Bidding Documents 11KK0054
Bidding Documents 11KK0054
Bidding Documents 11KK0054
OF THE DISTRICT ENGINEER Purok 5 Brgy. 26, Gingoog City Tel./ Fax. No. (088) 861-1185 www.dpwh.gov.ph
BIDDING DOCUMENTS
FOR
CONTRACT LOCATION : BCIR Km 1398+000 - Km 1398+700 DATE OF OPENING OF BIDS : December 6, 2011
TABLE OF CONTENTS
SECTION SECTION SECTION SECTION SECTION SECTION SECTION SECTION I. INVITATION TO BID II. BIDDERS CHECKLIST ... III. INSTRUCTION TO BIDDERS IV. BID DATA SHEETS V. GENERAL CONDITIONS OF CONTRACT .. VI. SPECIAL CONDITION OF CONTRACT .. VII. BILL OF QUANTITIES. VIII. BIDDING FORMS 3 6 7 23 26 47 49 53
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Misamis Oriental First District Engineering Office OFFICE OF THE DISTRICT ENGINEER Brgy 26., Gingoog City Tel./ Fax. No. (088) 861-1185 www.dpwh.gov.ph
INVITATION TO BID
The Bids and Awards Committee (BAC) of the Department of Public Works and HighwaysMisamis Oriental First District Engineering Office (DPWH-MOFDEO), invites contractors to bid for the projects as specified below:
1) Contract ID. Contract Name Contract Location Scope of Work Availability of Fund Approved Budget for The Contract (ABC) Contract Duration Cost of Bid Documents LOI 2) Contract ID. Contract Name Contract Location Scope of Work Availability of Fund Approved Budget for The Contract (ABC) Contract Duration Cost of Bid Documents LOI 3) Contract ID. Contract Name Contract Location Scope of Work Availability of Fund Approved Budget for The Contract (ABC) Contract Duration Cost of Bid Documents LOI 4) Contract ID. Contract Name Contract Location Scope of Work
Availability of Fund Approved Budget for The Contract (ABC) Contract Duration Cost of Bid Documents LOI : : : : : : : : : : : : : : : : : : : : : : : : : : : 11KK0053 Preventive Maintenance/Asphalt Overlay BCIR Km 1358+000 - Km 1360+677 Preventive Maintenance/Asphalt Overlay - 950 Ln.m. Asphalt Overlay 2012 - GAA Reg. Infra Php 11,331,740.00 30 calendar days Php 10,000.00 Php 2,500.00 11KK0054 Rehab/Reconstn/Upgrading of Damaged Paved National Road BCIR Km 1398+000 - Km 1398+700 Concrete Reblocking 248 Blocks 2012 - GAA Reg. Infra Php 11,791,360.00 120 calendar days Php 10,000.00 Php 2,500.00 11KK0055 Rehab/Reconstn/Upgrading of Damaged Paved National Road BCIR Km 1396+000 - Km 1398+000 Concrete Reblocking 435 Blocks 2012 - GAA Reg. Infra Php 20,214,460.00 180 calendar days Php 20,000.00 Php 2,500.00
: 11KK0056 : Construction of Flood Control : Agay-ayan, Gingoog City : Construction of Concrete Revetment w/ Driven Untreated Timber Piles - 136.2 Ln.m : SARO # A - 11 - 01496 dtd October 20, 2011 : : : : Php 7,560,000.00 150 calendar days Php 10,000.00 Php 1,000.00
The BAC will conduct the procurement process in accordance with the Revised IRR of R.A. 9184. Bids received in excess of the ABC shall be automatically rejected at the opening of bid.
Page 1 of 2 Invitation to Bid for PID # 11KK0053 to 56
To bid for these contracts, a contractor must submit a Letter of Intent (LOI), purchase bid documents and must meet the following major criteria: (a) prior registration with the DPWH, (b) Filipino Citizen or 75% Filipino- owned partnership, corporation, cooperative, or joint venture, (c) with PCAB license applicable to the type and cost of these contracts, (d) completion of a similar contract costing at least 50% of ABC within a period of 10 years, and (e) Net Financial Contracting Capacity at least equal to ABC, or credit line commitment at least equal to 10% of ABC. The BAC will use non-discretionary pass/ fail criteria in the eligibility check and preliminary examination of bids. Unregistered contractors, however, shall submit their applications for registration to the DPWH-POCW Central Office before the deadline for the receipt of LOI. The DPWH POCWCentral Office will only process contractors applications for registration with complete requirements and issue the Contractors Certificate of Registration (CRC). Registration Forms may be downloaded at the DPWH website www.dpwh.gov.ph. The significant times and deadlines of procurement activities are shown below: Activities Issuance of Bid Documents Pre-bid Conference Deadline for the Submission of LOI Receipt of Bids Opening of Bids Schedule
From November 16 to November 22, 2011, 10:00 A.M.
November 24, 2011, 10:00 A.M. December 1, 2011, 3:00 P.M. Deadline: 10:00 A.M., December 6, 2011 December 6, 2011, 2:00 P.M
The BAC will only receive Contractors LOI/Expression of Interest (NR-003) and issue Bidding Documents upon presentation of the original copies of their PCAB License and Contractors Registration Certificate (CRC) in person or thru their authorized representative as reflected in their CRC; Special Power of Attorney will not be accepted. The BAC will issue hard copies of bidding documents (BDs) at BAC Secretariat, 3rd Floor DPWH Building, Purok 5, Brgy. 26, Gingoog City, upon payment of a non-refundable fee of the amount stated above. Prospective bidders may also download the BDs from the DPWH website, if applicable. Prospective bidders that will download the BDs from the DPWH website shall pay the said fees on or before the submission of their Bid Documents. The Pre-bid Conference shall be open only to interested parties who have purchased the BDs. Bids must be accompanied by a bid security, in the amount and acceptable form, as stated in Section 27.2 of the Revised IRR. Prospective bidders shall submit their duly accomplished forms as specified in the BDs in two (2) separate sealed bid envelopes to the BAC Chairman. The first envelope shall contain the technical component of the bid, which shall include a copy of the CRC. The second envelope shall contain the financial component of the bid. Contract will be awarded to the Lowest Calculated Responsive Bid as determined in the bid evaluation and post-qualification. The Department of Public Works and Highways- Misamis Oriental First District Engineering Office reserves the right to accept or reject any bid, to annul the bidding process at any time prior contract award, without thereby incurring any liability to the affected bidder/s.
Date of Publication : November 16 to November 22,2011
Newspaper : Manila Standard_
Posted
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Misamis Oriental First District Engineering Office OFFICE OF THE DISTRICT ENGINEER Purok 5 Brgy. 26, Gingoog City Tel./ Fax. No. (088) 861-1185 www.dpwh.gov.ph
Contract No. Name of project Location : 11KK0054 : Rehab/Reconstn/Upgrading of Damaged Paved National Road : BCIR Km 1398+000 - Km 1398+700
BIDDERS CHECKLIST OF REQUIREMENTS FOR ELIGIBILITY REQUIREMENTS, TECHNICAL COMPONENTS AND FINANCIAL PROPOSAL
FIRST ENVELOPE
ELIGIBILITY REQUIREMENTS SHALL CONTAIN THE FOLLOWING:
LEGAL DOCUMENTS SEC, DTI OR CDA registration Mayors Permit for principal place of business Articles of Incorporation, Partnership or Corporation, whichever is applicable, including
amendments thereto. Authenticated copy of Contractors Registration Certificate Certificate of PhilGEPS registration
TECHNICAL DOCUMENTS Statement of all completed and on-going contracts, including those awarded but not yet started Valid PCAB License & Registration for the type and cost of contract to be bid
FINANCIAL DOCUMENTS Audited Financial Statement stamped and received by the BIR NFCC computation or Notarized Credit Line Commitment issued from a universal or commercial bank BIR Tax clearance Latest income and business tax returns
SECOND ENVELOPE
THE FINANCIAL PROPOSAL SHALL CONTAIN THE FOLLOWING:
Duly signed and notarized Form of Bid under Section IX PBD 3rd Edition Duly signed Bid Prices in the Bill of Quantities (Forms DPWH-INFR-46 and 47)
Duly signed Detailed Estimates including Summary Sheets indicating the unit prices of
construction materials, labor rates and equipment rentals used in coming up with the bid
Duly signed Cash Flow by Quarter and Payments Schedule (Form DPWH-INFR-48)
Instructions to Bidders
A. 1. General Scope of Bid
1.1. The Procuring Entity as defined in the BDS, invites bids for the construction of Works, as described in Error! Reference source not found.. The name and identification number of the Contract is provided in the BDS. The successful bidder will be expected to complete the Works by the intended completion date specified in SCC Clause 1.16..
1.2.
2.
Source of Funds
The Procuring Entity has a budget or has applied for or received funds from the Funding Source named in the BDS, and in the amount indicated in the BDS. It intends to apply part of the funds received for the Project, as defined in the BDS, to cover eligible payments under the Contract for the Works.
3.
(ii)
(iii)
(iv)
(b)
will reject a proposal for award if it determines that the bidder recommended for award has engaged in corrupt or fraudulent practices in competing for the Contract; and will declare a firm ineligible, either indefinitely or for a stated period of time, to be awarded Contract funded by the Funding Source if it at any time determines that the firm has engaged in corrupt or fraudulent practices in competing or, or in executing, a Contract funded by the Funding Source.
(c)
3.2.
Further, the Procuring Entity will seek to impose the maximum civil, administrative, and/or criminal penalties available under the applicable laws on individuals and organizations deemed to be involved in any of the practices mentioned in ITB Clause 3.1(a). Furthermore, the Funding Source and the Procuring Entity reserve the right to inspect and audit records and accounts of a contractor in the bidding for and performance of a contract themselves or through independent auditors as reflected in the GCC Clause 34..
3.3.
4.
Conflict of Interest
4.1. All bidders found to have conflicting interests shall be disqualified to participate in the procurement at hand, without prejudice to the imposition of appropriate administrative, civil, and criminal sanctions. A Bidder may be considered to have conflicting interests with another Bidder in any of the events described in paragraphs (a) through (c) and a general conflict of interest in any of the circumstances set out in paragraphs (d) through (g) below: (a) (b) (c) (d) A Bidder has controlling shareholders in common with another Bidder; A Bidder receives or has received any direct or indirect subsidy from any other Bidder; A Bidder has the same legal representative as that of another Bidder for purposes of this Bid; A Bidder has a relationship, directly or through third parties, that puts them in a position to have access to information about or influence on the bid of another Bidder or influence the decisions of the Procuring Entity regarding this bidding process. This will include a firm or an organization who lends, or temporarily seconds, its personnel to firms or organizations which are engaged in consulting services for the preparation related to procurement for or implementation of the project if the personnel would be involved in any capacity on the same project; A Bidder submits more than one bid in this bidding process. However, this does not limit the participation of subcontractors in more than one bid; A Bidder who participated as a consultant in the preparation of the design or technical specifications of the goods and related services that are the subject of the bid; or A Bidder who lends, or temporary seconds, its personnel to firms or organizations which are engaged in consulting services for the preparation related to procurement for or implementation of the project, if the personnel would be involved in any capacity on the same project.
(e) (f)
(g)
4.2.
In accordance with Section 47 of the IRR of RA 9184, all Bidding Documents shall be accompanied by a sworn affidavit of the Bidder that it is not related to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), members of the Technical Working Group (TWG), members of the BAC Secretariat, the head of the Project Management Office (PMO) or the end-user unit, and the project consultants, by consanguinity or affinity up to the third civil degree. On the part of the bidder, this Clause shall apply to the following persons: (a) (b) (c) (d) If the Bidder is an individual or a sole proprietorship, to the Bidder himself; If the Bidder is a partnership, to all its officers and members; If the Bidder is a corporation, to all its officers, directors, and controlling stockholders; and If the Bidder is a joint venture (JV), the provisions of items (a), (b), or (c) of this Clause shall correspondingly apply to each of the members of the said JV, as may be appropriate.
Relationship of the nature described above or failure to comply with this Clause will result in the automatic disqualification of a Bidder.
5.
