Estimating Guide Sample Chapter
Estimating Guide Sample Chapter
Estimating Guide
For Project, Programme and Portfolio Managers
Contents
Table of Figures v
Foreword vi
Acknowledgements vii
Purpose and reason for this guide viii
Estimating framework x
1 Developing the estimating plan 1
1.1 Stakeholder engagement and mobilisation 1
1.1.1 Stakeholder commitment 1
1.1.2 Responsibility assignment matrix (RAM) 2
1.1.3 Interpretation of stakeholder objectives and targets 2
1.2 Understanding the estimate scope 2
1.2.1 Scoping the estimate 2
1.2.2 Understanding the estimate maturity requirements 5
1.3 Manage the information requirements 6
1.3.1 Identifying the information requirements 6
1.3.2 Storing information 7
1.3.3 Reviewing the maturity of the information available 7
1.3.4 Revising the ADORE in line with information
maturity risk 8
1.3.5 Data normalisation 8
1.4 Prepare the estimating plan 9
1.4.1 Agreeing the estimating approach(es) to be used 9
1.4.2 Agreeing the competency requirements of the team 9
1.4.3 Agreeing the schedule of estimating activities and
project dependencies 9
1.4.4 Updating the estimating RAM 10
1.4.5 Defining the toolsets and information communication
media 10
2 Creating the base estimate 11
2.1 Estimate management 11
iii
Contents
iv
Table of Figures
v
Foreword
Estimation and its diligent application within any project is one of the cornerstones
of successful project delivery. This guide has been created to assist the current
and next generation of project stakeholders to understand the core values,
information sets and underpinning knowledge that, if applied diligently, will
improve the clarity and robustness of an estimate, informing the organisation
with transparency and clarity and supporting better decision making.
The Association for Project Management (APM) and the Association of Cost
Engineers (ACostE) have collaborated to bring this guide to you. All the
collaborators have an excellent understanding of the challenges faced when
generating an estimate that is fit for purpose, having had the experience of real-life
situations where good estimates made the difference in delivering the project, and
a burning desire to share their combined knowledge for the benefit of all.
vi
Purpose and reason for
this guide
viii
Purpose and reason for this guide
ix
Estimating framework
x
2
11
Estimating Guide
12
Estimating framework
can still be useful throughout the life cycle of a project, e.g. for validation
purposes.
The main benefit of working at a higher level is that there is a tendency to
use more holistic data from previous projects or products, including unmitigated
and unforeseen risks, and scope creep. This can reduce the risk of emerging
work activities or costs being overlooked. As a result, top-down estimates are
typically greater than those created by a bottom-up approach.
Base estimates created by a top-down approach should exclude consideration
of additional risks and opportunities. These should be considered separately by
either a top-down or bottom-up approach as part of the formulation of the project
baseline estimate. See section 3.
It is considered good practice to express an uncertainty range around a
top-down estimate, based on the maturity of the information available, and the
estimating methodologies employed. According to the NAO survival guide to
challenging costs in major projects, (National Audit Office, 2018) “Early cost
estimates should be presented as a range and never a point estimate”. Note that
APM and ACostE believe this should apply to all cost estimates.
13
3
23
Estimating Guide
24
Estimating framework
Lognormal distribution:
This distribution can be used in reliability analysis to model the repair time of
items, in particular in relation to the fatigue-stress characteristics of
mechanical systems. It is often an empirical distribution observed in natural
growth or human behaviour systems. When a variable is deemed to be
lognormally distributed in linear space, its values will be normally distributed
in logarithmic space. As a consequence, the scatter or deviation of values
around a power or exponential cost estimating relationship is expected to be
lognormally distributed.
Triangular distribution:
Uniform distribution:
25
6
Ethics in estimation
The estimating codes of conduct lay down the behaviours we would like to see
from both the estimator and the customer of those estimates. The customer is
defined in this guide as the person who asks for the estimate: project manager,
chief engineer, etc.
All professional bodies have a code of conduct which their members are expected
to follow. These include, but are not limited to:
47
Glossary
The terms in this glossary represent the views of both APMBok (APM, 2019),
ACostE and the authors of the guide.
3-point estimate/ [APM] An estimate in which optimistic best case, pessimistic worst
three-point case and most likely values are given.
estimate [ACostE] A three-point estimate represents three cases produced by
estimating. Some organisations (and this guide) refer to these as the
minimum, the most likely and the maximum.
The three-point estimating technique is used for the construction of
an approximate distribution representing the uncertainty of future
events; this will ensure the estimate is credible.
Accuracy The correctness of an estimate. This can be measured as the
percentage error between the estimate and actual. In the case of
3-point estimates, an estimate is considered accurate if the actual
cost/schedule lies inside the estimate uncertainty range.
ADORE Assumptions, dependencies, opportunities, risks, exclusions
(Shermon D, 2017)
Assumptions A statement that is taken as being true for the purposes of estimating,
but which could change later. An assumption is made where some
data is not available or facts are not yet known.
Baseline The reference levels against which a project, programme or portfolio
is monitored and controlled.
Bottom-up [APM] An estimating technique that uses detailed specifications to
estimating estimate time and cost for each product or activity. Also known as
analytical estimating. This should not be confused with the
‘Estimating Method of Estimating by Analogy’ (Section 2.3.1).
[ACostE] An approach to estimating all individual work packages or
activities with appropriate level of detail, which are then rolled up to
higher-level estimates. The accuracy of bottom-up estimating is
improved when individual work packages or activities are defined in
more detail. See section 2.2.2.
49