss ) due to the increased
reactive power production can be expressed as
∆Ploss = al (Irm s,1 − Irm s,0 ) + bl (Irm
2
s,1 − Irm s,0 )
2
(30)
where Irm s,1 and Irm s,0 are the rms values of the current with
and without the increased reactive power, respectively, and can
be calculated as follows:
B. Cost of Losses
P02 + Q2m an
The additional active power losses incurred by the WF be- Irm s,0 = (31)
Vg
cause of increased reactive power demand from the ISO need to
be calculated for financial compensation purpose, if it accounts P12 + Q21
Irm s,1 = . (32)
for a significant value. In cases where the reactive power de- Vg
mand is met by the grid-side VSC of the built-in back-to-back In (31) and (32), P0 and P1 are the active power produc-
converter of WTs, as considered in this paper, the additional ac- tion before and after the increased reactive power production
tive power losses due to increased reactive power supply from (P0 ≥ P1 ), respectively, Qm an is the mandatory reactive power
the WF mainly occur in the GSC switches and the resistances production set out by the grid connectivity standard or by the
of transformers/cables. grid code, and Q1 is the enhanced reactive power production
Each switch of the GSC consists of a transistor (T) and a (Q1 > Qm an ).
reverse diode (D). The losses of a converter is divided into The power module, whose parameters are shown in Table III,
switching losses and conduction losses. The switching losses of can be seen as a 1-MW module when connected to a 690-V
the transistors are due to turn-on and turn-off losses, while for grid and 900 A is taken out of it. The losses are calculated as a
diodes, these are due to the turn-off losses [24]. The turn-on and percentage of the rated power of the converter for the following
turn-off losses for transistors and diodes can be found from data scenarios, assuming unity pf design case and Vg = 1.0 p.u.:
sheets. The conduction losses arise from the current flowing 1) rated operation, unity pf. Loss = 1.15%;
through the transistors and diodes. 2) 50% rated operation, unity pf. Loss = 0.52%;
For the purpose of modeling of losses, the transistors and 3) 50% rated operation, 0.9 pf. Loss = 0.58%.
diodes can be modeled as constant voltage drops (VC E O and The losses in the power module increases by 12% when 25%
VT O ) with series resistances (rC E and rT ; see Fig. 9) [25]. The reactive power is supplied at 50% rated operation in scenario 3
calculation of losses of a typical industrial power module used as compared to scenario 2. The increase in active power loss is
in WTs is presented in [25]. Different parameters of the power 0.06% of the rated or the base value. On the other hand, when
module are shown in Table III [26]. the reactive power demand is met by reducing the active power
The conduction and switching losses can be expressed as [25] production (reducing the active power production to 50% of the
√
2 2 rated value from the 100% operation to provide 25% reactive
2
Pc = VIGBT Irm s + rIGBT Irm s (23) power), the power loss decreased by 0.57% of the rated or the
π
√ base value.
2 2 Irm s As the power module will be used in a parallel configuration
Ps,T = (EON + EOFF ) fsw (24)
π IC ,nom in a multimegawatt WT, the percentage or the p.u. losses in the
√ GSC, on the WT base quantities, will be the same. This value
2 2 Irm s
Ps,D = Er r fsw (25) will increase or decrease depending on the amount of reactive
π IC ,nom
power supply from the module, as can be expected. Although
where Pc is the conduction losses in Ts and Ds, Ps,T is the not significant, a certain amount of increased active power loss
switching losses in Ts, Ps,D is the switching losses in Ds, Irm s can be incurred by the WF or can be reduced by the WF, while
is the rms value of the sinusoidal current to the grid or the ma- fulfilling the ISO’s request to increase the reactive power pro-
chine, VIGBT = VC E O ≈ VT O , and rIGBT = rC E ≈ rT . Now, duction from the mandatory value (grid code requirement), with
ULLAH et al.: WIND FARMS AS REACTIVE POWER ANCILLARY SERVICE PROVIDERS—TECHNICAL AND ECONOMIC ISSUES 667
or without reducing the present active power production. The highest limit on the active power production (Plim ,k ). In other
cost of this power loss can be considered by the ISO while words, to fulfill the ISO reactive power demand of Qr,k , which
formulating mechanisms for reactive power procurement from is ∆Qk in excess of the available reactive power capability, the
WFs. WF may lose ∆Pk active power production, where
∆Pk = Pm∗ ax,k − Plim ,k . (34)
C. Opportunity Cost Component
If the WF has to decrease its active power generation, and ∆Pk is the amount of the lost active power production that the
hence forgo market opportunity in order to fulfill ISO request WF should be compensated for in the form of LOC.