Eligible Bidders
5.1. Unless otherwise indicated in the BDS, the following persons shall be eligible to participate in this Bidding: (a) (b) (c) Duly licensed Filipino citizens/sole proprietorships; Partnerships duly organized under the laws of the Philippines and of which at least seventy five percent (75%) of the interest belongs to citizens of the Philippines; Corporations duly organized under the laws of the Philippines, and of which at least seventy five percent (75%) of the outstanding capital stock belongs to citizens of the Philippines; Cooperatives duly organized under the laws of the Philippines, and of which at least seventy five percent (75%) of the interest belongs to citizens of the Philippines; and Persons/entities forming themselves into a JV, i.e., a group of two (2) or more persons/entities that intend to be jointly and severally responsible or liable for a particular contract: Provided, however, that, in accordance with Letter of Instructions No. 630, Filipino ownership or interest of the joint venture concerned shall be at least seventy five percent (75%): Provided, further, that joint ventures in which Filipino ownership or interest is less than seventy five percent (75%) may be eligible where the structures to be built require the application of techniques and/or technologies which are not adequately possessed by a person/entity meeting the seventy five percent (75%) Filipino ownership requirement: Provided, finally, that in the latter case, Filipino ownership or interest shall not be less than twenty five percent (25%). For this purpose Filipino ownership or interest shall be based on the contributions of each of the members of the joint venture as specified in their JVA.
(d) (e)
5.2. 5.3.
The Procuring Entity may also invite foreign bidders when provided for under any Treaty or International or Executive Agreement as specified in the BDS. Government Corporate Entities may be eligible to participate only if they can establish that they (a) are legally and financially autonomous, (b) operate under commercial law, and (c) are not dependent agencies of the GOP or the Procuring Entity. Unless otherwise provided in the BDS, the Bidder must have completed at least one contract similar to the Project the value of which, adjusted to current prices using the National Statistics Office consumer price index, must be at least equivalent to a percentage of the ABC stated in the BDS. For this purpose, contracts similar to the Project shall be those described in the BDS, and completed within the period stated in the Invitation to Bid and ITB Clause 12.1(a)(iii).
5.4.
5.5.
Unless otherwise provided in the BDS, the Bidder must submit a computation of its Net Financial Contracting Capacity (NFCC) or a Commitment from a Universal or Commercial bank to extend a credit line in its favor if awarded the contract for this project (CLC). The NFCC, computed using the following formula, must be at least equal to the ABC to be bid: NFCC = [(Current assets minus current liabilities) (K)] minus the value of all outstanding or uncompleted portions of the projects under ongoing contracts, including awarded contracts yet to be started coinciding with the contract for this Project. Where: K = 10 for a contract duration of one year or less, 15 for a contract duration of more than one year up to two years, and 20 for a contract duration of more than two years. The CLC must be at least equal to ten percent (10%) of the ABC for this Project. If issued by a foreign bank, it shall be confirmed or authenticated by a Universal or Commercial Bank. In the case of local government units (LGUs), the Bidder may also submit CLC from other banks certified by the Bangko Sentral ng Pilipinas (BSP) as authorized to issue such financial instrument.
6.
Bidders Responsibilities
6.1. 6.2. The Bidder or its duly authorized representative shall submit a sworn statement in the form prescribed in in Error! Reference source not found. as required in ITB Clause 12.1(b)(iii). The Bidder is responsible for the following: (a) (b) (c) (d) (e) Having taken steps to carefully examine all of the Bidding Documents; Having acknowledged all conditions, implementation of the contract; local or otherwise, affecting the
Having made an estimate of the facilities available and needed for the contract to be bid, if any; and Having complied with its responsibility to inquire or secure Supplemental/Bid Bulletin/s as provided under ITB Clause 10.3. Ensuring that it is not blacklisted or barred from bidding by the GOP or any of its agencies, offices, corporations, or LGUs, including foreign government/foreign or international financing institution whose blacklisting rules have been recognized by the GPPB; Ensuring that each of the documents submitted in satisfaction of the bidding requirements is an authentic copy of the original, complete, and all statements and information provided therein are true and correct; Authorizing the Head of the Procuring Entity or its duly authorized representative/s to verify all the documents submitted; Ensuring that the signatory is the duly authorized representative of the Bidder, and granted full power and authority to do, execute and perform any and all acts necessary and/or to represent the Bidder in the bidding, with the duly notarized Secretarys Certificate attesting to such fact, if the Bidder is a corporation, partnership, cooperative, or joint venture; Complying with the disclosure provision under Section 47 of the Act in relation to other provisions of Republic Act 3019; and Complying with existing labor laws and standards, if applicable. of the Bidder
(f)
(g) (h)
(i) (j)
Failure to observe any of the above responsibilities shall be at the risk concerned. 6.3.
The Bidder, by the act of submitting its bid, shall be deemed to have inspected the site and determined the general characteristics of the contract works and the conditions for this Project. Unless otherwise indicated in the BDS, failure to furnish all information or documentation required in this Bidding Documents shall result in the rejection of the bid and the disqualification of the Bidder. It shall be the sole responsibility of the prospective bidder to determine and to satisfy itself by such means as it considers necessary or desirable as to all matters pertaining to this Project, including: (a) the location and the nature of the contract, project, or work; (b) climatic conditions; (c) transportation facilities; (c) nature and condition of the terrain, geological conditions at the site communication facilities, requirements, location and availability of construction aggregates and other materials, labor, water, electric power and access roads; and (d) other factors that may affect the cost, duration and execution or implementation of the contract, project, or work. The Procuring Entity shall not assume any responsibility regarding erroneous interpretations or conclusions by the prospective or eligible bidder out of the data furnished by the procuring entity.
6.4.
6.5.
6.6.
Before submitting their bids, the Bidders are deemed to have become familiar with all existing laws, decrees, ordinances, acts and regulations of the Philippines which may affect the contract in any way. The Bidder shall bear all costs associated with the preparation and submission of his bid, and the Procuring Entity will in no case be responsible or liable for those costs, regardless of the conduct or outcome of the bidding process. Bidders should note that the Procuring Entity will only accept bids only from those that have paid the nonrefundable fee for the Bidding Documents at the office indicated in the Invitation to Bid.
6.7.
6.8.
7.
8.
Subcontracts
8.1. Unless otherwise specified in the BDS, the Bidder may subcontract portions of the Works to an extent as may be approved by the Procuring Entity and stated in the BDS. However, subcontracting of any portion shall not relieve the Bidder from any liability or obligation that may arise from the contract for this Project. Subcontractors must submit the documentary requirements under ITB Clause 12 and comply with the eligibility criteria specified in the BDS. In the event that any subcontractor is found by the Procuring Entity to be ineligible, the subcontracting of such portion of the Works shall be disallowed. The Bidder may identify the subcontractor to whom a portion of the Works will be subcontracted at any stage of the bidding process or during contract implementation. If the Bidder opts to disclose the name of the subcontractor during bid submission, the Bidder shall include the required documents as part of the technical component of its bid.
8.2.
8.3.
B. 9. Pre-Bid Conference
9.1.
If so specified in the BDS, a pre-bid conference shall be held at the venue and on the date indicated therein, to clarify and address the Bidders questions on the technical and financial components of this Project. Bidders are encouraged to attend the pre-bid conference to ensure that they fully understand the Procuring Entitys requirements. Non-attendance of the Bidder will in no way prejudice its bid; however, the Bidder is expected to know the changes and/or amendments to the Bidding Documents discussed during the pre-bid conference. Any statement made at the pre-bid conference shall not modify the terms of the bidding documents unless such statement is specifically identified in writing as an amendment thereto and issued as a Supplemental/Bid Bulletin.
9.2.
9.3.
10.
seven (7) calendar days before the deadline for the submission and receipt of Bids. Any modification to the Bidding Documents shall be identified as an amendment. 10.3. Any Supplemental/Bid Bulletin issued by the BAC shall also be posted on the Philippine Government Electronic Procurement System (PhilGEPS) and the website of the Procuring Entity concerned, if available. It shall be the responsibility of all Bidders who secure the Bidding Documents to inquire and secure Supplemental/Bid Bulletins that may be issued by the BAC. However, bidders who have submitted bids before the issuance of the Supplemental/Bid Bulletin must be informed and allowed to modify or withdraw their bids in accordance with ITB Clause 23.
Preparation of Bids
The Bid, as well as all correspondence and documents relating to the Bid exchanged by the Bidder and the Procuring Entity, shall be written in English. Supporting documents and printed literature furnished by the Bidder may be in another language provided they are accompanied by an accurate translation in English certified by the appropriate embassy or consulate in the Philippines, in which case the English translation shall govern, for purposes of interpretation of the Bid.
12.
(iii.12) the statement shall be supported by the notices of award and/or notices to proceed issued by the owners; and (iii.13) the statement shall be supported by the Constructors Performance Evaluation System (CPES) rating sheets, and/or certificates of completion and owners acceptance, if applicable; (iv) Unless otherwise provided in the BDS, valid Philippine Contractors Accreditation Board (PCAB) license and registration for the type and cost of the contract for this Project; Audited financial statements, showing, among others, the prospective total and current assets and liabilities, stamped received by the BIR or its duly accredited and authorized institutions, for the preceding calendar year which should not be earlier than two (2) years from the date of bid submission; NFCC computation or CLC in accordance with ITB Clause 5.5; and
(v)
(vi)
Class "B" Document: (vii) If applicable, valid Joint Venture Agreement (JVA) or, in lieu thereof, duly notarized statements from all the potential joint venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful shall be included in the bid.
(b)
Technical Documents (i) Bid security as prescribed in ITB Clause 18. If the Bidder opts to submit the bid security in the form of: (i.1) a bank draft/guarantee or an irrevocable letter of credit issued by a foreign bank, it shall be accompanied by a confirmation from a Universal or Commercial Bank; or a surety bond accompanied by a certification coming from an authorized Insurance Commission that a surety or insurance company is authorized to issue such instrument;
(i.2)
(ii)
Project Requirements, which shall include the following: (ii.1) (ii.2) Organizational chart for the contract to be bid; List of contractors personnel (viz, project Manager, Project Engineers, Materials Engineers, and Foremen), to be assigned to the contract to be bid, with their complete qualification and experience data; and List of contractors equipment units, which are owned, leased, and/or under purchase agreements, supported by certification of availability of equipment from the equipment lessor/vendor for the duration of the project; and
(ii.3)
(iii)
Sworn statement in accordance with Section 25.2(b)(iv) of the IRR of RA 9184 and using the form prescribed in Error! Reference source not found..
13.
13.2. Unless indicated in the BDS, all Bids that exceed the ABC shall not be accepted.
14.
Alternative Bids
14.1. Alternative Bids shall be rejected. For this purpose, alternative bid is an offer made by a Bidder in addition or as a substitute to its original bid which may be included as part of its original bid or submitted separately therewith for purposes of bidding. A bid with options is considered an alternative bid regardless of whether said bid proposal is contained in a single envelope or submitted in two (2) or more separate bid envelopes. 14.2. Bidders shall submit offers that comply with the requirements of the Bidding Documents, including the basic technical design as indicated in the drawings and specifications. Unless there is a value engineering clause in the BDS, alternative bids shall not be accepted. 14.3. Each Bidder shall submit only one Bid, either individually or as a partner in a JV. A Bidder who submits or participates in more than one bid (other than as a subcontractor if a subcontractor is permitted to participate in more than one bid) will cause all the proposals with the Bidders participation to be disqualified. This shall be without prejudice to any applicable criminal, civil and administrative penalties that may be imposed upon the persons and entities concerned.
15.
Bid Prices
15.1. The contract shall be for the whole Works, as described in ITB Clause 1.1, based on the priced Bill of Quantities submitted by the Bidder. 15.2. The Bidder shall fill in rates and prices for all items of the Works described in the Bill of Quantities. Bids not addressing or providing all of the required items in the Bidding Documents including, where applicable, bill of quantities, shall be considered nonresponsive and, thus, automatically disqualified. In this regard, where a required item is provided, but no price is indicated, the same shall be considered as non-responsive, but specifying a "0" (zero) for the said item would mean that it is being offered for free to the Government. 15.3. All duties, taxes, and other levies payable by the Contractor under the Contract, or for any other cause, prior to the deadline for submission of bids, shall be included in the rates, prices, and total bid price submitted by the Bidder. 15.4. Unless otherwise provided in the BDS, all bid prices for the given scope of work in the contract as awarded shall be considered as fixed prices, and therefore not subject to price escalation during contract implementation, except under extraordinary circumstances as indicated in the BDS and specified in GCC Clause 48 and its corresponding SCC provision.
16.
