DDD
DDD
DDD
Tie brick
A.
Half brick
B.
Quoin brick
C.
Queen closer
D.
Bricks
A.
river sand
B.
cement
C.
crushed stone
D.
SECTION B………ANSWER
H
I
a)
Name the type of platform shown and state its function. [2]
b)
At what height is the platform erected? [1]
c)
Which three things are supported by the platform? [3]
d)
Redraw the diagram and label the parts indicated by the arrows [11
e)
Name three different materials from which the platform is made.
[3]
40. Draw elevational diagrams (4 courses) or plan diagrams (2 courses) to illustrate the
following types of bonds.
a) Stretcher bond [6]
b) English bond [6]
c) English garden wall bond [6]
d) Define the term ‘bonding’. [2]
41. A brick wall is 10m in length and 3m high. The wall has a window opening measuring
1.5m by 0.9m.Calculate the following:
a) Area of wall [3]
b) Area of opening [3]
c) Actual area of brickwork
[4]
d) number of bricks required to build the wall at 110 bricks per square metre.[4]
e) Volume of bricklaying mortar at 0,5m3 per 1000 bricks [2]
f) Time taken to build the wall if a bricklayer builds 600 bricks per day [2]
42. A concrete slab measures 7m in length, 4,5m in width and 0,1m depth. Using a mix
ratio 1:3:6,calculate the following aspects:
a) Compacted (solid) volume of concrete. [2]
b) Loose (dry) volume of concrete. [3]
c) Volume of cement [2]
d) Number of cement bags [2]
e) Volume of river sand [2]
f) Volume of stones [3]
g) Volume of cement [3]
3
h) Number of cement bags if a bag has a volume of 0,035m [3]
a)