for additional reactive power, then the WF should receive a During the operational planning phase, prior to the kth hour,
payment to cover its LOC. Conventional generators receive such the ISO can calculate the LOC in the following way:
payment in some electricity markets [27]. LOC = ρk ∆Pk (35)
Because of the high degree of variability of wind speed during
an hour, it is difficult for the WF to guarantee the provision where ρk is the spot price of the electricity at hour k. Note that,
of a certain amount of reactive power to the ISO based on the since the WF does not save any fuel cost by reducing its active
forecasted power. The maximum hourly variation of wind power power production, the LOC should only reflect the revenue lost
from historical data needs to be considered, and the method of due to the nondelivered energy.
calculating the available amount of reactive power considering In the context of the operation of the Swedish power sys-
the hourly wind variation has been introduced in Section II-D. tem, and the energy balance service market functioning [28],
Furthermore, it would be difficult for the ISO to determine at the end of the kth hour of operation, when the WF genera-
the LOC for a WF, since the ISO will not have information on tion imbalance Pimb,k and the market regulation state (up- or
whether the wind speed was naturally low (so that the WF could down-regulation) are known, then the account for the LOC can
provide enhanced reactive power supply) or it acted on ISO’s be settled as
request for increased reactive power supply. In this section, a LOC = ρk ∆Pk (36)
procedure to calculate the LOC for a WF is proposed.
When the forecasted wind power is Pk∗ at the kth hour of op- where ρk can be equal to the spot price ρk , the up-regulation
eration, the actual Q-capability is Qac,k (see Fig. 10). However, price ρup,k or the down-regulation price ρdn,k depending on the
this much Q cannot be uniformly guaranteed by the WF dur- WF imbalance Pimb,k and the market regulation state (up- or
ing the whole kth hour of operation. Due to the high degree of down-regulation).
variability of wind, the actual production of the WF can exceed Now, consider the situation when the WF imbalance Pimb,k is
the forecasted value during the hour. Taking such variations into positive, i.e., the WF produces more energy than scheduled. The
account, a value ∆Pm ax can be estimated, which can, for in- excess energy should be sold to the balance market at a price
stance, be based on previous meteorological data. The kth hour lower or equal to the spot market price if the system is down-
wind power forecast Pk∗ can now be immediately converted to regulated or up-regulated, respectively [28]. In the absence of
a forecasted maximum wind power Pm∗ ax,k , where the production ceiling from the WF (Plim ,k ), the WF imbalance
Pimb,k could have been more positive than it is. Now, if the
Pm∗ ax,k = min{PR , Pk∗ + ∆Pm ax }. (33)
system was on up-regulation at hour k, then the WF should
The available reactive power from the WF at the kth hour of receive the price ρk , while if down-regulation was ordered, the
operation is Qav,k , considering the hourly wind variation, as WF should receive ρdn,k .
shown in Fig. 10. Now, if the reactive power demand from the For the other situation when the WF imbalance Pimb,k is
ISO is Qr,k , which is in excess of Qav,k , then it will impose a negative, i.e., the WF produces less energy than scheduled, the
668 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 24, NO. 3, SEPTEMBER 2009
TABLE IV tion cost is 5% of the computer and sensor cost, i.e., 0.27% of
ENERGY PRICE ρk TO BE USED IN LOC ACCOUNT SETTLEMENT
the total investment cost (from Section III-A). Considering the
recently completed WF project Lillgrund WF as an example (see
Table II), such a modification would cost around 6750 $/MW
installed capacity of the WF. Assuming an economic lifetime
of 20 years and the interest rate of 5% per year, the cost of
such a modification is around 0.06 $/MW installed/h (based on
continuous compounding [29]).