Bid Currencies
16.1. All bid prices shall be quoted in Philippine Pesos unless otherwise provided in the BDS. However, for purposes of bid evaluation, bids denominated in foreign currencies shall be converted to Philippine currency based on the exchange rate prevailing on the day of the Bid opening. 16.2. If so allowed in accordance with ITB Clause 16.1, the Procuring Entity for purposes of bid evaluation and comparing the bid prices will convert the amounts in various currencies in which the bid price is expressed to Philippine Pesos at the exchange rate as published in the BSP reference rate bulletin on the day of the bid opening. 16.3. Unless otherwise specified in the BDS, payment of the contract price shall be made in Philippine Pesos.
17.
Bid Validity
17.1. Bids shall remain valid for the period specified in the BDS which shall not exceed one hundred twenty (120) calendar days from the date of the opening of bids. 17.2. In exceptional circumstances, prior to the expiration of the bid validity period, the Procuring Entity may request Bidders to extend the period of validity of their bids. The request and the responses shall be made in writing. The bid security described in ITB Clause 18 should also
be extended corresponding to the extension of the bid validity period at the least. A Bidder may refuse the request without forfeiting its bid security, but his bid shall no longer be considered for further evaluation and award. A Bidder granting the request shall not be required or permitted to modify its bid.
18.
Bid Security
18.1. The bid security, issued in favor of the Procuring Entity, in the amount stated in the BDS shall be equal to the percentage of the ABC in accordance with the following schedule: Form of Bid Security (a) Cash or cashiers/managers check issued by a Universal or Commercial Bank. Bank draft/guarantee or irrevocable letter of credit issued by a Universal or Commercial Bank: Provided, however, that it shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank. Surety bond callable upon demand issued by a surety or insurance company duly certified by the Insurance Commission as authorized to issue such security; and/or Any combination of the foregoing. Amount of Bid Security (Equal to Percentage of the ABC)
(b)
(c)
(d)
For biddings conducted by local government units, the Bidder may also submit bid securities in the form of cashiers/managers check, bank draft/guarantee, or irrevocable letter of credit from other banks certified by the BSP as authorized to issue such financial statement. 18.2. The bid security should be valid for the period specified in the BDS. Any bid not accompanied by an acceptable bid security shall be rejected by the Procuring Entity as nonresponsive. 18.3. No bid securities shall be returned to bidders after the opening of bids and before contract signing, except to those that failed or declared as post-disqualified, upon submission of a written waiver of their right to file a motion for reconsideration and/or protest. Without prejudice on its forfeiture, Bid Securities shall be returned only after the bidder with the Lowest Calculated Responsive Bid has signed the contract and furnished the Performance Security, but in no case later than the expiration of the Bid Security validity period indicated in ITB Clause 18.2. 18.4. Upon signing and execution of the contract, pursuant to ITB Clause 31, and the posting of the performance security, pursuant to ITB Clause 32, the successful Bidders Bid security will be discharged, but in no case later than the Bid security validity period as indicated in ITB Clause 18.2. 18.5. The bid security may be forfeited: (a) if a Bidder: (i) (ii) withdraws its bid during the period of bid validity specified in ITB Clause 17; does not accept the correction of errors pursuant to ITB Clause 27.3(b);
fails to submit the requirements within the prescribed period, or a finding against their veracity, as stated in ITB Clause 28.2; or any other reason stated in the BDS.
if the successful Bidder: (i) (ii) (iii) fails to sign the contract in accordance with ITB Clause 31; fails to furnish performance security in accordance with ITB Clause 32; or any other reason stated in the BDS.
19.
20.
(e)
bear a warning DO NOT OPEN BEFORE the date and time for the opening of bids, in accordance with ITB Clause 21.
20.5. If bids are not sealed and marked as required, the Procuring Entity will assume no responsibility for the misplacement or premature opening of the bid.
D. 21.
22.
Late Bids
Any bid submitted after the deadline for submission and receipt of bids prescribed by the Procuring Entity, pursuant to ITB Clause 21, shall be declared Late and shall not be accepted by the Procuring Entity.
23.
24.
the bid requirements for both components shall be rated passed and shall immediately be considered for evaluation and comparison. 24.3. Letters of withdrawal shall be read out and recorded during bid opening, and the envelope containing the corresponding withdrawn bid shall be returned to the Bidder unopened. If the withdrawing Bidders representative is in attendance, the original bid and all copies thereof shall be returned to the representative during the bid opening. If the representative is not in attendance, the Bid shall be returned unopened by registered mail. The Bidder may withdraw its bid prior to the deadline for the submission and receipt of bids, provided that the corresponding letter of withdrawal contains a valid authorization requesting for such withdrawal, subject to appropriate administrative sanctions. 24.4. If a Bidder has previously secured a certification from the Procuring Entity to the effect that it has previously submitted the above-enumerated Class A Documents, the said certification may be submitted in lieu of the requirements enumerated in ITB Clause 12.1(a), items (i) to (vi). 24.5. In the case of an eligible foreign Bidder as described in ITB Clause 5, the Class A Documents enumerated in ITB Clause 12.1(a) may be substituted with the appropriate equivalent documents, if any, issued by the country of the foreign Bidder concerned. 24.6. Each partner of a joint venture agreement shall likewise submit the documents required in ITB Clauses 12.1(a)(i) and 12.1(a)(ii). Submission of documents required under ITB Clauses 12.1(a)(iii) to 12.1(a)(vi) by any of the joint venture partners constitutes compliance. 24.7. A Bidder determined as failed has three (3) calendar days upon written notice or, if present at the time of bid opening, upon verbal notification within which to file a request for reconsideration with the BAC: Provided, however, that the request for reconsideration shall not be granted if it is established that the finding of failure is due to the fault of the Bidder concerned: Provided, further, that the BAC shall decide on the request for reconsideration within seven (7) calendar days from receipt thereof. If a failed Bidder signifies his intent to file a request for reconsideration, the BAC shall keep the bid envelopes of the said failed Bidder unopened and/or duly sealed until such time that the request for reconsideration or protest has been resolved.
E. 25.
Process to be Confidential
25.1. Members of the BAC, including its staff and personnel, as well as its Secretariat and TWG, are prohibited from making or accepting any kind of communication with any bidder regarding the evaluation of their bids until the issuance of the Notice of Award, unless otherwise allowed in the BDS or in the case of ITB Clause 26. 25.2. Any effort by a bidder to influence the Procuring Entity in the Procuring Entitys decision in respect of Bid evaluation, Bid comparison or contract award will result in the rejection of the Bidders Bid.
26.
Clarification of Bids
To assist in the evaluation, comparison and post-qualification of the bids, the Procuring Entity may ask in writing any Bidder for a clarification of its bid. All responses to requests for clarification shall be in writing. Any clarification submitted by a Bidder in respect to its bid and that is not in response to a request by the Procuring Entity shall not be considered
27.
(a) (b)
The detailed evaluation of the financial component of the bids, to establish the correct calculated prices of the bids; and The ranking of the total bid prices as so calculated from the lowest to highest. The bid with the lowest price shall be identified as the Lowest Calculated Bid.
27.3. The Procuring Entity's BAC shall immediately conduct a detailed evaluation of all bids rated passed, using non-discretionary pass/fail criterion. Unless otherwise specified in the BDS, the BAC shall consider the following in the evaluation of bids: (a) Completeness of the bid. Unless the ITB specifically allows partial bids, bids not addressing or providing all of the required items in the Schedule of Requirements including, where applicable, bill of quantities, shall be considered non-responsive and, thus, automatically disqualified. In this regard, where a required item is provided, but no price is indicated, the same shall be considered as non-responsive, but specifying a "0" (zero) for the said item would mean that it is being offered for free to the Procuring Entity; and Arithmetical corrections. Consider computational errors, omissions, and other bid modifications, if allowed in the BDS, to enable proper comparison of all eligible bids. Any adjustment shall be calculated in monetary terms to determine the calculated prices.
(b)
27.4. Based on the detailed evaluation of bids, those that comply with the above-mentioned requirements shall be ranked in the ascending order of their total calculated bid prices, as evaluated and corrected for computational errors, discounts and other modifications, to identify the Lowest Calculated Bid. Total calculated bid prices, as evaluated and corrected for computational errors, discounts and other modifications, which exceed the ABC shall not be considered. 27.5. Unless otherwise indicated in the BDS, the Procuring Entitys evaluation of bids shall only be based on the bid price quoted in the Financial Bid Form 27.6. Bids shall be evaluated on an equal footing to ensure fair competition. For this purpose, all bidders shall be required to include in their bids the cost of all taxes, such as, but not limited to, value added tax (VAT), income tax, local taxes, and other fiscal levies and duties which shall be itemized in the bid form and reflected in the detailed estimates. Such bids, including said taxes, shall be the basis for bid evaluation and comparison.
28.
Post Qualification
28.1. The Procuring Entity shall determine to its satisfaction whether the Bidder that is evaluated as having submitted the Lowest Calculated Bid (LCB) complies with and is responsive to all the requirements and conditions specified in ITB Clauses 5, 12, and 13. 28.2. Within a non-extendible period of three (3) calendar days from receipt by the Bidder of the notice from the BAC that it submitted the LCB, the Bidder shall submit the following documentary requirements: (a) (b) (c) (d) Tax clearance per Executive Order 398, Series of 2005; Latest income and business tax returns in the form specified in the BDS; Certificate of PhilGEPS Registration; and Other appropriate licenses and permits required by law and stated in the BDS.
Failure of the Bidder declared as LCB to duly submit the requirements under this Clause or a finding against the veracity of such, shall be ground for forfeiture of the bid security and disqualification of the Bidder for award. 28.3. The determination shall be based upon an examination of the documentary evidence of the Bidders qualifications submitted pursuant to ITB Clauses 12 and 13, as well as other information as the Procuring Entity deems necessary and appropriate, using a nondiscretionary pass/fail criterion.
28.4. If the BAC determines that the Bidder with the Lowest Calculated Bid passes all the criteria for post-qualification, it shall declare the said bid as the Lowest Calculated Responsive Bid, and recommend to the Head of the Procuring Entity the award of contract to the said Bidder at its submitted price or its calculated bid price, whichever is lower, subject to ITB Clause 30.3. 28.5. A negative determination shall result in rejection of the Bidders Bid, in which event the Procuring Entity shall proceed to the next Lowest Calculated Bid to make a similar determination of that Bidders capabilities to perform satisfactorily. If the second Bidder, however, fails the post qualification, the procedure for post qualification shall be repeated for the Bidder with the next Lowest Calculated Bid, and so on until the Lowest Calculated and Responsive Bid is determined for contract award. 28.6. Within a period not exceeding seven (7) calendar days from the date of receipt of the recommendation of the BAC, the Head of the Procuring Entity shall approve or disapprove the said recommendation. In the case of government owned and government-owned and/or controlled corporations (GOCCs) and government financial institutions (GFIs), the period provided herein shall be fifteen (15) calendar days.
29.
Reservation Clause
29.1. Notwithstanding the eligibility or post-qualification of a bidder, the Procuring Entity concerned reserves the right to review its qualifications at any stage of the procurement process if it has reasonable grounds to believe that a misrepresentation has been made by the said bidder, or that there has been a change in the Bidders capability to undertake the project from the time it submitted its eligibility requirements. Should such review uncover any misrepresentation made in the eligibility and bidding requirements, statements or documents, or any changes in the situation of the Bidder which will affect its capability to undertake the project so that it fails the preset eligibility or bid evaluation criteria, the Procuring Entity shall consider the said Bidder as ineligible and shall disqualify it from submitting a bid or from obtaining an award or contract. 29.2. Based on the following grounds, the Procuring Entity reserves the right to reject any and all Bids, declare a Failure of Bidding at any time prior to the contract award, or not to award the contract, without thereby incurring any liability, and make no assurance that a contract shall be entered into as a result of the bidding: (a) if there is prima facie evidence of collusion between appropriate public officers or employees of the Procuring Entity, or between the BAC and any of the bidders, or if the collusion is between or among the bidders themselves, or between a bidder and a third party, including any act which restricts, suppresses or nullifies or tends to restrict, suppress or nullify competition; if the Procuring Entitys BAC is found to have failed in following the prescribed bidding procedures; or for any justifiable and reasonable ground where the award of the contract will not redound to the benefit of the Government as follows: (i) If the physical and economic conditions have significantly changed so as to render the project no longer economically, financially or technically feasible as determined by the head of the procuring entity; If the project is no longer necessary as determined by the head of the procuring entity; and If the source of funds for the project has been withheld or reduced through no fault of the Procuring Entity.
