How To Estimate The Resources of A Project
How To Estimate The Resources of A Project
Knowing how to estimate the resources required to carry out a project is never the simplest
of tasks.
CONTENTS
Resource estimation
Estimation of activities’ duration
Project planning and critical roadmap
Resource equalization
Resources are people, equipment, places, money or anything else a project needs to be executed.
As a result, resources must be allocated for each activity on the to-do list.
Before you can assign resources to the project, however, you need to know their availability.
Some resources need to be scheduled in advance and may only be available at certain times or
times – for example, a room for a kick-off meeting or a rented office.
It is therefore essential to know this before you can finish programming a project.
Resource estimation
The objective of the resource estimate is to allocate the necessary resources to each activity on
the list.
There are five tools and techniques for estimating activity resources:
1. The judgement of experts: this means involving experts who have already performed
this type of work before and obtaining opinions on what resources are needed.
2. Alternative analysis: this means considering different options on how to allocate
resources. This includes changing the number of resources and the type of resources
used. Many times, there is more than one way to perform a task, and alternative analysis
helps you decide between different possibilities.
3. Published estimation data: something that project managers in many industries use to
understand how many resources they need for a specific project. These are based on
articles, research and studies that collect, analyze and publish data from other people and
organizations’ projects.
4. Project management software: these often feature functions designed to help project
managers estimate resource needs and constraints and find the best combination for the
project in question.
5. The bottom-up estimate: this means splitting complex tasks into simpler tasks and
processing the resources needed for each small step. The need or cost of the resources of
the individual tasks is then added together to obtain a total estimate. The smaller and
more detailed the task, the greater the accuracy of this technique.
Once you have finished estimating resources per activity, you have everything you need to
understand how long it will take to complete each activity.
Estimating the duration of a task means starting with information about that specific task and
then working with the project team to develop a time estimate.
Here are the five tools and techniques to create more accurate durability estimates:
1. The evaluation of the experts that will come from the members of the project team who
are familiar with the work that needs to be done.
2. The equivalent estimate, i.e. when looking at similar activities from previous projects
and how much time they took.
3. Parametric Estimation, i.e. linking the project data into a formula that provides an
estimation.
4. The three-point estimate, i.e. when three numbers come up: a realistic estimate that is
more likely to occur, an optimistic estimate that represents the best scenario and a
pessimistic estimate that represents the worst scenario. The final estimate is the weighted
average of the three.
5. The Back-up Analysis, i.e. adding extra time to the program (called emergency reserve
or buffer) to take account of additional risk.
Activity duration estimates are a quantitative measure usually expressed in hours, weeks, days
or months.
Another thing to keep in mind when estimating activity duration is to determine the effort
required.
Duration is the amount of time an activity takes, while effort is the total number of people-hours
required.
If, for example, two people work a total of 6 hours (3 hours one and 3 hours the other) to
complete an activity, the duration is six hours. However, if these two people worked the whole
time (simultaneously, for 6 hours), the duration would be 12 hours.
This ensures that everyone is familiar with the program, including dates and resource
commitments.
In addition, (written) confirmation will be required that resources will be available as indicated
in the planning.
The progress of the project and the completion of activities will be monitored compared to
project planning to determine if the project is running as planned.
Resource balancing
Resource balancing is used to examine and resolve the unequal use of resources, usually related
to people or equipment, over time.
During the execution of project planning, the project manager will attempt to plan certain
activities simultaneously.
As the project progresses, however, there are situations where more resources – such as
equipment or people – may be needed than are available and planned.
The project manager will attempt to schedule certain tasks at the same time as the project is
progressing.
When using project software, resource equalization can take place automatically, allowing the
software to calculate delays and automatically update tasks.
The project manager offers several tools for the development of good quantitative information,
based on numbers and measurements, such as project schedules, financial and budget reports,
risk analysis and objective monitoring.
This quantitative information is essential to understand the current status and trends of a project.