So, in this case, the cost components for reactive power ser-
vice from the wind turbine consist of a small fixed cost compo-
nent a0 covering the software modification cost, a cost of loss
component covering the cost of increased active power losses
in the converter switches due to the increased reactive power
production, and an opportunity cost if the WF has to reduce
active power generation, and hence forgo market opportunity
in order to fulfil the ISO request for additional reactive power.
The cost function for case 1 (C1 ), which the ISO can use during
Fig. 11. (a) Fixed cost and cost of loss of reactive power production from the the reactive power procurement phase to determine the possible
WF as a function of produced reactive power within the available reactive power
limit. (b) LOC together with the fixed cost and the cost of loss as a function
payment toward WFs for the reactive power service, becomes
of produced reactive power in excess of the available capacity. The figures are
drawn for P k∗ = 0.5 p.u. and ∆P m a x = 0.2 p.u. assuming V g = 1.0 p.u. and C1 = a0 + ρk ∆Ploss,k + ρk ∆Pk (37)
ρk = 60 $/MW·h, when Q m a n = 0.0 and the design pf is 0.95.
where a0 is the fixed cost (in dollars per hour) that the WF will
spend on software modification, ∆Ploss,k is the increased active
additional energy should be bought from the regulation market power losses in the converter switches due to the increased
at a price higher than or equal to the spot market price if the reactive power production above the mandatory requirement
system is up-regulated or down-regulated, respectively. In the Qm an [can be found from (30)], ∆Pk is the lost active power
absence of the production ceiling from the WF (Plim ,k ), the WF production of the WF to fulfill the ISO request for additional
imbalance Pimb,k could have been less negative than it is. If the reactive power support, and ρk is the electricity market price (in
ISO calls for up-regulation, then the WF should pay the price dollars per megawatt hour). At the end of the hour in question,
ρup,k . If down-regulation is ordered by the ISO during that hour the LOC payment can be made using the method described in
of operation, the WF should pay ρk . These are summarized in Section III-C.
Table IV.
Fig. 11 shows the total cost of reactive power production from B. Case 2: Mandatory 0.95 pf Requirement From ISO
the WF for different reactive power production levels for one
particular case. Fig. 11(a) shows the cost of loss component The reactive power capability of a WF is shown in Fig. 5,
together with the fixed cost within the range of Qm an ≤ Q ≤ when the grid code requires the WF to operate at leading/lagging
Qav,k , and Fig. 11(b) shows the total cost taking the LOC com- 0.95 pf at rated operation. As can be seen from the figure,
ponent into account. Note the large LOC component that is additional reactive power production from the WF is possible
due to the relative flatness of the capability diagram of the WF during low wind speed conditions with control modifications.
in the converter-voltage-limited zone (see Fig. 8). It is important Although hardware modifications (enhancing the GSC power
to point out that the calculation of LOC component based on rating, see Table I) are needed in this case, as compared to
the “forecasted maximum wind power (Pm∗ ax,k )” may result in case 1, the cost will not appear in the reactive power cost model.