(b) (c)
(ii) (iii)
29.3. In addition, the Procuring Entity may likewise declare a failure of bidding when: (a) (b) No bids are received; All prospective bidders are declared ineligible;
(c) (d)
All bids fail to comply with all the bid requirements or fail post-qualification; or The bidder with the Lowest Calculated Responsive Bid refuses, without justifiable cause to accept the award of contract, and no award is made.
Award of Contract
30.1. Subject to ITB Clause 28, the Procuring Entity shall award the contract to the Bidder whose Bid has been determined to be the Lowest Calculated and Responsive Bid (LCRB). 30.2. Prior to the expiration of the period of Bid validity, the Procuring Entity shall notify the successful Bidder in writing that its Bid has been accepted, through a Notice of Award received personally or sent by registered mail or electronically, receipt of which must be confirmed in writing within two (2) days by the LCRB and submitted personally or sent by registered mail or electronically to the Procuring Entity. 30.3. Notwithstanding the issuance of the Notice of Award, award of contract shall be subject to the following conditions: (a) Submission of the following documents within the prescribed period from receipt by the Bidder of the notice that it has the Lowest Calculated and Responsive Bid: (i) (ii) Valid JVA, if applicable, within ten (10) calendar days; Valid PCAB license and registration for the type and cost of the contract to be bid for foreign bidders, within thirty (30) calendar days, if allowed under a Treaty or International or Executive Agreement mentioned in ITB Clause 12.1(a)(iv);
Posting of the performance security in accordance with ITB Clause 32; Signing of the contract as provided in ITB Clause 31; and Approval by higher authority, if required.
31.
(g)
Other contract documents that may be required by existing laws and/or specified in the BDS.
32.
Performance Security
32.1. To guarantee the faithful performance by the winning Bidder of its obligations under the contract, it shall post a performance security within a maximum period of ten (10) calendar days from the receipt of the Notice of Award from the Procuring Entity and in no case later than the signing of the contract. 32.2. The performance security shall be denominated in Philippine Pesos and posted in favor of the Procuring Entity in an amount equal to the percentage of the total contract price in accordance with the following schedule:
Form of Performance Security (a) Cash or cashiers/managers check issued by a Universal or Commercial Bank. (b) Bank draft/guarantee or irrevocable letter of credit issued by a Universal or Commercial Bank: Provided, however, that it shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank. (c) Surety bond callable upon demand issued by a surety or insurance company duly certified by the Insurance Commission as authorized to issue such security; and/or (d) Any combination of the foregoing.
32.3. Failure of the successful Bidder to comply with the above-mentioned requirement shall constitute sufficient ground for the annulment of the award and forfeiture of the bid security, in which event the Procuring Entity shall initiate and complete the post qualification of the second Lowest Calculated Bid. The procedure shall be repeated until the Lowest Calculated and Responsive Bid is identified and selected for contract award. However if no Bidder passed post-qualification, the BAC shall declare the bidding a failure and conduct a rebidding with re-advertisement.
33.
Notice to Proceed
33.1. Within three (3) calendar days from the date of approval of the Contract by the appropriate government approving authority, the Procuring Entity shall issue its Notice to Proceed to the Bidder. 33.2. The date of the Bidders receipt of the Notice to Proceed will be regarded as the effective date of the Contract, unless otherwise specified in the BDS.
If the Funding Source is GOP: The Government of the Philippines (GOP) through 2012 - GAA Reg. Infra in the amount of Eleven Million Three
Hundred Thirty One Thousand Seven Hundred Forty Pesos Only (PHP 11,791,360.00)
No further instructions. Bidding is restricted to eligible bidders as defined in ITB Clause 5.1 The Bidder must have completed, within ten (10) years from the submission of bids, a single contract that is similar to this Project, equivalent to at least fifty percent (50%) of the ABC. For this purpose, similar contracts shall refer to [Roads- RehabilitationPCCP].
No further instructions. No further instructions. No further instructions. Subcontracting is not allowed. If subcontracting is allowed, specify the eligibility criteria that subcontractors must comply with; otherwise, state Not applicable. The pre-bid conference for this project is on November 24, 2011 at 10:00 in the morning at the Conference Room, 2nd floor, Department of
Public Works and Highways - Misamis Oriental First District Engineering Office, , Purok 5, Barangay 26, Gingoog City The Procuring Entitys address is: Purok 5, Barangay 26, Gingoog City DOROTEO A. LAGUNA, Chief, MQC Section, BAC Chairman Tel/Fax Nos. 088-861-1185 (Philcom) and 08842 7474 (MisOrTel)
10.1
12.1
[Insert email address of contact (if applicable)]None The first envelope shall contain the eligibility and technical documents stated in the Bidders Checklist of Requirements. The last day of submission of Letter of Intent will be on December 1, 2011, 3:00P.M. Any application for eligibility or updates submitted after the deadline for the submission of the letter of intent shall not be considered for the bidding at hand. Refer to Bidders Checklist of Requirements as attached. If the Funding Source is GOP: No further instructions. No further instructions. List any additional requirements or state No additional Requirements If the Funding Source is the GOP: The ABC is Php. 11,791,360.00. Any bid with a financial component exceeding this amount shall not be accepted. Insert value engineering clause if allowed, otherwise state No further instructions. If the Funding Source is the GOP or WB: Bid Prices shall be fixed. Adjustable price proposals shall be treated as non-responsive and shall be rejected. If the Funding Source is the GOP, add the following to the first paragraph above: Price escalation may be allowed in extraordinary circumstances as may be determined by the National Economic and Development Authority in accordance with the Civil Code of the Philippines, and upon the recommendation of the Procuring Entity. The bid prices shall be quoted in Philippine Pesos. If the Funding Source is GOP, maintain the ITB Clause and state here: No further instructions. Bids will be valid 120 CD from opening of bids.
18.1
If the Funding Source is the GOP or WB: The bid security shall be in the following amount: 1. [P 235,827.20 - 2% of ABC], if bid security is in cash, cashiers/managers check, bank draft/guarantee or irrevocable letter of credit issued by a Universal or Commercial Bank, notarized and with check writer; 2. [P 589,568.00 - 5% of ABC] if bid security is in Surety Bond callable on demand issued by a surety or insurance company duly certified by the Insurance Commission as authorized to issue such security; or 3. Any combination of the foregoing proportionate to the share of form with respect to total amount of security.
18.2 18.5(a)(iv)
The bid security shall be valid 120 CD from opening of bids. If the Funding Source is GOP or WB, maintain the ITB clause and include the following as additional grounds for forfeiture of bid security: 1. Submission of eligibility requirements containing false information or falsified documents. 2. Submission of bids that contain false information or falsified documents, or the concealment of such information in the bids in order to influence the outcome of eligibility screening or any other stage of the public bidding. 3. Allowing the use of ones name, or using the name of another for purposes of public bidding. 4. Withdrawal of a bid, or refusal to accept an award, or enter into contract with the Government without justifiable cause, after the Bidder had been adjudged as having submitted the Lowest Calculated and Responsive Bid. 5. Refusal or failure to post the required performance security within the prescribed time. 6. Refusal to clarify or validate in writing its bid during postqualification within a period of seven (7) calendar days from receipt of the request for clarification. 7. Any documented unsolicited attempt by a bidder to unduly influence the outcome of the bidding in his favor. 8. Failure of the potential joint venture partners to enter into the joint venture after the bid is declared as successful. 9. All other acts that tend to defeat the purpose of the competitive bidding, such as habitually withdrawing from bidding, submitting late Bids or patently insufficient bid, for at least three (3) times within a year, except for valid reasons.
If the Funding Source is GOP, ADB, or WB, maintain the ITB clause and state here: No further instructions. If the Funding Source is GOP, maintain the ITB Clause and state here: No further instructions. Each Bidder shall submit one(1)set original and 2(two)sets of Xerox copies of the first and second components of its bid. The address for submission of bids is DPWH-Misamis Oriental First
District Engineering Office, Purok 5, Barangay 26, Gingoog City The deadline for submission of bids is December 6, 2011 at 10:00 in the morning The place of bid opening is at the Conference Room, 2nd floor, DPWHMisamis Oriental First District Engineering Office, Purok 5, Brgy. 26, Gingoog City
24.1
The date and time of bid opening is December 6, 2011 at 2:00 in the
afternoon.
28.2(d) 31.4g
33.2
No further instructions. No further instructions. Bid modification is not allowed. No further instructions. The bidder has the option to submit manually filed tax returns or tax returns filed through the Electronic Filing and Payment System. NOTE: The latest income and business tax returns are those within the last six months preceding the date of bid submission No other licenses and permits required relevant to the project. List of additional contract documents relevant to the project that is required by existing laws and this procuring office such as construction schedule and S-curve, manpower schedule, construction methods, equipment utilization schedule, construction safety and health program approved by the Department of Labor and Employment, and PERT/CPM. (Note: The documents mentioned shall form part of the contract.) The effective date of the Contract is December 23, 2011
1.10. Dayworks are varied work inputs subject to payment on a time basis for the Contractors employees and Equipment, in addition to payments for associated Materials and Plant. 1.11. A Defect is any part of the Works not completed in accordance with the Contract. 1.12. The Defects Liability Certificate is the certificate issued by Procuring Entitys Representative upon correction of defects by the Contractor. 1.13. The Defects Liability Period is the one year period between project completion and final acceptance within which the Contractor assumes the responsibility to undertake the repair of any damage to the Works at his own expense. 1.14. Drawings are graphical presentations of the Works. They include all supplementary details, shop drawings, calculations, and other information provided or approved for the execution of this Contract. 1.15. Equipment refers to all facilities, supplies, appliances, materials or things required for the execution and completion of the Work provided by the Contractor and which shall not form or are not intended to form part of the Permanent Works. 1.16. The Intended Completion Date refers to the date specified in the SCC when the Contractor is expected to have completed the Works. The Intended Completion Date may be revised only by the Procuring Entitys Representative by issuing an extension of time or an acceleration order. 1.17. Materials are all supplies, including consumables, used by the Contractor for incorporation in the Works. 1.18. The Notice to Proceed is a written notice issued by the Procuring Entity or the Procuring Entitys Representative to the Contractor requiring the latter to begin the commencement of the work not later than a specified or determinable date.
1.19. Permanent Works all permanent structures and all other project features and facilities required to be constructed and completed in accordance with this Contract which shall be delivered to the Procuring Entity and which shall remain at the Site after the removal of all Temporary Works. 1.20. Plant refers to the machinery, apparatus, and the like intended to form an integral part of the Permanent Works. 1.21. The Procuring Entity is the party who employs the Contractor to carry out the Works stated in the SCC. 1.22. The Procuring Entitys Representative refers to the Head of the Procuring Entity or his duly authorized representative, identified in the SCC, who shall be responsible for supervising the execution of the Works and administering this Contract. 1.23. The Site is the place provided by the Procuring Entity where the Works shall be executed and any other place or places which may be designated in the SCC, or notified to the Contractor by the Procuring Entitys Representative as forming part of the Site. 1.24. Site Investigation Reports are those that were included in the Bidding Documents and are factual and interpretative reports about the surface and subsurface conditions at the Site. 1.25. Slippage is a delay in work execution occurring when actual accomplishment falls below the target as measured by the difference between the scheduled and actual accomplishment of the Work by the Contractor as established from the work schedule. This is actually described as a percentage of the whole Works. 1.26. Specifications means the description of Works to be done and the qualities of materials to be used, the equipment to be installed and the mode of construction. 1.27. The Start Date, as specified in the SCC, is the date when the Contractor is obliged to commence execution of the Works. It does not necessarily coincide with any of the Site Possession Dates. 1.28. A Subcontractor is any person or organization to whom a part of the Works has been subcontracted by the Contractor, as allowed by the Procuring Entity, but not any assignee of such person. 1.29. Temporary Works are works designed, constructed, installed, and removed by the Contractor that are needed for construction or installation of the Permanent Works. 1.30. Work(s) refer to the Permanent Works and Temporary Works to be executed by the Contractor in accordance with this Contract, including (i) the furnishing of all labor, materials, equipment and others incidental, necessary or convenient to the complete execution of the Works; (ii) the passing of any tests before acceptance by the Procuring Entitys Representative; (iii) and the carrying out of all duties and obligations of the Contractor imposed by this Contract as described in the SCC.
2.
Interpretation
2.1. In interpreting the Conditions of Contract, singular also means plural, male also means female or neuter, and the other way around. Headings have no significance. Words have their normal meaning under the language of this Contract unless specifically defined. The Procuring Entitys Representative will provide instructions clarifying queries about the Conditions of Contract. If sectional completion is specified in the SCC, references in the Conditions of Contract to the Works, the Completion Date, and the Intended Completion Date apply to any Section of the Works (other than references to the Completion Date and Intended Completion Date for the whole of the Works).