overcompensation for the WF owner since active power produc- The hardware modifications are needed to fulfill the grid code,
tion may need to be reduced only for a fraction of an hour in and hence, this cost will appear in the active power generation
order to produce enough reactive power. cost of the WF, and eventually affects its energy market bids,
or sell/purchase contract prices. Only the control modification
IV. COST MODEL OF REACTIVE POWER SUPPLY FROM WFS cost will appear as the fixed cost component of reactive power,
as in case 1. The other components of cost, as described in case
A. Case 1: Zero Reactive Power Requirement From ISO 1, are still applicable here. Therefore, the cost function C2 can
In this case, the wind turbine is able to inject reactive power be expressed as
into the grid, in addition to fulfilling the grid requirement, with-
C2 = a0 + ρk ∆Ploss,k + ρk ∆Pk . (38)
out any significant hardware modifications (see Fig. 4). It only
requires to modify the control of the converter, i.e., the software
modification, which is not a significant cost, as mentioned ear- C. Case 3: Enhanced WF Reactive Power Capability
lier. In Section III-A, it is mentioned that the converter control In order to enhance the reactive power capability over and
system cost is embedded as a small part of the computer and above the leading/lagging 0.95 pf grid requirement, additional
sensor cost. Let us assume that the control/software modifica- hardware cost is required compared to case 2. If the GSCs
ULLAH et al.: WIND FARMS AS REACTIVE POWER ANCILLARY SERVICE PROVIDERS—TECHNICAL AND ECONOMIC ISSUES 669
However, a 50% overrated GSC would cost around 2.25% of [11] K. Bhattacharya and J. Zhong, “Reactive power as an ancillary service,”
the total investment cost of the WF, and would be capable of IEEE Trans. Power Syst., vol. 16, no. 2, pp. 294–300, May 2001.
[12] M. Ahlstrom, L. Jones, R. Zavadil, and W. Grant, “The future of wind
providing 0.65 p.u. reactive power at the grid connection point forecasting and utility operations,” IEEE Power Energy Mag., vol. 3,
under nominal conditions. no. 6, pp. 57–64, Nov./Dec. 2005.
Among the three cost components associated with the reac- [13] B. Ernst, B. Oakleaf, M. L. Ahlstrom, M. Lange, C. Moehrlen, B. Lange,
U. Focken, and K. Rohrig, “Predicting the wind,” IEEE Power Energy
tive power supply from the WFs, the cost of loss component may Mag., vol. 5, no. 6, pp. 78–89, Nov./Dec. 2007.
exceed the fixed cost component depending on the amount of re- [14] P. Kundur, Power System Stability and Control. New York: McGraw-
active power production. However, due to the relative flatness of Hill, 1993.
[15] Grid code: High and extra high voltage, E.ON Netz GmbH, Bayreuth,
the capability curve of the WF in the converter-voltage-limited Germany, Tech. Rep., Apr. 2006 (Status 1).
region, the LOC component is relatively larger than the other [16] Nordic grid code 2007 (Nordic collection of rules), Nordel, Oslo, Norway,
two components. It is also due to the fact that the WF does Tech. Rep., Jan. 2004 (updated 2007).
[17] K. Zhou and D. Wang, “Relationship between space-vector modulation
not save any fuel cost by reducing its active power production and three-phase carrier-based PWM: A comprehensive analysis,” IEEE
unlike the conventional generators. The relative sizes of the cost Trans. Ind. Electron., vol. 49, no. 1, pp. 186–196, Feb. 2002.
components depend on the forecasted wind power, wind speed [18] M. B. Zaaijer, H. B. Hendriks, S. Herman, A. Winnemuller, T. Topper,
R. van der Berg, and W. op den Velde, “Optimization through conceptual
prediction error, and the grid voltage at the point of connection. variation of a baseline wind farm,” presented at the Marine Renewable
Another finding from the study is that higher wind speed Energy Conf. (MAREC), Newcastle Upon Tyne, U.K., Sep. 2002.
prediction errors, i.e., a WF site with high degree of wind vari- [19] S. Herman, “DOWEC cost model—Implementation,” Energy Res. Centre
The Netherlands, Petten, The Netherlands, Tech. Rep. ECN-CX-02-048,
ations, may result in higher payments to WFs for the reactive Dec. 2002.
power service, mainly due to the increased LOC component. [20] J. T. G. Pierik, M. Pavlovsky, J. Bozelie, P. Bauer, and S. W. H. de Haan,
For the investigated case considered, the expected payment to “DOWEC electrical system baseline design,” Energy Res. Centre The
Netherlands, Petten, The Netherlands, Tech. Rep. ECN-CX-02-021, Feb.
the WF for a 0.3 p.u. reactive power service is 54 $/h consid- 2002.
ering 0.2 p.u. wind power prediction error, while the payment [21] (2008, Jan.). Facts about The Horns Rev Wind Farm [Online]. Available:
increases to 2394 $/h when the prediction error is 0.5 p.u. http://www.hornsrev.dk/Engelsk/default_ie.htm
[22] (2008, Jan.). Fakta om Lillgrund (in Swedish) [Online]. Available: http://
www.vattenfall.se/
ACKNOWLEDGMENT [23] (2008, Jan.) Våre vindparker [Online]. Available: http://www.statkraft.no/
pub/vindkraft/Kraftverkene/index.asp
The authors would like to express their gratitude to D. Ander- [24] N. Mohan, T. Undeland, and W. Robbins, Power Electronics Converters,
sson, Å. Juntti, and C. Andersson from E.ON Elnät Sverige AB, Applications and Design, 3rd ed. Hoboken, NJ: Wiley, 2003.
[25] A. Petersson, “Analysis, modeling and control of doubly-fed induction
J. Svensson from E.ON Vind Sverige AB, Prof. O. Samuelsson generators for wind turbines,” Ph.D. dissertation, Dept. Energy Environ.,
from Lund University, Faculty of Engineering, Lund, Sweden, Chalmers Univ. Technol., Göteborg, Sweden, 2005.
and D. Karlsson from Gothia Power AB, Göteborg, Sweden, for [26] (2008, Jan.). SKiiP 1803GB172-3DW power module data sheet [Online].
Available: http://www.semikron.com/internet/ds.jsp?file=1264.html
their valuable technical assistance. [27] J. Zhong and K. Bhattacharya, “Reactive power management in dereg-
ulated electricity markets—A review,” in Proc. IEEE Power Eng. Soc.
REFERENCES Winter Meeting, New York, Jan. 2002, pp. 1287–1292.
[28] (2007, Jan.). [Online]. The Swedish electricity market and the role of
[1] E. A. DeMeo, W. Grant, M. R. Milligan, and M. J. Schuerger, “Wind Svenska Kraftnät, Vällingby, Sweden. Available: www.svk.se
plant integration,” IEEE Power Energy Mag., vol. 3, no. 6, pp. 38–46, [29] R. A. Brealey, S. C. Myers, and F. Allen, Corporate Finance, 8th ed.
Nov./Dec. 2005. New York/Homewood, IL: McGraw-Hill/Irwin, 2006.
[2] R. Piwko, N. Miller, J. Sanchez-Gasca, X. Yuan, R. Dai, and J. Lyons, “In- [30] J. Zhong and K. Bhattacharya, “Toward a competitive market for reactive
tegrating large wind farms into weak power grids with long transmission power,” IEEE Trans. Power Syst., vol. 17, no. 4, pp. 1206–1215, Nov.
lines,” in Proc. IEEE/PES Transmiss. Distrib. Conf. Exhib.: Asia Pacific, 2002.
2005, pp. 1–7. [31] I. El-Samahy, K. Bhattacharya, C. Cañizares, M. Anjos, and J. Pan, “A
[3] A. Yazdani and R. Iravani, “A neutral-point clamped converter system procurement market model for reactive power services considering system
for direct-drive variable-speed wind power unit,” IEEE Trans. Energy security,” IEEE Trans. Power Syst., vol. 23, no. 1, pp. 137–149, Feb. 2008.