2.2.
3.
All correspondence and other documents pertaining to this Contract which are exchanged by the parties shall be written in English. 3.2. This Contract shall be interpreted in accordance with the laws of the Republic of the Philippines.
4.
Communications
Communications between parties that are referred to in the Conditions shall be effective only when in writing. A notice shall be effective only when it is received by the concerned party.
5.
Possession of Site
5.1. On the date specified in the SCC, the Procuring Entity shall grant the Contractor possession of so much of the Site as may be required to enable it to proceed with the execution of the Works. If the Contractor suffers delay or incurs cost from failure on the part of the Procuring Entity to give possession in accordance with the terms of this clause, the Procuring Entitys Representative shall give the Contractor a Contract Time Extension and certify such sum as fair to cover the cost incurred, which sum shall be paid by Procuring Entity. If possession of a portion is not given by the date stated in the SCC Clause 5.1, the Procuring Entity will be deemed to have delayed the start of the relevant activities. The resulting adjustments in contact time to address such delay shall be in accordance with GCC Clause 47. The Contractor shall bear all costs and charges for special or temporary right-of-way required by it in connection with access to the Site. The Contractor shall also provide at his own cost any additional facilities outside the Site required by it for purposes of the Works. The Contractor shall allow the Procuring Entitys Representative and any person authorized by the Procuring Entitys Representative access to the Site and to any place where work in connection with this Contract is being carried out or is intended to be carried out.
5.2.
5.3.
5.4.
6.
6.2.
6.6.
6.7. 6.8.
6.9.
The Contractor shall cooperate and share the Site with other contractors, public authorities, utilities, and the Procuring Entity between the dates given in the schedule of other contractors particularly when they shall require access to the Site. The Contractor shall also provide facilities and services for them during this period. The Procuring Entity may modify the schedule of other contractors, and shall notify the Contractor of any such modification thereto.
6.10. Should anything of historical or other interest or of significant value be unexpectedly discovered on the Site, it shall be the property of the Procuring Entity. The Contractor shall notify the Procuring Entitys Representative of such discoveries and carry out the Procuring Entitys Representatives instructions in dealing with them.
7.
Performance Security
7.1. Unless otherwise specified in the SCC, within ten (10) calendar days from receipt of the Notice of Award from the Procuring Entity but in no case later than the signing of the contract by both parties, the Contractor shall furnish the performance security in any the forms prescribed in ITB Clause 32.2. The performance security posted in favor of the Procuring Entity shall be forfeited in the event it is established that the Contractor is in default in any of its obligations under the Contract. The performance security shall remain valid until issuance by the Procuring Entity of the Certificate of Final Acceptance. The performance security may be released by the Procuring Entity and returned to the Contractor after the issuance of the Certificate of Final Acceptance subject to the following conditions: (a) (b) (c) 7.5. There are no pending claims against the Contractor or the surety company filed by the Procuring Entity; The Contractor has no pending claims for labor and materials filed against it; and Other terms specified in the SCC.
7.2.
7.3. 7.4.
The Contractor shall post an additional performance security following the amount and form specified in ITB Clause 32.2 to cover any cumulative increase of more than ten percent (10%) over the original value of the contract as a result of amendments to order or change orders, extra work orders and supplemental agreements, as the case may be. The Contractor shall cause the extension of the validity of the performance security to cover approved contract time extensions. In case of a reduction in the contract value or for partially completed Works under the contract which are usable and accepted by the Procuring Entity the use of which, in the judgment of the implementing agency or the Procuring Entity, will not affect the structural integrity of the entire project, the Procuring Entity shall allow a proportional reduction in the original performance security, provided that any such reduction is more than ten percent (10%) and that the aggregate of such reductions is not more than fifty percent (50%) of the original performance security. The Contractor, by entering into the Contract with the Procuring Entity, acknowledges the right of the Procuring Entity to institute action pursuant to Act 3688 against any subcontractor be they an individual, firm, partnership, corporation, or association supplying the Contractor with labor, materials and/or equipment for the performance of this Contract.
7.6.
7.7.
8.
Subcontracting
8.1. Unless otherwise indicated in the SCC, the Contractor cannot subcontract Works more than the percentage specified in ITB Clause 8.1.
8.2.
Subcontracting of any portion of the Works does not relieve the Contractor of any liability or obligation under this Contract. The Contractor will be responsible for the acts, defaults, and negligence of any subcontractor, its agents, servants or workmen as fully as if these were the Contractors own acts, defaults, or negligence, or those of its agents, servants or workmen. Subcontractors disclosed and identified during the bidding may be changed during the implementation of this Contract, subject to compliance with the required qualifications and the approval of the Procuring Entity.
8.3.
9.
Liquidated Damages
9.1. The Contractor shall pay liquidated damages to the Procuring Entity at the rate per day stated in the SCC for each day that the Completion Date is later than the Intended Completion Date. The total amount of liquidated damages shall not exceed the amount defined in the SCC. The Procuring Entity may deduct liquidated damages from payments due to the Contractor. Payment of liquidated damages shall not affect the Contractor. Once the cumulative amount of liquidated damages reaches ten percent (10%) of the amount of this Contract, the Procuring Entity shall rescind this Contract, without prejudice to other courses of action and remedies open to it. If the Intended Completion Date is extended after liquidated damages have been paid, the Engineer of the Procuring Entity shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment certificate. The Contractor shall be paid interest on the overpayment, calculated from the date of payment to the date of repayment, at the rates specified in GCC Clause 40.1.
9.2.
10.
11.
12.
elements in an infrastructure facility fails or collapses, thereby rendering the facility or part thereof incapable of withstanding the design loads, and/or endangering the safety of the users or the general public: (a) Contractor Where Structural Defects/Failures arise due to faults attributable to improper construction, use of inferior quality/substandard materials, and any violation of the contract plans and specifications, the contractor shall be held liable; Consultants Where Structural Defects/Failures arise due to faulty and/or inadequate design and specifications as well as construction supervision, then the consultant who prepared the design or undertook construction supervision for the project shall be held liable; Procuring Entitys Representatives/Project Manager/Construction Managers and Supervisors The project owners representative(s), project manager, construction manager, and supervisor(s) shall be held liable in cases where the Structural Defects/Failures are due to his/their willful intervention in altering the designs and other specifications; negligence or omission in not approving or acting on proposed changes to noted defects or deficiencies in the design and/or specifications; and the use of substandard construction materials in the project; Third Parties - Third Parties shall be held liable in cases where Structural Defects/Failures are caused by work undertaken by them such as leaking pipes, diggings or excavations, underground cables and electrical wires, underground tunnel, mining shaft and the like, in which case the applicable warranty to such structure should be levied to third parties for their construction or restoration works. Users - In cases where Structural Defects/Failures are due to abuse/misuse by the end user of the constructed facility and/or noncompliance by a user with the technical design limits and/or intended purpose of the same, then the user concerned shall be held liable.
(b)
(c)
(d)
(e)
12.5. The warranty against Structural Defects/Failures, except those occasioned on force majeure, shall cover the period specified in the SCC reckoned from the date of issuance of the Certificate of Final Acceptance by the Procuring Entity. 12.6. The Contractor shall be required to put up a warranty security in the form of cash, bank guarantee, letter of credit, GSIS or surety bond callable on demand, in accordance with the following schedule: Form of Warranty (a) Cash or letter of credit issued by Universal or Commercial bank: provided, however, that the letter of credit shall be confirmed or authenticated by a Universal or Commercial bank, if issued by a foreign bank (b) Bank guarantee confirmed by Universal or Commercial bank: provided, however, that the letter of credit shall be confirmed or authenticated by a Universal or Commercial bank, if issued by a foreign bank (c) Surety bond callable upon demand issued by GSIS or any surety or insurance company duly certified by the Insurance Commission Minimum Amount in Percentage (%) of Total Contract Price
12.7. The warranty security shall be stated in Philippine Pesos and shall remain effective for one year from the date of issuance of the Certificate of Final Acceptance by the Procuring Entity, and returned only after the lapse of said one year period. 12.8. In case of structural defects/failure occurring during the applicable warranty period provided in GCC Clause 12.5, the Procuring Entity shall undertake the necessary restoration or reconstruction works and shall be entitled to full reimbursement by the parties found to be liable for expenses incurred therein upon demand, without prejudice to the filing of appropriate administrative, civil, and/or criminal charges against the responsible persons as well as the forfeiture of the warranty security posted in favor of the Procuring Entity.
13.
14.
(b)
The risk of damage to the Works, Plant, Materials, and Equipment to the extent that it is due to a fault of the Procuring Entity or in the Procuring Entitys design, or due to war or radioactive contamination directly affecting the country where the Works are to be executed.
15.
Insurance
15.1. The Contractor shall, under his name and at his own expense, obtain and maintain, for the duration of this Contract, the following insurance coverage: (a) (b) (c) (d) Contractors All Risk Insurance; Transportation to the project Site of Equipment, Machinery, and Supplies owned by the Contractor; Personal injury or death of Contractors employees; and Comprehensive insurance for third party liability to Contractors direct or indirect act or omission causing damage to third persons.
15.2. The Contractor shall provide evidence to the Procuring Entitys Representative that the insurances required under this Contract have been effected and shall, within a reasonable time, provide copies of the insurance policies to the Procuring Entitys Representative. Such evidence and such policies shall be provided to the Procuring Entitys through the Procuring Entitys Representative. 15.3. The Contractor shall notify the insurers of changes in the nature, extent, or program for the execution of the Works and ensure the adequacy of the insurances at all times in accordance with the terms of this Contract and shall produce to the Procuring Entitys Representative the insurance policies in force including the receipts for payment of the current premiums. The above insurance policies shall be obtained from any reputable insurance company approved by the Procuring Entitys Representative.
15.4. If the Contractor fails to obtain and keep in force the insurances referred to herein or any other insurance which he may be required to obtain under the terms of this Contract, the Procuring Entity may obtain and keep in force any such insurances and pay such premiums as may be necessary for the purpose. From time to time, the Procuring Entity may deduct the amount it shall pay for said premiums including twenty five percent (25%) therein from any monies due, or which may become due, to the Contractor, without prejudice to the Procuring Entity exercising its right to impose other sanctions against the Contractor pursuant to the provisions of this Contract. 15.5. In the event the Contractor fails to observe the above safeguards, the Procuring Entity may, at the Contractors expense, take whatever measure is deemed necessary for its protection and that of the Contractors personnel and third parties, and/or order the interruption of dangerous Works. In addition, the Procuring Entity may refuse to make the payments under GCC Clause 40 until the Contractor complies with this Clause. 15.6. The Contractor shall immediately replace the insurance policy obtained as required in this Contract, without need of the Procuring Entitys demand, with a new policy issued by a new insurance company acceptable to the Procuring Entity for any of the following grounds: (a) The issuer of the insurance policy to be replaced has: (i) (ii) (iii) (iv) (v) become bankrupt; been placed under receivership or under a management committee; been sued for suspension of payment; or been suspended by the Insurance Commission and its license to engage in business or its authority to issue insurance policies cancelled; or Where reasonable grounds exist that the insurer may not be able, fully and promptly, to fulfill its obligation under the insurance policy.
16.
(b)
16.5. All materials on the Site, Plant, Equipment, and Works shall be deemed to be the property of the Procuring Entity if this Contract is rescinded because of the Contractors default.
17.
(b)
18.
(b) (c)
(d)
(e)
(f) (g)
(h)
behaviors relative to contract acquisition and implementation, such as, but not limited to, the following: (i) (ii) (iii) (iv) corrupt, fraudulent, collusive and coercive practices as defined in ITB Clause 3.1(a); drawing up or using forged documents; using adulterated materials, means or methods, or engaging in production contrary to rules of science or the trade; and any other act analogous to the foregoing.
18.4. The Funding Source or the Procuring Entity, as appropriate, will seek to impose the maximum civil, administrative and/or criminal penalties available under the applicable law on individuals and organizations deemed to be involved with corrupt, fraudulent, or coercive practices. 18.5. When persons from either party to this Contract gives notice of a fundamental breach to the Procuring Entitys Representative in order to terminate the existing contract for a cause other than those listed under GCC Clause 18.3, the Procuring Entitys Representative shall decide whether the breach is fundamental or not. 18.6. If this Contract is terminated, the Contractor shall stop work immediately, make the Site safe and secure, and leave the Site as soon as reasonably possible.