Convers., vol. 21, no. 2, pp. 596–607, Jun. 2006. [32] K. Walve, “Nordic32-A CIGRÉ test system for simulation of transient
[4] M. Chinchilla, S. Arnaltes, and J. C. Burgos, “Control of permanent- stability and long term dynamics,” Svenska Kraftnät, Vällingby, Sweden,
magnet generators applied to variable-speed wind-energy systems con- Tech. Rep., 1993.
nected to the grid,” IEEE Trans. Energy Convers., vol. 21, no. 1, pp. 130– [33] A User’s Guide, GAMS Development Corporation, Washington, DC,
135, Mar. 2006. GAMS release 2.5, 1999.
[5] G. N. Bathurst, J. Weatherill, and G. Strbac, “Trading wind generation
in short term energy markets,” IEEE Trans. Power Syst., vol. 17, no. 3,
pp. 782–789, Aug. 2002.
[6] J. Matevosyan and L. Söder, “Minimization of imbalance cost trading Nayeem Rahmat Ullah (S’04–M’09) received the
wind power on the short-term power market,” IEEE Trans. Power Syst., B.Sc. degree in electrical and electronic engineering
vol. 21, no. 3, pp. 1396–1404, Aug. 2006. in 2002 from Bangladesh University of Engineering
[7] N. R. Ullah and T. Thiringer, “Variable speed wind turbines for power and Technology (BUET), Dhaka, Bangladesh, and
system stability enhancement,” IEEE Trans. Energy Convers., vol. 22, the M.Sc. and Ph.D. degrees in electrical engineering
no. 1, pp. 52–60, Mar. 2007. in 2004 and 2008, respectively, from Chalmers Uni-
[8] N. R. Ullah, T. Thiringer, and D. Karlsson, “Voltage and transient stability versity of Technology, Göteborg, Sweden.
support by wind farms complying with the E.ON Netz grid code,” IEEE During summer 2007, he was a Visiting Scholar at
Trans. Power Syst., vol. 22, no. 4, pp. 1647–1656, Nov. 2007. the University of Waterloo, Waterloo, ON, Canada.
[9] N. R. Ullah, T. Thiringer, and D. Karlsson, “Temporary primary frequency After completing his Ph.D., he joined the Asset Man-
control support by variable speed wind turbines—Potential and applica- agement Department of E.ON Elnät AB, Malmö,
tions,” IEEE Trans. Power Syst., vol. 23, no. 2, pp. 601–612, May 2008. Sweden, as a Network Planning Engineer. His current research interests in-
[10] S. Hao and A. Papalexopoulas, “Reactive power pricing and management,” clude grid integration of wind energy converters.
IEEE Trans. Power Syst., vol. 12, no. 1, pp. 95–104, Feb. 1997. Dr. Ullah is a member of the IEEE Power and Energy Society.
672 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 24, NO. 3, SEPTEMBER 2009
Kankar Bhattacharya (M’95–SM’01) received the Torbjörn Thiringer (S’92–M’96) received the Ph.D.
Ph.D. degree in electrical engineering from the Indian degree from Chalmers University of Technology,
Institute of Technology-Delhi, New Delhi, India, in Göteborg, Sweden, in 1996.
1993. He is currently is a Professor in the Division of
During 1993–1998, he was a faculty member at Electric Power Engineering, Department of Energy
Indira Gandhi Institute of Development Research, and Environment, Chalmers University of Technol-
Mumbai, India. During 1998–2002, he was with the ogy, Göteborg, Sweden. His current research inter-
Department of Electric Power Engineering, Chalmers ests include power electronic applications for wind
University of Technology, Göteborg, Sweden. Since energy, automotive, and telecom applications as well
January 2003, he has been with the Department of as grid integration of wind energy converters. Prof.
Electrical and Computer Engineering, University of Thiringer is a member of the Cigré B4-39 Group
Waterloo, Waterloo, ON, Canada, where he is currently a Professor. His current “Large-scale integration of wind energy using power electronics and HVDC.”
research interests include power system dynamics, stability and control, eco-
nomic operations planning, electricity pricing, and electric utility deregulation.