19.
(b)
The Notice to Terminate shall be accompanied by a copy of the Verified Report; (c) Within a period of seven (7) calendar days from receipt of the Notice of Termination, the Contractor shall submit to the Head of the Procuring Entity a verified position paper stating why the contract should not be terminated. If the Contractor fails to show cause after the lapse of the seven (7) day period, either by inaction or by default, the Head of the Procuring Entity shall issue an order terminating the contract; The Procuring Entity may, at anytime before receipt of the Bidders verified position paper to withdraw the Notice to Terminate if it is determined that certain items or works subject of the notice had been completed, delivered, or performed before the Contractors receipt of the notice;
(d)
(e)
Within a non-extendible period of ten (10) calendar days from receipt of the verified position paper, the Head of the Procuring Entity shall decide whether or not to terminate this Contract. It shall serve a written notice to the Contractor of its decision and, unless otherwise provided in the said notice, this Contract is deemed terminated from receipt of the Contractor of the notice of decision. The termination shall only be based on the ground(s) stated in the Notice to Terminate; and The Head of the Procuring Entity may create a Contract Termination Review Committee (CTRC) to assist him in the discharge of this function. All decisions recommended by the CTRC shall be subject to the approval of the Head of the Procuring Entity.
(f)
19.2. Pursuant to Section 69(f) of RA 9184 and without prejudice to the imposition of additional administrative sanctions as the internal rules of the agency may provide and/or further criminal prosecution as provided by applicable laws, the procuring entity shall impose on contractors after the termination of the contract the penalty of suspension for one (1) year for the first offense, suspension for two (2) years for the second offense from participating in the public bidding process, for violations committed during the contract implementation stage, which include but not limited to the following: (a) (b) Failure of the contractor, due solely to his fault or negligence, to mobilize and start work or performance within the specified period in the Notice to Proceed (NTP); Failure by the contractor to fully and faithfully comply with its contractual obligations without valid cause, or failure by the contractor to comply with any written lawful instruction of the procuring entity or its representative(s) pursuant to the implementation of the contract. For the procurement of infrastructure projects or consultancy contracts, lawful instructions include but are not limited to the following: (i) (ii) (iii) Employment of competent technical personnel, competent engineers and/or work supervisors; Provision of warning signs and barricades in accordance with approved plans and specifications and contract provisions; Stockpiling in proper places of all materials and removal from the project site of waste and excess materials, including broken pavement and excavated debris in accordance with approved plans and specifications and contract provisions; Deployment of committed equipment, facilities, support staff and manpower; and Renewal of the effectivity dates of the performance security after its expiration during the course of contract implementation.
Assignment and subcontracting of the contract or any part thereof or substitution of key personnel named in the proposal without prior written approval by the procuring entity. Poor performance by the contractor or unsatisfactory quality and/or progress of work arising from his fault or negligence as reflected in the Constructor's Performance Evaluation System (CPES) rating sheet. In the absence of the CPES rating sheet, the existing performance monitoring system of the procuring entity shall be applied. Any of the following acts by the constructor shall be construed as poor performance: (i) (ii) Negative slippage of 15% and above within the critical path of the project due entirely to the fault or negligence of the contractor; and Quality of materials and workmanship not complying with the approved specifications arising from the contractor's fault or negligence.
(d)
(e)
Willful or deliberate abandonment or non-performance of the project or contract by the contractor resulting to substantial breach thereof without lawful and/or just cause.
In addition to the penalty of suspension, the performance security posted by the contractor shall also be forfeited.
20.
20.5. The net balance due shall be paid or repaid within a reasonable time period from the time of the notice of termination.
21.
Resolution of Disputes
21.1. If any dispute or difference of any kind whatsoever shall arise between the parties in connection with the implementation of the contract covered by the Act and this IRR, the parties shall make every effort to resolve amicably such dispute or difference by mutual consultation. 21.2. If the Contractor believes that a decision taken by the PROCURING ENTITYs Representative was either outside the authority given to the PROCURING ENTITYs Representative by this Contract or that the decision was wrongly taken, the decision shall be referred to the Arbiter indicated in the SCC within fourteen (14) days of the notification of the PROCURING ENTITYs Representatives decision. 21.3. Any and all disputes arising from the implementation of this Contract covered by the R.A. 9184 and its IRR shall be submitted to arbitration in the Philippines according to the provisions of Republic Act No. 876, otherwise known as the Arbitration Law and Republic Act 9285, otherwise known as the Alternative Dispute Resolution Act of 2004: Provided, however, That, disputes that are within the competence of the Construction Industry Arbitration Commission to resolve shall be referred thereto. The process of arbitration shall be incorporated as a provision in this Contract that will be executed pursuant to the provisions of the Act and its IRR-A: Provided, further, That, by mutual agreement, the parties may agree in writing to resort to other alternative modes of dispute resolution. Additional instructions on resolution of disputes, if any, shall be indicated in the SCC.
22.
(a) (b)
The Procuring Entity is obligated to notify the Contractor of such suspension within seven (7) days of having received the suspension notice. If the Contractor has not received sums due it for work already done within forty five (45) days from the time the Contractors claim for payment has been certified by the Procuring Entitys Representative, the Contractor may immediately issue a suspension of work notice in accordance with SCC Clause 45.2.
23.
24.
25.
26.
27.
Right to Vary
27.1. The Procuring Entitys Representative with the prior approval of the Procuring Entity may instruct Variations, up to a maximum cumulative amount of ten percent (10%) of the original contract cost. 27.2. Variations shall be valued as follows: (a) (b) (c) (d) At a lump sum price agreed between the parties; where appropriate, at rates in this Contract; in the absence of appropriate rates, the rates in this Contract shall be used as the basis for valuation; or failing which at appropriate new rates, equal to or lower than current industry rates and to be agreed upon by both parties and approved by the Head of the Procuring Entity.
28.
29.
Dayworks
29.1. Subject to GCC Clause 43 on Variation Order, and if applicable as indicated in the SCC, the Dayworks rates in the Contractors Bid shall be used for small additional amounts of work only when the Procuring Entitys Representative has given written instructions in advance for additional work to be paid for in that way. 29.2. All work to be paid for as Dayworks shall be recorded by the Contractor on forms approved by the Procuring Entitys Representative. Each completed form shall be verified and signed by the Procuring Entitys Representative within two days of the work being done. 29.3. The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks forms.
30.
Early Warning
30.1. The Contractor shall warn the Procuring Entitys Representative at the earliest opportunity of specific likely future events or circumstances that may adversely affect the quality of the work, increase the Contract Price, or delay the execution of the Works. The Procuring Entitys Representative may require the Contractor to provide an estimate of the expected effect of the future event or circumstance on the Contract Price and Completion Date. The estimate shall be provided by the Contractor as soon as reasonably possible. 30.2. The Contractor shall cooperate with the Procuring Entitys Representative in making and considering proposals for how the effect of such an event or circumstance can be avoided or reduced by anyone involved in the work and in carrying out any resulting instruction of the Procuring Entitys Representative.
31.
Program of Work
31.1. Within the time stated in the SCC, the Contractor shall submit to the Procuring Entitys Representative for approval a Program of Work showing the general methods, arrangements, order, and timing for all the activities in the Works. 31.2. An update of the Program of Work shall the show the actual progress achieved on each activity and the effect of the progress achieved on the timing of the remaining work, including any changes to the sequence of the activities. 31.3. The Contractor shall submit to the Procuring Entitys Representative for approval an updated Program of Work at intervals no longer than the period stated in the SCC. If the Contractor does not submit an updated Program of Work within this period, the PROCURING ENTITYs Representative may withhold the amount stated in the SCC from
the next payment certificate and continue to withhold this amount until the next payment after the date on which the overdue Program of Work has been submitted. 31.4. The Procuring Entitys Representatives approval of the Program of Work shall not alter the Contractors obligations. The Contractor may revise the Program of Work and submit it to the Procuring Entitys Representative again at any time. A revised Program of Work shall show the effect of any approved Variations; and if allowed, any Compensation Event. 31.5. When the Program of Work is updated, the Contractor shall provide the Procuring Entitys Representative with an updated cash flow forecast. The cash flow forecast shall include different currencies, as defined in the Contract, converted as necessary using the Contract exchange rates. 31.6. All Variations shall be included in updated Program of Work produced by the Contractor.
32.
Management Conferences
32.1. Either the Procuring Entitys Representative or the Contractor may require the other to attend a Management Conference. The Management Conference shall review the plans for remaining work and deal with matters raised in accordance with the early warning procedure. 32.2. The Procuring Entitys Representative shall record the business of Management Conferences and provide copies of the record to those attending the Conference and to the Procuring Entity . The responsibility of the parties for actions to be taken shall be decided by the PROCURING ENTITYs Representative either at the Management Conference or after the Management Conference and stated in writing to all who attended the Conference.
33.
Bill of Quantities
33.1. The Bill of Quantities shall contain items of work for the construction, installation, testing, and commissioning of work to be done by the Contractor. 33.2. The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for the quantity of the work done at the rate in the Bill of Quantities for each item. 33.3. If the final quantity of any work done differs from the quantity in the Bill of Quantities for the particular item and is not more than twenty five percent (25%) of the original quantity, provided the aggregate changes for all items do not exceed ten percent (10%) of the Contract price, the Procuring Entitys Representative shall make the necessary adjustments to allow for the changes subject to applicable laws, rules, and regulations. 33.4. If requested by the Procuring Entitys Representative, the Contractor shall provide the Procuring Entitys Representative with a detailed cost breakdown of any rate in the Bill of Quantities.
34.
35.
Identifying Defects
The Procuring Entitys Representative shall check the Contractors work and notify the Contractor of any defects that are found. Such checking shall not affect the Contractors responsibilities. The Procuring Entitys Representative may instruct the Contractor to search uncover defects and test any work that the Procuring Entitys Representative considers below standards and defective.
36.
Cost of Repairs
Loss or damage to the Works or Materials to be incorporated in the Works between the Start Date and the end of the Defects Liability Periods shall be remedied by the Contractor at the Contractors cost if the loss or damage arises from the Contractors acts or omissions.
37.
Correction of Defects
37.1. The Procuring Entitys Representative shall give notice to the Contractor of any defects before the end of the Defects Liability Period, which begins at Completion Date up to final acceptance by the Procuring Entitys unless otherwise specified in the SCC. The Defects Liability Period shall be extended for as long as defects remain to be corrected. 37.2. Every time notice of a defect is given, the Contractor shall correct the notified defect within the length of time specified in the Procuring Entitys Representatives notice. 37.3. The Contractor shall correct the defects which he notices himself before the end of the Defects Liability Period. 37.4. The Procuring Entity shall certify that all defects have been corrected. If the Procuring Entity considers that correction of a defect is not essential, he can request the Contractor to submit a quotation for the corresponding reduction in the Contract Price. If the Procuring Entity accepts the quotation, the corresponding change in the SCC is a Variation.
38.
Uncorrected Defects
38.1. The Procuring Entity shall give the Contractor at least fourteen (14) days notice of his intention to use a third party to correct a Defect. If the Contractor does not correct the Defect himself within the period, the Procuring Entity may have the Defect corrected by the third party. The cost of the correction will be deducted from the Contract Price. 38.2. The use of a third party to correct defects that are uncorrected by the Contractor will in no way relieve the Contractor of its liabilities and warranties under the Contract.
39.
Advance Payment
39.1. The Procuring Entity shall, upon a written request of the contractor which shall be submitted as a contract document, make an advance payment to the contractor in an amount not exceeding fifteen percent (15%) of the total contract price, to be made in lump sum or, at the most two, installments according to a schedule specified in the SCC. 39.2. The advance payment shall be made only upon the submission to and acceptance by the Procuring Entity of an irrevocable standby letter of credit of equivalent value from a commercial bank, a bank guarantee or a surety bond callable upon demand, issued by a surety or insurance company duly licensed by the Insurance Commission and confirmed by the Procuring Entity. 39.3. The advance payment shall be repaid by the Contractor by an amount equal to the percentage of the total contract price used for the advance payment. 39.4. The contractor may reduce his standby letter of credit or guarantee instrument by the amounts refunded by the Monthly Certificates in the advance payment. 39.5. The Procuring Entity will provide an Advance Payment on the Contract Price as stipulated in the Conditions of Contract, subject to the maximum amount stated in SCC Clause 39.1.
40.
Progress Payments
40.1. The Contractor may submit a request for payment for Work accomplished. Such request for payment shall be verified and certified by the Procuring Entitys Representative/Project Engineer. Except as otherwise stipulated in the SCC, materials and equipment delivered on the site but not completely put in place shall not be included for payment. 40.2. The Procuring Entity shall deduct the following from the certified gross amounts to be paid to the contractor as progress payment: (a) (b) (c) (d) (e) Cumulative value of the work previously certified and paid for. Portion of the advance payment to be recouped for the month. Retention money in accordance with the condition of contract. Amount to cover third party liabilities. Amount to cover uncorrected discovered defects in the works.
40.3. Payments shall be adjusted by deducting therefrom the amounts for advance payments and retention. The Procuring Entity shall pay the Contractor the amounts certified by the Procuring Entitys Representative within twenty eight (28) days from the date each certificate was issued. Unless otherwise indicated in the SCC, no payment of interest for delayed payments and adjustments shall be made by the Procuring Entity. 40.4. The first progress payment may be paid by the Procuring Entity to the Contractor provided that at least twenty percent (20%) of the work has been accomplished as certified by the Procuring Entitys Representative. 40.5. Items of the Works for which a price of 0 (zero) has been entered will not be paid for by the Procuring Entity and shall be deemed covered by other rates and prices in the Contract.
41.
Payment Certificates
41.1. The Contractor shall submit to the Procuring Entitys Representative monthly statements of the estimated value of the work executed less the cumulative amount certified previously. 41.2. The Procuring Entitys Representative shall check the Contractors monthly statement and certify the amount to be paid to the Contractor. 41.3. The value of Work executed shall: (a) (b) (c) be determined by the Procuring Entitys Representative; comprise the value of the quantities of the items in the Bill of Quantities completed; and include the valuations of approved variations.
41.4. The Procuring Entitys Representative may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
42.
Retention
42.1. The Procuring Entity shall retain from each payment due to the Contractor an amount equal to a percentage thereof using the rate as specified in SCC Clause 42.2. 42.2. Progress payments are subject to retention of ten percent (10%), unless otherwise specified in the SCC, referred to as the retention money. Such retention shall be based on the total amount due to the Contractor prior to any deduction and shall be retained from every progress payment until fifty percent (50%) of the value of Works, as determined by the Procuring Entity, are completed. If, after fifty percent (50%) completion, the Work is
satisfactorily done and on schedule, no additional retention shall be made; otherwise, the ten percent (10%) retention shall again be imposed using the rate specified therefor. 42.3. The total retention money shall be due for release upon final acceptance of the Works. The Contractor may, however, request the substitution of the retention money for each progress billing with irrevocable standby letters of credit from a commercial bank, bank guarantees or surety bonds callable on demand, of amounts equivalent to the retention money substituted for and acceptable to the Procuring Entity, provided that the project is on schedule and is satisfactorily undertaken. Otherwise, the ten (10%) percent retention shall be made. Said irrevocable standby letters of credit, bank guarantees and/or surety bonds, to be posted in favor of the Government shall be valid for a duration to be determined by the concerned implementing office/agency or Procuring Entity and will answer for the purpose for which the ten (10%) percent retention is intended, i.e., to cover uncorrected discovered defects and third party liabilities. 42.4. On completion of the whole Works, the Contractor may substitute retention money with an on demand Bank guarantee in a form acceptable to the Procuring Entity.
43.
Variation Orders
43.1. Variation Orders may be issued by the Procuring Entity to cover any increase/decrease in quantities, including the introduction of new work items that are not included in the original contract or reclassification of work items that are either due to change of plans, design or alignment to suit actual field conditions resulting in disparity between the preconstruction plans used for purposes of bidding and the as staked plans or construction drawings prepared after a joint survey by the Contractor and the Procuring Entity after award of the contract, provided that the cumulative amount of the Variation Order does not exceed ten percent (10%) of the original project cost. The addition/deletion of Works should be within the general scope of the project as bid and awarded. The scope of works shall not be reduced so as to accommodate a positive Variation Order. A Variation Order may either be in the form of a Change Order or Extra Work Order. 43.2. A Change Order may be issued by the implementing official to cover any increase/decrease in quantities of original Work items in the contract. 43.3. An Extra Work Order may be issued by the implementing official to cover the introduction of new work necessary for the completion, improvement or protection of the project which were not included as items of Work in the original contract, such as, where there are subsurface or latent physical conditions at the site differing materially from those indicated in the contract, or where there are duly unknown physical conditions at the site of an unusual nature differing materially from those ordinarily encountered and generally recognized as inherent in the Work or character provided for in the contract. 43.4. Any cumulative Variation Order beyond ten percent (10%) shall be subject of another contract to be bid out if the works are separable from the original contract. In exceptional cases where it is urgently necessary to complete the original scope of work, the Head of the Procuring Entity may authorize a positive Variation Order go beyond ten percent (10%) but not more than twenty percent (20%) of the original contract price, subject to the guidelines to be determined by the GPPB: Provided, however, That appropriate sanctions shall be imposed on the designer, consultant or official responsible for the original detailed engineering design which failed to consider the Variation Order beyond ten percent (10%). 43.5. In claiming for any Variation Order, the Contractor shall, within seven (7) calendar days after such work has been commenced or after the circumstances leading to such condition(s) leading to the extra cost, and within twenty-eight (28) calendar days deliver a written communication giving full and detailed particulars of any extra cost in order that it may be investigated at that time. Failure to provide either of such notices in the time stipulated shall constitute a waiver by the contractor for any claim. The preparation and submission of Variation Orders are as follows: (a) If the Procuring Entitys representative/Project Engineer believes that a Change Order or Extra Work Order should be issued, he shall prepare the proposed Order accompanied with the notices submitted by the Contractor, the plans therefore, his computations as to the quantities of the additional works involved per item indicating
the specific stations where such works are needed, the date of his inspections and investigations thereon, and the log book thereof, and a detailed estimate of the unit cost of such items of work, together with his justifications for the need of such Change Order or Extra Work Order, and shall submit the same to the Head of the Procuring Entity for approval. (b) The Head of the Procuring Entity or his duly authorized representative, upon receipt of the proposed Change Order or Extra Work Order shall immediately instruct the technical staff of the Procuring Entitys to conduct an on-the-spot investigation to verify the need for the Work to be prosecuted. A report of such verification shall be submitted directly to the Head of the Procuring Entity or his duly authorized representative. The, Head of the Procuring Entity or his duly authorized representative, after being satisfied that such Change Order or Extra Work Order is justified and necessary, shall review the estimated quantities and prices and forward the proposal with the supporting documentation to the Head of Procuring Entity for consideration. If, after review of the plans, quantities and estimated unit cost of the items of work involved, the proper office of the procuring entity empowered to review and evaluate Change Orders or Extra Work Orders recommends approval thereof, Head of the Procuring Entity or his duly authorized representative, believing the Change Order or Extra Work Order to be in order, shall approve the same. The timeframe for the processing of Variation Orders from the preparation up to the approval by the Head of the Procuring Entity concerned shall not exceed thirty (30) calendar days.
(c)
(d)
(e)
44.
Contract Completion
Once the project reaches an accomplishment of ninety five (95%) of the total contract amount, the Procuring Entity may create an inspectorate team to make preliminary inspection and submit a punch-list to the Contractor in preparation for the final turnover of the project. Said punch-list will contain, among others, the remaining Works, Work deficiencies for necessary corrections, and the specific duration/time to fully complete the project considering the approved remaining contract time. This, however, shall not preclude the claim of the Procuring Entity for liquidated damages.
45.
Suspension of Work
45.1. The Procuring Entity shall have the authority to suspend the work wholly or partly by written order for such period as may be deemed necessary, due to force majeure or any fortuitous events or for failure on the part of the Contractor to correct bad conditions which are unsafe for workers or for the general public, to carry out valid orders given by the Procuring Entity or to perform any provisions of the contract, or due to adjustment of plans to suit field conditions as found necessary during construction. The Contractor shall immediately comply with such order to suspend the work wholly or partly. 45.2. The Contractor or its duly authorized representative shall have the right to suspend work operation on any or all projects/activities along the critical path of activities after fifteen (15) calendar days from date of receipt of written notice from the Contractor to the district engineer/regional director/consultant or equivalent official, as the case may be, due to the following: (a) (b) (c) There exist right-of-way problems which prohibit the Contractor from performing work in accordance with the approved construction schedule. Requisite construction plans which must be owner-furnished are not issued to the contractor precluding any work called for by such plans. Peace and order conditions make it extremely dangerous, if not possible, to work. However, this condition must be certified in writing by the Philippine National Police (PNP) station which has responsibility over the affected area and confirmed by the Department of Interior and Local Government (DILG) Regional Director.
(d) (e)
There is failure on the part of the Procuring Entity to deliver government-furnished materials and equipment as stipulated in the contract. Delay in the payment of Contractors claim for progress billing beyond forty-five (45) calendar days from the time the Contractors claim has been certified to by the procuring entitys authorized representative that the documents are complete unless there are justifiable reasons thereof which shall be communicated in writing to the Contractor.
45.3. In case of total suspension, or suspension of activities along the critical path, which is not due to any fault of the Contractor, the elapsed time between the effective order of suspending operation and the order to resume work shall be allowed the Contractor by adjusting the contract time accordingly.
46.
Payment on Termination
46.1. If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the Procuring Entitys Representative shall issue a certificate for the value of the work done and Materials ordered less advance payments received up to the date of the issue of the certificate and less the percentage to apply to the value of the work not completed, as indicated in the SCC. Additional Liquidated Damages shall not apply. If the total amount due to the Procuring Entity exceeds any payment due to the Contractor, the difference shall be a debt payable to the Procuring Entity. 46.2. If the Contract is terminated for the Procuring Entitys convenience or because of a fundamental breach of Contract by the Procuring Entity, the Procuring Entitys Representative shall issue a certificate for the value of the work done, Materials ordered, the reasonable cost of removal of Equipment, repatriation of the Contractors personnel employed solely on the Works, and the Contractors costs of protecting and securing the Works, and less advance payments received up to the date of the certificate. 46.3. The net balance due shall be paid or repaid within twenty eight (28) days from the notice of termination. 46.4. If the Contractor has terminated the Contract under GCC Clauses 17 or 18, the Procuring Entity shall promptly return the Performance Security to the Contractor.
47.
47.5. Extension of contract time shall be granted for rainy/unworkable days considered unfavorable for the prosecution of the works at the site, based on the actual conditions obtained at the site, in excess of the number of rainy/unworkable days pre-determined by the Procuring Entity in relation to the original contract time during the conduct of detailed engineering and in the preparation of the contract documents as agreed upon by the parties before contract perfection, and/or for equivalent period of delay due to major calamities such as exceptionally destructive typhoons, floods and earthquakes, and epidemics, and for causes such as non-delivery on time of materials, working drawings, or written information to be furnished by the Procuring Entity, non-acquisition of permit to enter private properties within the right-of-way resulting in complete paralyzation of construction activities, and other meritorious causes as determined by the Procuring Entitys Representative and approved by the Head of the Procuring Entity. Shortage of construction materials, general labor strikes, and peace and order problems that disrupt construction operations through no fault of the Contractor may be considered as additional grounds for extension of contract time provided they are publicly felt and certified by appropriate government agencies such as DTI, DOLE, DILG, and DND, among others. The written consent of bondsmen must be attached to any request of the Contractor for extension of contract time and submitted to the Procuring Entity for consideration and the validity of the Performance Security shall be correspondingly extended.
48.
Price Adjustment
Except for extraordinary circumstances as determined by NEDA and approved by the GPPB, no price adjustment shall be allowed unless otherwise specified in the SCC.
49.
Completion
The Contractor shall request the Procuring Entitys Representative to issue a certificate of Completion of the Works, and the Procuring Entitys Representative will do so upon deciding that the work is completed.
50.
Taking Over
The Procuring Entity shall take over the Site and the Works within seven (7) days from the date the Procuring Entitys Representative issues a certificate of Completion.
51.
1.22 1.23
The Procuring Entitys Representative is OMAR P. DIRON, OIC- District Engineer, DPWH-MOFDEO, Purok 5 Brgy. 26, Gingoog City The Site is located at the BCIR Km 1398+000 - Km 1398+700 List here locations of other Sites, if any.
1.27 1.30
The Start Date is December 23, 2011 The Works consist of the following items: 101(3)-Removal of Existing Pavement, 102(2)-Surplus Common Excavation, 200-Aggregate Sub-Base Course,201Aggregate Base Course, 311-Portland Cement Concrete Pavement, SPLI-Safety and Health, SPLII-Mob./Demobilization, SPLIII- Instn of DPWH Std. Billboard If different dates are specified for completion of the Works by section (sectional completion), these dates should be listed here. NO Instructions The Procuring Entity shall give possession of all parts of the Site to the Contractor on December 23, 2011. The Contractor shall employ the following Key Personnel: Project Engineer (CE), Licensed Materials Engineer, Safety Officer, Foreman, Skilled Workers/Laborers
No further instructions. No further instructions. No further instructions. The applicable liquidated damages is at least one tenth (1/10) of one percent of the cost of the unperformed portion for every day of delay. The maximum deduction shall be ten percent (10%) of the amount of the contract, the Procuring Entity shall rescind the contract, without prejudice to other courses of action and remedies open to it.
10 12.5
No further instructions. Select one, delete the other. In case of permanent structures, such as buildings of types 4 and 5 as classified under the National Building Code of the Philippines and other structures made of steel, iron, or concrete which comply with relevant structural codes (e.g., DPWH Standard Specifications), such as, but not limited to, steel/concrete bridges, flyovers, aircraft movement areas, ports, dams, tunnels, filtration and treatment plants, sewerage systems, power plants, transmission and communication towers, railway system, and other similar permanent structures: Fifteen (15) years. In case of semi-permanent structures, such as buildings of types 1, 2, and 3 as classified under the National Building Code of the Philippines, concrete/asphalt roads, concrete river control, drainage, irrigation lined canals, river landing, deep wells, rock causeway, pedestrian overpass, and other similar semi-permanent structures: Five (5) years. In case of other structures, such as Bailey and wooden bridges, shallow wells, spring developments, and other similar structures: Two (2) years.
13 21.2 21.3 26.1 29.1 31.1 31.3 34.3 37.1 39.1 40.1 40.3 42.2 48 51.1 51.2
No additional provision. The Arbiter is: DPWH-Misamis Oriental First District Engineering Office, Purok 5 Brgy 26, Gingoog City No further instructions. No further instructions. No dayworks are applicable to the contract. The Contractor shall submit the Program of Work to the Procuring Entitys Representative upon issuance of Notice of Award None The Funding Source is 2012 - GAA Reg. Infra No further instructions. The amount of the advance payment is 15% of the Contract Price and to be collected after the receipt of Notice to Proceed No further instructions. No further instructions. No further instructions. No further instructions. As built drawings are required after the completion of the project on April 20, 2012. The amount to be withheld for failing to produce as built drawings and/or operating and maintenance manuals by the date required is 1% of the Contract Cost
11KK0054
Contract Reference Number
Misamis Oriental First District Engineering Office OFFICE OF THE DISTRICT ENGINEER Purok 5 Brgy. 26, Gingoog City
BILL OF QUANTITIES
Name and Location of Contract ABC (Php)
11,791,360.00 120 CD
Item No.
Description
Qty
Unit
Amount (Pesos)
In words: (pesos)
101(3)
3,738.60
sq.m
In figure: Php)____________________ In words: (pesos) _________________ In figure: (Php)______________________________ In words: (pesos) ___________________
102(2)
747.72
Cu.m
In figure: (Php)___________________ In words: (pesos) _________________ In figure: (Php)______________________________ In words: (pesos) ____________________
200
373.86
Cu.m
In figure: (Php)__________________ In words: (pesos) _________________ In figure: (Php)______________________________ In words: (pesos) ____________________
201
167.20
Cu.m
In figure: (Php)__________________ In words: (pesos) _________________ In figure: (Php)______________________________ In words: (pesos) ____________________
311
3,738.6
sq.m
In figure: (Php)__________________ In words: (pesos) _________________ In figure: (Php)______________________________ In words: (pesos) ____________________
SPL I
1.00
ls
In figure: (Php)__________________ In words: (pesos) _________________ In figure: (Php)______________________________ In words: (pesos) ____________________
SPL II
Mob./Demobilization
1.00
ls
In figure: (Php)__________________ In words: (pesos) _________________ In figure: (Php)______________________________ In words: (pesos) ____________________
SPL III
1.00
set
In figure: (Php)__________________ In figure: (Php)______________________________
Submitted by: __________________________ Name/Signature of Bidder __________________________ Position ___________________________ Name of Bidder
Date: ____________________
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Region X Contract Reference Number
Misamis Oriental First District Engineering Office OFFICE OF THE DISTRICT ENGINEER Purok 5 Brgy. 26, Gingoog City
BILL OF QUANTITIES
Name and Location of Contract ABC (Php)
Item No.
Description
Quantity
Unit
Amount (Pesos)
In words: (pesos)
In figure: (Php)__________________
In figure: (Php)______________________________
Date: ____________________
__________________________
Position
___________________________
Name of Bidder
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Region X Contract Reference Number
Misamis Oriental First District Engineering Office OFFICE OF THE DISTRICT ENGINEER Purok 5 Brgy. 26, Gingoog City
BILL OF QUANTITIES
Name and Location of Contract ABC (Php)
Item No.
Description
Quantity
Unit
Amount (Pesos)
In words: (pesos)
In figure: (Php)__________________
In figure: (Php)__________________
In figure: (Php)______________________________
Date: ____________________
__________________________
Position
___________________________
Name of Bidder
Republic of the Philippines DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Region X Misamis Oriental First District Engineering Office OFFICE OF THE DISTRICT ENGINEER P-5 Brgy. 26, Gingoog City
11KK0054
Rehab/Reconstn/Upgrading of Damaged Paved National Road
Name of Contract
Bid Form
_________________ Date OMAR P. DIRON OIC-District Engineer DPWH-Misamis Oriental First District Engineering Office Purok 5, Brgy. 26, Gingoog City We, the undersigned, declare that: (a) We have examined and have no reservation to the Bidding Documents, including Addenda, for the Contract [insert name of contract]; (b) We offer to execute the Works for this Contract in accordance with the Bid and Bid Data Sheet, General and Special Conditions of Contract accompanying this Bid; The total price of our Bid, excluding any discounts offered in item (d) below is: [insert information]; The discounts offered and the methodology for their application are: [insert information]; (c) Our Bid shall be valid for a period of [insert number] days from the date fixed for the Bid submission deadline in accordance with the Bidding Documents, and it shall remain binding upon us and may be accepted at any time before the expiration of that period; (d) If our Bid is accepted, we commit to obtain a Performance Security in the amount of [insert percentage amount] percent of the Contract Price for the due performance of the Contract; (e) Our firm, including any subcontractors or suppliers for any part of the Contract, have nationalities from the following eligible countries: [insert information]; (f) We are not participating, as Bidders, in more than one Bid in this bidding process, other than alternative offers in accordance with the Bidding Documents; (g) Our firm, its affiliates or subsidiaries, including any subcontractors or suppliers for any part of the Contract, has not been declared ineligible by the Funding Source; (h) We understand that this Bid, together with your written acceptance thereof included in your notification of award, shall constitute a binding contract between us, until a formal Contract is prepared and executed; and (i) We understand that you are not bound to accept the Lowest Evaluated Bid or any other Bid that you may receive. Name: In the capacity of: Signed: Duly authorized to sign the Bid for and on behalf of: Date: ___________
REPUBLIC OF THE PHILIPPINES) CITY OF __________________ ) S.S SUBSCRIBED AND SWORN to before me this ______ day of _____________ 2011, affiant exhibited to me his/her Community Tax Certificate No. ____________________ issued on ________________ at _______________________. Doc. No. ________ Page No. ________ Book No. ________ Series of 2011.
AFFIDAVIT
I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of Affiant], after having been duly sworn in accordance with law, do hereby depose and state that: 1. Select one, delete the other: If a sole proprietorship: I am the sole proprietor of [Name of Bidder] with office address at [address of Bidder]; If a partnership, corporation, cooperative, or joint venture: I am the duly authorized and designated representative of [Name of Bidder] with office address at [address of Bidder]; 2. Select one, delete the other: If a sole proprietorship: As the owner and sole proprietor of [Name of Bidder], I have full power and authority to do, execute and perform any and all acts necessary to represent it in the bidding for [Name of the Project] of the [Name of the Procuring Entity]; If a partnership, corporation, cooperative, or joint venture: I am granted full power and authority to do, execute and perform any and all acts necessary and/or to represent the [Name of Bidder] in the bidding as shown in the attached [state title of attached document showing proof of authorization (e.g., duly notarized Secretarys Certificate issued by the corporation or the members of the joint venture)]; 3. [Name of Bidder] is not blacklisted or barred from bidding by the Government of the Philippines or any of its agencies, offices, corporations, or Local Government Units, foreign government/foreign or international financing institution whose blacklisting rules have been recognized by the Government Procurement Policy Board; 4. Each of the documents submitted in satisfaction of the bidding requirements is an authentic copy of the original, complete, and all statements and information provided therein are true and correct; 5. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly authorized representative(s) to verify all the documents submitted; 6. Select one, delete the rest: If a sole proprietorship: I am not related to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project Management Office or the end-user unit, and the project consultants by consanguinity or affinity up to the third civil degree; If a partnership or cooperative: None of the officers and members of [Name of Bidder] is related to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project Management Office or the end-user unit, and the project consultants by consanguinity or affinity up to the third civil degree; If a corporation or joint venture: None of the officers, directors, and controlling stockholders of [Name of Bidder] is related to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project Management Office or the end-user unit, and the project consultants by consanguinity or affinity up to the third civil degree;
7. [Name of Bidder] complies with existing labor laws and standards; and 8. [Name of Bidder] is aware of and has undertaken the following responsibilities as a Bidder: a) Carefully examine all of the Bidding Documents; b) Acknowledge all conditions, local or otherwise, affecting the implementation of the Contract; c) Made an estimate of the facilities available and needed for the contract to be bid, if any; and d) Inquire or secure Supplemental/Bid Bulletin(s) issued for the [Name of the Project].
IN WITNESS WHEREOF, I have hereunto set my hand this __ day of ___, 20__ at ____________, Philippines.
ACKNOWLEDGEMENT
SUBSCRIBED AND SWORN to before me this ______ day of _____________ 2011, affiant exhibited to me his/her Community Tax Certificate No. ____________________ issued on ________________ at _______________________. Doc. No. ________ Page No. ________ Book No. ________ Series of 2011.
AFFIDAVIT
NO CONFLICT OF INTEREST
I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of Affiant], after having been duly sworn in accordance with law, do hereby depose and state that:
1. That, I am authorized representative of [Name of Bidder] with of office address at [address of Bidder]; 2. That the firm/partnership/joint venture/corporation, or any of its officers, directors, controlling stockholders and members, I represent for the bidding of the above-mentioned project HAS NO conflicting interest with the another Bidder in any of the events described in paragraphs (a) through (c) and a general conflicting interest in any of the circumstances set out in paragraphs (d) through (g) below; a) A Bidder has controlling shareholders in common with another bidder; b) A Bidder receives or has received any direct or indirect subsidy from any other bidder; c. A Bidder has the same legal representative as that of the another Bidder for the purpose of this bid; d) A Bidder has a relationship, directly or through third parties, that puts them in a position to have access to information about or influence on the Bid of another Bidder or an organization who lends, or temporarily seconds, its personnel to firms or organizations which are engaged in consulting services for the preparation related to procurement for or implementation of the project if the personnel would be involved in any capacity on the same project; e) A Bidder submits more than one bid in this bidding process, however, this does not limit the participation of subcontractors in more than one bid; f) A Bidder who participated as a consultant in the preparation of the design or technical specifications of the goods and related services that are subject of the bid; or g) A Bidder who lends, or temporary seconds, its personnel to firms or organization which are engaged in consulting services for the preparation related to the procurement for or implementation of the project, if the personnel would be involved in any capacity on the same project. 3. That I am making this statement in compliance with the bidding requirements of the Department of Public Works and Highways, Misamis Oriental First District Engineering Office, Gingoog City for the above-stated project. IN WITNESS WHEREOF, I have hereunto set my hand this __________ day of ________________ 2011 at __________________, Philippines.
_____________________________________ Bidders Representative/Authorized Signatory REPUBLIC OF THE PHILIPPINES) CITY OF __________________ ) S.S SUBSCRIBED AND SWORN to before me this ______ day of _____________ 2011, affiant exhibited to me his/her Community Tax Certificate No. ____________________ issued on ________________ at _______________________. Doc. No. ________ Page No. ________ Book No. ________ Series of 2011.